Galena signs up Contract Power for hybrid power gen facility at Abra JV

Abra Mining Pty Ltd, the joint venture company behind the Abra base metals project, has executed a power purchase agreement (PPA) with Contract Power Australia that could see the construction and operation of a hybrid power generation facility made up of a natural gas and solar energy array at the Western Australia project.

Announcing the PPA, Galena Mining, which owns 77.28% of the project, said Contract Power will build, own and operate an integrated hybrid power generation facility combining a 10 MW natural gas fired power station, a 6 MW solar array, 2 MW of battery energy storage and a 900 Kl LNG storage and regasification facility.

Power will be purchased by Abra under the PPA for an initial term of 16-years (extendable), it said.

Galena Managing Director, Alex Molyneux, said: “We’re pleased to partner with Contract Power on a clean, cost-effective power solution for Abra. Integrating solar with relatively clean natural gas instead of diesel achieves a marked reduction in Abra’s carbon footprint compared to alternatives considered in the tender process.

“Pleasingly, the design also offered the most cost-effective solution, in line with our feasibility study estimates.”

This definitive feasibility study outlined development of a mine and processing facility with a 16-year life producing a high-value, high-grade lead-silver concentrate containing around 95,000 t/y of lead and 805,000 oz/y of silver after ramp-up.

A Western Australia-based company wholly-owned by Pacific Energy Ltd, Contract Power specialises in the design, construction and operation of remote power stations for the mining and government sectors.

Contract Power has operated power stations around Australia under turnkey build-own-operate arrangements since 1999, and recent projects include a 56 MW gas fired power station for Mineral Resources Ltd’s Wodgina lithium project, a 18 MW gas fired station for Capricorn Resources’ Karlawinda project and a 18 MW gas and diesel power station at Wiluna Mining Corp‘s Wiluna gold project.

Contract Power’s Managing Director, Leon Hodges, said: “We are very pleased to be working with Galena on this important project and look forward to rewarding their confidence by delivering a world-class hybrid power station.

“Contract Power’s combined LNG and renewables integration capability has allowed our design team to maximise solar penetration as high as the economics and technology allows, providing the Abra project with the highest reliability and lowest cost of power on an unsubsidised basis.”

The PPA remains subject to the condition of Abra Mining Pty Ltd proceeding to final investment decision for the project, Galena said.