Full speed ahead for Wiluna Mining sulphide gold project

Wiluna Mining’s board has approved the staged development of its sulphide project at the Wiluna gold operation in Western Australia, enlisting GR Engineering Services to build the 750,000 t/y concentrator required to process the ore.

The development will see the company transition from its current production profile of producing 62,000 oz/y from mining free milling ore through the current 2.1 Mt/y carbon-in-leach processing facility, initially producing 100,000-120,000 oz/y of gold and gold in concentrate.

This will be implemented using the current, recently refurbished crushing circuit, the previously expanded mill circuit and a new 750,000 t/y concentrator by October 2021, the company said. This forms Stage 1 of the project. Wiluna then intends to increase production of gold and gold in concentrate by, at a minimum, doubling the mining rate and the concentrator to produce circa-250,000 oz/y by the end of 2023/early 2024. This is Stage 2.

Of the A$81 million ($58 million) capital cost estimate of the sulphide project, of which around A$20 million has already been committed, the concentrator is expected to cost A$26 million, pre-production underground mine activities/infrastructure development is estimated at A$37 million, drilling comes in at A$9 million and the feasibility study had a A$2 million price tag. A 10% contingency of A$7 million was also calculated.

Wiluna said Murray Engineering has been contracted to supply and maintain mine fleet for current production associated development and stoping, while Byrnecut Contractors have been engaged to provide equipment and personnel for existing development rehabilitation and new development for resource-reserve drill out programs and production from new mine areas.

To complement the current equipment and development work, the first development crew from Byrnecut is expected to be mobilised in the December quarter with further development crews to be mobilised during June 2021 to maintain the required work program, the company said.

GR Engineering has been appointed as the engineering, procurement and construction contractor by Wiluna for Stage 1 works relating to the concentrator development, the engineering firm said, adding that it expects to commence work in early December with commissioning scheduled for October 2021.