Anglo American Platinum’s modernisation drive to continue into 2021

Posted on 22 Feb 2021

Anglo American Platinum says it is looking to deliver the next phase of value to its stakeholders after reporting record EBITDA for 2020 in the face of COVID-19-related disruption.

The miner, majority-owned by Anglo American, saw production drop 14% year-on-year in 2020 to 3.8 Moz (on a 100% basis) due to COVID-related stoppages. Despite this, a higher basket price for its platinum group metals saw EBITDA jump 39% to R41.6 billion ($2.8 billion) for the year.

As all its mines are now back to their full operating rates, the company was confident enough to state PGM metal in concentrate production should rise to 4.2-4.6 Moz in 2021.

Part of its pledge to deliver more value to stakeholders was related to turning 100% of its operations into fully modernised and mechanised mines by 2030. At the end of 2020, the company said 88% of its mines could be classified as fully modernised and mechanised.

There were some operational bright spots during 2020 the company flagged.

At Mogalakwena – very much the company’s flagship operation – Anglo Platinum said the South Africa mine continued its journey to deliver best-in-class performance through its P101 program.

Rope-shovel performance improved to 26 Mt in 2020, from 15 Mt in 2019, while drill penetration rates for big rigs increased from 15 m/h, to 16.7 m/h. Alongside this, the company said its Komatsu 930E truck fleet performance improved to 298 t/load in 2020, from 292 t/load in 2019.

These were contributing factors to concentrator recoveries increasing by two percentage points in 2020 over 2019.

During the next few years, the company has big plans to further improve Mogalakwena’s performance.

In 2020, the mine invested R500 million in operating and capital expenditure, which included commissioning a full-scale bulk ore sorting plant, coarse particle rejection project and development of the hydrogen-powered fuel-cell mining haul-truck (otherwise referred to as the FCEV haul truck).

First motion of the 291 t FCEV haul truck is still on track for the second half of 2021, with the company planning to roll out circa-40 such trucks from 2024.

Anglo Platinum said the bulk sorting plant (which includes a Prompt Gamma Neutron Activation Analysis and XRF sensor-based setup, pictured) campaign at the Mogalakwena operation is due to end this quarter.

The company’s hydraulic dry stacking project is only just getting started.

This project, which involves coarse gangue rejection before primary flotation for safer tailings storage facilities, is expected to see a construction start in the June quarter, followed by a campaign commencement and conclusion in the September quarter and December quarters, respectively.

On another of Anglo Platinum’s big technology breakthrough projects – coarse particle rejection for post primary milling rejection of coarse gangue before primary flotation – the company plans to start a campaign in the December quarter of this year and conclude said campaign by the end of the March quarter of 2022.

The company also has eyes on making progress underground at Mogalakwena, with a hard-rock cutting project to “increase stoping productivity and safety” set for Phase A early access works this year. This project is set to involve swarm robotics for autonomous, 24/7 self-learning underground mining, the company said.

Lastly, the company’s said the digital operational planning part of its VOXEL digital platform had gone live at Mogalakwena. VOXEL is expected to eventually connect assets, processes, and people in a new digital thread across the value chain to create a family of digital twins of the entire mining environment, the company says. Development is currently ongoing.

Looking back to 2020 performance at the Unki mine, in Zimbabwe, Anglo reflected on some more technology initiatives related to R26 million of expenditure for a digitalisation program. This included installing underground Wi-Fi infrastructure, as well as a fleet data management system to track analytics on primary production equipment. The company says these digital developments will enhance real-time data analysis, improve short-interval control and overall equipment effectiveness.

To step up mechanisation of its PGM operations at Amandelbult, Anglo American Platinum is also investing in innovation.

This includes in-stope safety technologies such as split panel layouts to allow buffer times between cycles, creating safer continuous operation and reduced employee exposure; improved roof support technology and new drilling technologies; a shift to emulsion blasting from throw blasting; and safety enhancements through fall of ground indicators, 2 t safety nets, LED lights, and winch proximity detection.

Meanwhile, at the company’s Mototolo/Der Brochen operations, it is working on developing the first lined tailings storage facility at Mareesburg in South Africa to ensure zero contamination of ground water. The three-phase approach adopted for construction of this facility will be completed this year.