Nouveau Monde Graphite turns to Metso Outotec for key Matawinie processing equipment

Posted on 29 Jul 2021

Nouveau Monde Graphite has launched civil construction works at its flagship Matawinie graphite mining project in Saint-Michel-des-Saints, Québec, having steadily advanced detailed engineering and engaged in the procurement of key service providers, long-lead equipment and contractors to deliver the project, billed as a “zero-emission mine”, in Québec by the end of 2023.

One of these service providers has been confirmed as Metso Outotec, which has been engaged to supply key mineral processing equipment required for the Matawinie concentrator plant for high-purity graphite flake production.

The agreement with the OEM will support the development of design and integration efficiencies through process equipment chain optimisation objectives, NMG said. It also seeks to promote planning efforts, optimisation of the project cost curve and support the company during the construction, commissioning and operation phases.

“This agreement complements Nouveau Monde’s de-risking strategy and helps ensure a rapid progression of final design elements and construction of the ore processing facility,” the company added.

Following the governmental authorisation of the project in February, Nouveau Monde executed its phased program to initiate preliminary works in March. For the site preparation of the mine industrial platform and the access road connecting the project to the local highway, tree clearing was completed before the nesting season to limit impacts to avifauna.

To protect the environment and the community’s well-being, Nouveau Monde has developed an environmental surveillance and monitoring program to oversee the construction, operation and closure activities of the Matawinie project. Nouveau Monde has hired an environmental coordinator to support construction and environmental monitoring activities on-site and enlisted third-party biologists to conduct inspections for the presence of vulnerable species.

Nouveau Monde is also delivering on its commitment to maximise local opportunities and support service providers by engaging with Atikamekw, local and regional contractors and service providers via dedicated activities related to its construction procurement strategy, the associated business opportunities, as well as health, environment and safety requirements for bidding.

The company has retained mining contractor L Fournier & Fils to build the access road connecting the main Highway 131 to Matawinie’s industrial platform. Works for the 7.8-km access road began in July as part of the company’s 30-month construction and commissioning timeline. Construction of the access road is scheduled to be completed in September 2021 to facilitate subsequent civil works and on-site activities.

Eric Desaulniers, President and CEO of Nouveau Monde, said: “This first milestone kick starts the construction of the Matawinie mine, as we strive to build the high-quality, ethical and sustainable project that can cater to the growing electric vehicle and energy storage markets. We have spent the past months refining our execution plan to carry out engineering, procurement and construction activities safely and with a focus on cost and timeline efficiency. I am confident in the expertise of the technical team that we have assembled, coupled with the support of Tier 1 service providers such as Metso Outotec, L Fournier & Fils and many local contractors, to deliver on our commitments of safety, responsible practices and excellence.”

In the 2018 definitive feasibility study on Matawinie, the mine, scheduled to produce 100,000 t/y of graphite concentrate, was expected to use an electric in-pit mobile crusher and overland conveyor system to feed crushed material to the plant.