Atalaya Mining approves construction of E-LIX-backed processing plant at Riotinto

Atalaya Mining has, following a feasibility study, approved the construction of the first phase of an industrial-scale plant using the E-LIX System to produce high value copper and zinc metals from the complex sulphide concentrates sourced from Proyecto Riotinto (pictured) in Spain.

Following its announcement on October 28, 2020, Atalaya concluded the study, which evaluated the technical and economic viability of producing cathodes from complex sulphide concentrates by applying E-LIX, a new, patented electrochemical extraction process developed and owned by Lain Technologies Ltd.

Relative to conventional flotation techniques, the value creation potential of E-LIX offers a unique opportunity for Atalaya, it said. As a result – and as previously disclosed – the company secured certain terms of exclusivity with Lain Tech for the use of E-LIX within the Iberian Pyrite Belt.

The E-LIX plant will dissolve the valuable metals contained within the concentrates. The test work and system design allows for the dissolution of chalcopyrite while avoiding the passivation of particles. After copper or other metals are brought into solution, they can be recovered by conventional precipitation or solvent extraction followed by electrowinning (SX-EW).

Phase I plant capacity has been designed to produce between 3,000-10,000 t of copper or zinc metal per year depending on the ratio of copper to zinc in the concentrate feed.

The estimated capex for Phase I is €12 million ($13.6 million) and the design allows for unlimited capacity expansion through the addition of multiple lines in parallel. Atalaya will start the construction of the plant in the coming weeks and it is expected to be operational in 2022, including commissioning.

The decision to approve and construct the Phase I industrial-sized plant follows over six years of evaluation and de-risking work including continuous tests at the laboratory, a small pilot plant and finally a semi-industrial pilot plant, Atalaya explained.

A semi-industrial E-LIX pilot plant was constructed in late 2019 and has operated during 2020 and 2021, despite the challenges of the COVID-19 outbreak. The results of the pilot tests were included in the feasibility study and successive optimisation work. The long run continuous tests demonstrated the feasibility of leaching complex polymetallic concentrates with global recoveries of over 95% for copper and zinc while producing clean metal precipitates and/or high purity metals.

Atalaya said the use of the E-LIX System has shown the potential to unlock the significant value from the polymetallic sulphides contained within Atalaya’s mineral resources, including:

  • The polymetallic deposits of San Dionisio, San Antonio, Masa Valverde and Majadales, all of which are located in the Iberian Pyrite Belt and within trucking distance of Proyecto Riotinto’s  15 Mt/y processing facility;
  • The significant contained metal within these historical drilled resources from San Dionisio and Masa Valverde contain over 1.1 Mt of copper, 2.4 Mt of zinc, 1.7 Moz of gold, over 110 Moz of silver as well as additional lead resources. These figures are in addition to the over 1 Mt of copper reserve at Proyecto Riotinto’s Cerro Colorado orebody and at Proyecto Touro; and
  • Historical applications of differential flotation within the Iberian Pyrite Belt in Spain and Portugal have typically resulted in recoveries of 60-80% into concentrates for complex copper-zinc polymetallic sulphides, with even lower recoveries historically reported for lead, silver and gold. The use of hydrometallurgical systems, such as E-LIX, has demonstrated that base metal recoveries of over 90% can be achieved.

E-LIX is, Atalaya said, also expected to reduce Atalaya’s carbon footprint. By producing high-purity metals on-site, Atalaya can reduce the transportation costs associated with delivering concentrates to smelters, avoid treatment and refining charges associated with converting concentrates into metal and eliminate penalties associated with deleterious elements often contained within concentrates produced in the Iberian Pyrite Belt and elsewhere. The E-LIX plant is also expected to use the renewable energy that will be produced by Proyecto Riotinto’s planned solar plant.

Alberto Lavandeira, Atalaya CEO, said: “The E-LIX System offers Atalaya a unique opportunity to unlock significant value from its portfolio of deposits that contain complex polymetallic mineralisation. Atalaya has worked together with Lain Technologies for many years in order to test, refine and demonstrate the E-LIX process, providing the company with confidence in its potential. In addition to enhancing recoveries, E-LIX will eliminate penalties associated with deleterious elements and reduce the costs of transportation and energy, thereby improving the company’s carbon footprint.”

Atalaya Mining evaluating Lain Tech’s E-LIX System for copper cathode production

Atalaya Mining has commenced the execution of a feasibility study to evaluate the economic viability of producing cathodes from complex sulphide ores prevalent in the Iberian Pyrite Belt through the application of a new extraction process called the E-LIX System.

The production of cathodes has the potential to generate cost savings by reducing charges associated with concentrate transportation, treatment and refining, and penalty elements, while also reducing carbon emissions, the company said.

E-LIX System is a newly developed electrochemical extraction process developed and owned by Lain Technologies Ltd, led by Dr Eva Lain, who holds a PhD in Electrochemistry research from the University of Cambridge.

Through the application of singular catalysts and physico-chemical conditions, E-LIX System is able to achieve high metal recoveries under low residence times, by accomplishing rapid reaction rates while overcoming classic surface passivation issues that have typically impaired metal recovery from complex sulphide ores, Atalaya said. E-LIX System is considered to be a more environmentally-friendly process than existing technologies; it generates zero emissions and does not consume water or acid, and runs under mild operating conditions (atmospheric pressure and room temperature).

Patented in 2014 by Lain Tech, the E-LIX System has been developed in collaboration with Atalaya from an initial concept in the laboratory to a fully operational pilot plant located at Proyecto Riotinto, in Spain.

The pilot plant with a capacity of 5 t/d has been running for the past nine months, with only mandatory stoppage owing to COVID-19 restrictions. Leach rates of up to 250 kg/h have been achieved processing copper concentrates, zinc concentrates and blends of different types of sulphides, according to the company. The pilot plant also contains a solvent extraction and electrowinning (SX-EW) section and has successfully produced high purity copper cathodes as a proof of concept.

Excellent leach results with recovery rates well over 90% have been attained, the company said. Fast kinetics for copper and zinc have also been successfully achieved overcoming the well-known passivation problem of leaching primary sulphides.

The pilot plant has demonstrated that the E-LIX System effectively treats the impurity levels typically associated with the complex sulphides present in the pyrite belt that runs through the south of Portugal and Spain and prevalent at Proyecto Riotinto.

During the past five years, Atalaya has provided financial assistance to Lain Tech to develop the E-LIX System and has now reached an agreement with Lain Tech to use its patents, on an exclusive licence basis within the Iberian pyrite belt in Spain and Portugal.

Under the terms of the licence agreement and based on the encouraging operating results at the pilot plant, the company has commissioned a feasibility study to evaluate the construction of an industrial scale plant for the production of a minimum of 10,000 t/y of copper cathode metal. The study at a cost of around €1 million ($1.2 million) will be funded by Atalaya and is expected to be finalised in 2021. The agreement also provides for a profit sharing arrangement between Atalaya and Lain Tech.

“The feasibility study will be based on the results obtained from the pilot plant and aims to confirm the scalability of the E-LIX System and the capital and operating costs of the industrial plant,” Atalaya said. “Should the industrial plant be built, it will be funded and constructed by Atalaya with Lain Tech designing, operating and managing the E-LIX System.”

Atalaya believes that the use of the E-LIX System could potentially be applicable to the large amount of complex sulphide ore inventory present throughout the Iberian pyrite belt, including Atalaya’s mining properties such as Proyecto Riotinto and Proyecto Masa Valverde, it said.

Atalaya CEO, Alberto Lavandeira, said: “We are fortunate to have been given this unique opportunity to work with Dr Eva Lain in the development of the E-LIX System. I believe this system has the potential to play an important role in the economic treatment of many complex orebodies worldwide. We look forward to updating the market on the results of the feasibility study.”

Atalaya Mining looks to solar power for Proyecto Riotinto GHG emission, cost reductions

Atalaya Mining is looking to take advantage of a natural abundance of sunlight at its Proyecto Riotinto copper operation in Spain with the development of a 50 MW solar plant.

The company announced today that it has started the permitting process for the plant build, with the 50 MW generated set to be used for “self-consumption” at the operation.

Technical studies carried out by a third party during the past months have indicated that, in addition to making a significant contribution to reducing carbon emissions, the solar project is economically viable and could potentially contribute to reducing Proyecto Riotinto’s operating costs, Atalaya said.

“The decision to pursue the solar project is in line with Atalaya’s ongoing commitment to environmental sustainability and to continue to have a positive impact on the people, environment and society surrounding the mine,” it added.

During the permitting period, the company will evaluate the various financing options being proposed by industry players in Spain.

Subject to completing the permitting process and securing financing, construction is targeted to commence by mid-2021.

Alberto Lavandeira, CEO of Atalaya Mining, said: “We are pleased to be committing to this solar initiative which will be one of the largest projects of renewable self-consumption in the industry. This is only a first step in achieving our long-term sustainability goals, but one that will have a positive and near term impact on Proyecto Riotinto.”

Earlier this year, Atalaya Mining completed an expansion of the operation to hit 15 Mt/y, up from the previous rate of 9.5 Mt/y.