Metso says Pavlik Gold JSC has chosen it as the supplier for the key crushing and grinding equipment for its ore processing plant in Magadan, Russia.
The Pavlik gold plant, which commenced its operations in 2015, currently produces around 225,000 oz/y of gold. With the new equipment, the plant expects to double its ore processing capacity and increase gold production, according to Metso.
Metso’s delivery consists of the primary crushing station with a Nordberg® C160™ jaw crusher, one SAG mill and two ball mills with a total installed power of more than 20 MW. The circa-€25 million ($27 million) order has been booked in Metso’s March quarter orders received, with delivery expected to take place in the first half of 2021.
Alexey Muzychkin, SVP, Russia and CIS, Metso, said: “We greatly value our long-term cooperation with Pavlik Gold, where Metso’s equipment has been in use already for several years. We are sure that the experience and technical competence of both companies in this type of projects will help us rapidly achieve the goals.”
Earlier this month, FLSmidth announced that it would supply a new 7 Mt/y gold processing plant to the mine.