Early work at the Gruyere JV (now Gold Fields 50%, Gold Road Resources 50%) began in December 2016, with Gold Fields taking over management of the project on 1 February 2017. The project construction schedule remains unchanged, with engineering progress in line with budget at 72% and construction progress at 32% also in line with plan as at end-December 2017. The Gruyere village, which includes 648 rooms, offices and recreational facilities, was commissioned during H1 2017.
Costs incurred to date are also in line with the project budget, which was slightly increased to A$532 million (100% basis) during H1 2017 following a detailed review of the feasibility study. A$477 million of the total capital cost has been committed and priced, with A$186 million already spent.
The Bulk Earthworks contract was awarded to MACA Civil in May 2017. The 28 km Gruyere main access road and sealed airstrip have been completed, while the pit and tailings storage facility (TSF) areas were cleared during Q4 2017. Construction of the TSF embankment walls is scheduled for completion during H1 2018. The engineering, procurement and construction (EPC) contract for the Gruyere CIL processing plant and the associated infrastructure was awarded to Amec Foster Wheeler Cimvec JV. Construction of the seven carbon-in-leach tanks is progressing to plan. The SAG mill has been delivered while the ball mill components, which are currently in Perth undergoing final inspection, is planned to be delivered in Q1 2018.
During H1 2017, a power supply contract was signed with APA Group, a leading Australian energy infrastructure business. APA has received final approval from the Western Australian Department of Mines for the 198km Yamarna gas pipeline from Laverton, which is scheduled for completion in H1 2018. Civil and structural works have also begun at the 45 MW gas-powered Gruyere plant (build, own, operate model over life), which will be connected to the gas pipeline, and will supply the mine’s energy needs for the life of mine.
The Yeo borefield is planned to serve as the main water source for the Gruyere processing plant. All 32 boreholes have been drilled and installation of the 95km water pipeline to the processing plant has commenced. Installation of the 22 kV overhead power line servicing the borefield is scheduled to commence in Q2 2018. Finally, the mining services contract, which has a cost of A$400 million over a five-year term, was executed with Downer EDI in Q4 2017. Downer began mobilising their workforce during Q1 2018 to begin construction of the mining infrastructure. Mining activities are planned to commence in Q4 2018.
Total project capital of A$311 million (100% basis) has been budgeted for 2018. Gold Fields budget for Gruyere in 2018 is A$181m, which includes items not picked up in the JV such as capitalised interest on the Gruyere debt facility drawn down to fund the project. Gruyere remains on track for first production during Q1 2019.