Foran Mining drafts in G Mining Services for McIlvenna Bay project build

Foran Mining has selected G Mining Services (GMS) as its partner in the formation of the integrated project management team (IPMT) for construction of its 100%-owned McIlvenna Bay Complex in Saskatchewan, Canada.

Founded in 2006, GMS is a mining consultancy firm excelling in both underground and open-pit mining and processing projects, including operations in Canada. It has a range of services spanning greenfield projects to mine operation, with notable work carried out on Lundin Gold’s Fruta del Norte project in Ecuador, Newmont Mining’s Merian Mine in Suriname, the Greenstone project in Ontario and the Tocantinzinho project in Brazil.

Foran says GMS has achieved a remarkable 100% success rate in delivering projects on or below budget.

Dan Myerson, Foran’s Executive Chairman & CEO, said: “G Mining Services is the ideal partner to deliver the McIlvenna Bay Complex into production and unlock this meaningful critical minerals district. GMS’ unique and innovative IPMT model enables a harmoniously aligned construction team seamlessly transitioning into an operating team, which is critical to success. Integrating GMS within our ranks provides the support and accountability needed in delivering safe, on-budget, and on-schedule mine construction. Their expertise, unwavering commitment to safety, and dedication to timely and fiscally prudent project delivery are expected to play an instrumental role into McIlvenna Bay’s development.”

Mathieu Gignac, President of G Mining, added: “We consider ourselves fortunate to partner on projects that align with our expertise and with people who align with our values. The opportunity to work with Foran, be an integral part of their team and contribute to the development of McIlvenna Bay brings us great excitement, particularly as McIlvenna Bay becomes Saskatchewan’s pioneering base and precious metals project. Our involvement not only emphasises our commitment to delivering excellence but also highlights our role in bolstering Canada’s critical minerals sector.”

In line with this transition, Gilbert Lamarche, previously Vice President, Technical Services, has been promoted to Chief Operating Officer. David Bernier, former COO, will continue to play a role within the company, leveraging his contributions in de-risking, building and growing the project and advancing key strategic initiatives, the company says. Sam Renelli has been promoted from Operational Readiness Manager to the position of Vice President, Technical Services.

The 2022 feasibility study on McIlvenna Bay outlined a 4,200 t/d operation over an 18.4-year mine life, able to produce an average annual production of 33,000 t of copper-equivalent output over the first 15 years of mine life. By individual metal, this equates to 17,600 t of copper, 28,900 t of zinc, 20,000 oz of gold and 486,000 oz of silver.

Foran Mining assembles FS team for ‘world first’ carbon neutral copper mine project

Foran Mining says it has bolstered the design team for its ongoing definitive feasibility study at the McIlvenna Bay project, in Saskatchewan, Canada, providing the company with the technical expertise to execute on its strategy of building the world’s first copper mine designed to be “carbon neutral” from day one of production.

The advisors are anticipated to employ a range of technologies and initiatives in the design of the mine and processing facilities to materially reduce greenhouse gas emissions and the environmental impact of the operations.

Foran says its due diligence to date has highlighted the potentially superior returns achievable through implementing this strategy, while the use of battery-electric vehicles will also be safer for employees, reducing risk of injury and physical stressors, such as vibration and noise.

The FS team includes experts from:

  • Stantec – mine design and engineering;
  • Knight Piésold Ltd – tailings storage facility design;
  • Halyard Inc – process plant design;
  • Micon International Limited – resource estimate;
  • Base Metallurgical Laboratories Ltd – metallurgical testing;
  • Canada North Environmental Services Ltd – environmental; and
  • Synergy Enterprises – sustainability and carbon accounting

Dan Myerson, Executive Chair of Foran, said: “The appointment of these world-class environmental and engineering specialists reflects our ambition to develop a technically and economically compelling solution to the environmental and social challenges which have been traditionally associated with the sector. We are therefore thrilled that professionals of this calibre have agreed to support us on this journey.”

He added: “Together, we intend to ensure that our operations emit net zero greenhouse gases and set new safety benchmarks for the industry, while also ensuring that the local community and the broader Canadian population benefit from our operations. The responsible production of copper and zinc is critical as the world transitions to a low carbon future; these metals are used in the production of renewable energy assets and electronic industries, for example. We look forward to providing more updates, in relation to our infill and expansion drilling, as well as announcing more detailed plans about how we will be putting our ambitions into practice.”

The 2020 prefeasibility study on McIlvenna Bay envisaged a 3,600 t/d underground operation with on‐site crushing and mineral processing facilities, a paste plant and filtered tailings storage facility. It considered a nine-year life of mine and scheduled treatment of the full reserve of 11.34 Mt grading 4.01% Zn, 1.14% Cu, 0.54 g/t Au and 20.97 g/t Ag. It also included plans for McIlvenna Bay to be an early adopter of battery-electric haul trucks.

Foran recently commenced its largest drill program ever (pictured), with over 30,000 m of infill and expansion drilling in the deposit. This has been designed to maximise the conversion of the current inferred resource to the indicated resource category, which can then be interrogated for inclusion in the updated reserve statement.

Foran says the feasibility study will, among other things, look to:

  • Further optimise and detail the McIlvenna Bay project engineering, including the estimation of reserves, mine design, stope sequence, development and production schedules;
  • Refine power and equipment requirements to support the company’s commitment to carbon neutral operations;
  • Update and detail the design and feasibility of the tailings desulphurisation process, dry stack storage facility and cemented paste backfill processes;
  • Provide detailed construction scheduling, including optimisations that would arise from pre-fabrication and/or modular (off-site) construction to the greatest extent possible;
  • Identify further mine optimisation to increase productivity and reduce operational expenditures; and
  • Consider equipment usage and activities where greenhouse gas emissions can be eliminated, reduced or offset to ensure that McIlvenna Bay is a carbon neutral operation.