Clough works up integrated design layout for TNG’s Mount Peake project

TNG Ltd says an integrated design layout for its flagship Mount Peake vanadium-titanium-iron project in the Northern Territory of Australia has been developed and delivered by Australian engineering and construction company, Clough Projects Australia Pty Ltd.

As announced in October, TNG appointed Clough to work with its project team and SMS group for Mount Peake following a strategic decision to progress a fully-integrated operation at the Mount Peake mine site and given the severe restrictions on travel between Europe and Australia due to the COVID-19 pandemic that have impacted SMS’ ability to deliver a team in Australia.

Clough, together with TNG’s project team, has developed the integrated layout on the basis of the deliverables prepared under the front-end engineering and design study completed by SMS. The layout comprises the beneficiation plant, TIVAN® processing facility and plant utilities located within the mining lease footprint of Mount Peake site.

The integrated plants will be positioned adjacent to the western boundary of the designated mining areas within the company’s existing Mining Lease 29855, which covers an area of 1,460 ha. This area is capable of hosting a fully-integrated operation encompassing mining activities and waste storage, the beneficiation plant, the TIVAN processing facility and non-process infrastructure.

The integrated layout will be “unconstrained” compared with the size and shape requirements at the former Darwin site, TNG said. This offers the potential to capitalise on improving constructability, operability and maintenance for the project, as well as further cost optimisations from integrated infrastructure.

TNG has now commissioned Clough to progress value engineering to optimise outcomes in cost/schedule; and design aspects incorporating, civil, structural and architectural, mechanical, piping, electrical and instrumentation engineering disciplines, logistics and non-process infrastructure.

Clough will work with TNG’s project team and have support from SMS to undertake this next engineering and design stage and deliver an updated capital cost estimate for the development of Mount Peake, with this stage expected to be completed by May 2022.

TNG’s Managing Director and CEO, Paul Burton, said: “The completion of this design paves the way for value engineering and final design work to commence, which in turn will underpin an updated capital cost estimate and pave the way for project finance completion.”

Clough’s CEO and Managing Director, Peter Bennett, added: “We are excited with our ongoing collaboration with TNG on their Mount Peake project as we develop sustainable solutions for the resources sector in Australia. We are proud of our role and long history of delivering world-class engineering and construction projects and critical infrastructure both in Australia and overseas.”

Located 235 km north of Alice Springs, Mount Peake is expected to be a long-life project producing a suite of high-quality, high-purity strategic products for global markets including vanadium pentoxide, titanium dioxide pigment and iron ore fines. The project, which is expected to be a top-10 global producer, has received Major Project Status from the Northern Territory and Federal Governments.