Bellevue Gold tasks GR Engineering with process plant build

Posted on 24 May 2022

Bellevue Gold Limited has awarded GR Engineering Services Limited engineering, procurement and construction (EPC) work related to the 1 Mt/y gold processing plant and associated infrastructure for its namesake project in Western Australia.

GR Engineering will immediately commence design engineering services and ordering of long lead and design critical path equipment including the ball mill, crushing equipment, screens, agitators, leach and tailings thickeners, prior to entering into a formal EPC contract.

Geoff Jones, Managing Director, said: “GR Engineering is pleased to be working with the Bellevue team on this exciting gold project. This project further enhances GR Engineering’s reputation as the leading gold EPC contractor in Australia.”

Bellevue Managing Director, Steve Parsons, said GR Engineering knew the project well from its work during the study phase.

“Commencing manufacturing of these long-lead critical components of our 1 Mt/y processing plant de-risks the construction schedule and puts Bellevue on the pathway to first gold in the second half of 2023.

“The appetite among leading contractors and suppliers to be involved with our project speaks volumes about its strong future.”

Bellevue is forecasting production of 200,000 oz/y during years one to five at an all-in sustaining cost of A$922/oz ($653/oz) at its operation.