Primero banks new work with Fortescue, Rio Tinto and Hazer Group

Posted on 2 Oct 2020

Primero Group says it has recently booked new business totalling some A$55 million ($39 million) with Fortescue Metals Group, Rio Tinto and the Hazer Group as it continues to build out its 2021 financial year contracted order book.

First, it has been awarded the engineering, procurement and construction contract for the Non-Process Infrastructure (NPI) at Fortescue’s Eliwana mine and rail project, in the Pilbara.

Works commenced in late July based on a limited notice to proceed, with the full contract now awarded to Primero following a successful Early Contractor Involvement (ECI) process. The contract includes the complete engineering design, procurement and construction of heavy vehicle workshops and washdown and refuelling infrastructure required for the new Eliwana mine, with works expected to be completed in the 2021 financial year.

Once completed, the $1.275 billion Eliwana project, which includes the building of a 30 Mt/y iron ore processing facility, will maintain Fortescue’s overall production rate of a minimum 170 Mt/y over 20 years.

With Rio Tinto, Primero has been awarded two multi-year Master Service Agreements for NPI and Structural, Mechanical, Piping services across the miner’s Pilbara operational and project locations. The two contracts have an initial term of three years, with an option for a two-year extension. They cover sustaining capital and maintenance projects required over that period across all Rio Tinto Iron Ore Pilbara sites, it said.

The services cover design, procurement and construction activities for engagement under negotiated commercial terms in a “panel style agreement”, according to Primero.

Primero has also been awarded an EPC contract for Hazer Group’s hydrogen/graphene commercial demonstration plant in Western Australia at the Woodman Point Water Treatment Facility.

Hazer is undertaking the commercialisation of the Hazer Process, a low-emission hydrogen and graphite production process. This process enables the effective conversion of natural gas and similar methane feedstocks, into hydrogen and high-quality graphite, using iron ore as a process catalyst, according to the company.

“The full project award has followed a successful ECI process that has extended over the past 12 months,” Primero said. “This process was targeted at developing the technology engineering to the point where a commercial contract could be executed to deliver the project. The project is the first of its kind in the new global renewables energy market and is patented groundbreaking technology in the hydrogen space.”

Alongside this, Primero said it had been awarded the detailed design contract for a 130 km water delivery pipeline and associated pumping stations for the Covalent Lithium Mt Holland project feasibility study in Western Australia.

Primero said its committed order book for the 2021 financial year now stands at around A$285 million.