Orezone Gold Corp’s Bomboré gold project is to become the first mine in Burkina Faso to use LNG to power its operations after the Vancouver-based company signed a Power Purchase Agreement (PPA) with Genser Energy Burkina SA for the supply of “clean energy electrical power” to the project.
Under the PPA, Genser will use liquefied natural gas (LNG) as its main fuel, augmented with a staged solar plant, Orezone said. A fixed rate energy tariff will apply over the life of mine oxide operation with a fixed rate tariff to be negotiated for the additional energy demand upon commissioning of the sulphide processing circuit expected in Year three of commercial production.
The power plant will consist of 6 2.5 MW LNG generators with four 2.6 MW diesel back-up units. This configuration is sized for the initial oxide operation and the planned sulphide expansion, the company explained. At the same time, a solar photovoltaic plant, up to 14 MWp, is to be installed in stages with an 11 kV powerline to connect the gas and backup diesel generators, and solar plant.
Genser is to design, permit, finance and install all power generating equipment and associated infrastructure including LNG storage and diesel storage terminals. It will also be the operator and owner of the power plant facility.
Patrick Downey, President & CEO of Orezone, said: “We are extremely excited to be the first mine in Burkina Faso to use a LNG and solar hybrid power supply. Besides being an excellent cost-effective choice for Bomboré, we also see this new power solution as being a very positive step for the Burkina Faso mining and electricity generating sectors. LNG power systems, coupled with solar, will enable energy intensive industries such as mining to reduce fuel consumption, decrease energy costs, and significantly cut greenhouse gas emissions.”
He added: “This life of mine fixed cost agreement for clean energy from Genser provides power cost certainty over life of mine oxide production at Bomboré and provides an excellent platform for project expansion and growth.”
The Honourable Dr Bachir Ismael Ouedraogo, The Minister of Mines and Energy for Burkina Faso, said: “Having the first LNG plant at a mining operation is a great step forward for the industry and we congratulate Orezone in this regard. As a government, we continue to support clean energy alternatives that provides a platform for sustainable growth and benefits our communities.”
Alongside the announcement of the PPA, Orezone said that significant progress had been made at Bomboré during the first two quarters of the year. Engineering is now approximately 30% complete and on schedule, with design and bulk quantities from this work trending favourably against the quantity estimates used in the 2019 feasibility study.
Procurement is well advanced with firm orders placed for most mechanical and electrical equipment with purchase costs generally below budget estimates, it added.
In January, the company appointed Lycopodium Minerals Pty Ltd as the project’s EPCM contractor, while, in February, Sila Equipement ET BTP SA was named as its open-pit mining contractor.
Meanwhile, bulk materials including concrete reinforcing bar and embeds, CIL tank platework, structural steel and platework, HDPE liner, and overland piping have also been ordered with costs also trending within budget, Orezone said.
Off-channel reservoir mining, earthworks for the plant site area and tailings storage facility are rapidly advancing, and the award of the contracts for concrete installation and CIL tank erection and overland piping are imminent, it added.
Orezone’s 2019 feasibility study on Bomboré envisaged a 5.2 Mt/y throughput operation able to produce, on average, 117,760 oz of gold over a 13-year mine life where both oxide and sulphides would be mined and processed. The project remains on track for first gold pour in the September quarter of 2022.