Concor Infrastructure completing major works for Exxaro’s new Belfast digital coal mine

Concor Infrastructure is building dams, roads, platforms and other works at Exxaro’s new digital coal mine near Belfast in Mpumalanga province. At work since October 2017, Concor Infrastructure is constructing four major dams, 26 concrete platforms and terraces, 37 internal roads of 16 km in length, and the upgrade of almost 13 km of provincial roads, among other aspects of the mine.

According to Concor Infrastructure contracts manager Pierre van Vuuren, dams are being lined with both a geosynthetic clay liner (GCL) and high density polyethylene (HDP) sheets, in compliance with the water use licence and related environmental regulations. Various structures around the dams are also being installed, including large silt traps, drying beds, inflow chutes to prevent scouring, and spillways and sumps.

Among the concrete platforms and terraces are two primary crusher bases being built for the run-of-mine crushing facilities. The various structures being built by Concor Infrastructure on the mine will demand almost 350 t of steel reinforcing, and nearly 2,700 t of bulk cement. Other inputs will be around 15,000 t of 19 mm aggregate and nearly 13,000 t of crusher sand.

Extensive upgrading is being done on the D1770 and D1110 provincial roads – for the transport of coal to the rail siding – including eight major culverts under the roadway. For all the project’s road works, almost 9,5 km of subsoil drains is to be installed, as well as 2.7 km of stormwater culverts. G5 and G6 construction material comes from an external quarry and crushing plant located about 30 km from site towards Carolina.

Contracts manager Mabandla Dlamini highlights the substantial local impact of the project, including the accommodation of a core labour complement of about 180 personnel in the Emakhazeni municipal district. The overall workforce managed by Concor Infrastructure, with contractors, totals closer to 700 – who are all transported 30 km daily by the local taxi network.

Dlamini also points out that various subcontracts are outsourced to local small enterprises, such as drainage, stone pitching, paving, kerbing, fencing, security services and catering. Diesel is also sourced from a local fuel depot in Belfast; the project is expected to consume about 4.3 million litres of diesel in site-wide applications.

Over 150 items of plant and equipment are active on the site, says site agent Sarel van der Berg, with about 40 items such as articulated dump trucks, tippers and graders from local plant hirers.