News

Kibali heads for full production: underground mine nears completion and second hydropower station on line

Posted on 20 Apr 2017

The Kibali gold mine’s underground operation, which will significantly increase production, is on track to start commissioning in the third quarter of this year, Randgold Resources Chief Executive Mark Bristow said at a media briefing in Kinshasa this week.

The mine is forecast to deliver approximately 610,000 oz of gold this year, up from 585,000 oz in 2016, but annual production is scheduled to rise to around 750,000 oz from 2018, when the underground operation will make it fully functional.

Bristow noted that Kibali ended 2016 with a creditable performance after having to contend with a range of operational challenges as well as the constraints imposed by limited open pit mining flexibility. In addition to dealing with these issues, the Kibali team succeeded in keeping the underground development on track, successfully constructing and commissioning four ultrafine grind mills in the metallurgy circuit, as well as progressing work on the mine’s second new hydropower station which was commissioned in February this year. The third and last of the new hydropower stations is currently being built by an all-Congolese contracting group.

“Kibali has stayed on course to become one of the world’s great gold mines despite the challenges of last year and the volatile political climate in the DRC at present,” he said.

“Randgold remains committed to the DRC and is confident that its government, politicians and civil society have the will as well as the capacity to work together to secure the country’s future. We therefore continue to invest in exploration here and to lead the way in developing the north eastern DRC as a major new gold mining region.  Our engagement with the country and its people is also evident in our substantial investment in local economic development and community upliftment programmes.  These include macro and micro agribusinesses designed not only to provide regional food security but to generate surplus produce for export.”

It was a source of concern, however, that the DRC government had once again signalled its intention of reviewing the country’s 2002 mining code with the clear intention of maximising state revenue, Bristow said. This could have a very negative impact not only on the mining industry but also on the economy.

“Now more than ever the DRC should be focused on retaining its existing investors and attracting new ones. It’s certainly not the time to harvest more from less for short term gain.  It’s my sincere hope that this time round the government will engage the mining sector fully in the proposed review to achieve an outcome that will be in the best interests of the Congolese economy as well as the country’s mining sector,” he said.

“The existing code is in fact a good one but it is not always being applied effectively and there are still many mining operations that do not operate under the code. There are also a number of issues and challenges which mining companies are having to face which make operating in the DRC more challenging.  In Kibali’s case, these issues include more than $200 million in unpaid TVA and duty refunds.”