Tag Archives: George Ogilvie

Arizona Sonoran Copper hires Ausenco for Cactus and Parks/Salyer project PFS

Arizona Sonoran Copper Company says it has engaged Ausenco as lead engineer to deliver an integrated prefeasibility study (PFS) at the Cactus and Parks/Salyer project, in Arizona, USA, by early 2024.

The project, on private land, is a brownfields site with in-place infrastructure and is accessible via highway.

Additionally, the company is pleased to announce the appointment of Victor Moraila as Chief Engineer, joining as the company transitions into a US-based copper developer.

Ausenco will initially review the Cactus draft PFS and incorporate into the new re-scoped PFS, which includes Parks/Salyer. The study will explore a simple heap leach operation, targeting a potential of 50,000 tons (45,359 t) per annum of LME Grade A Copper Cathode from an on-site solvent extraction/electrowinning (SX/EW) plant.

Mineralised material will be sourced from four deposits initially, including Stockpile, Cactus East, Parks/Salyer and Cactus West.

Pending a successful metallurgical program with Rio Tinto’s Nuton Technologies, and a subsequent commercial agreement, the company and Ausenco will layer in the primary sulphides as a fifth source of mineralised material for the SX-EW plant.

Back in July, Arizona Sonoran announced it had entered into a one-year exclusivity period with Nuton™, a Rio Tinto Venture that, at its core, is a portfolio of proprietary copper leach related technologies and capability. The sulphide potential is not included in the 2021 Cactus preliminary economic assessment, which contemplated a simple heap leach and SX-EW operation over an 18-year mine life, producing an average of 28,000 t/y of LME Grade A copper cathode.

In addition to its own technical staff, Ausenco will lead a technical consultant team comprised of Samuel Engineering, AGP Mining Consultants, Stantec, MineFill Services, Clear Creek Associates and Call & Nicholas Inc.

As part of the PFS work for the project, the company and Ausenco have agreed to complete trade-off and optimisation studies and detailed mine production scenario analysis, in conjunction with AGP Mining, around the following areas:

  • Mineralised material sources from an open-pit expansion (Cactus West), underground development (Cactus East and Parks/Salyer), and the existing stockpile;
  • Ore handling, storage, and agglomeration;
  • Leach pad design and operation;
  • Acid storage, consumption and handling;
  • Solvent extraction and electro-winning;
  • Existing and new infrastructure (as required);
  • Preliminary design of access roads in coordination with mine access roads;
  • Preliminary design and location of mine support facilities; and
  • Mine and geotechnical design.

A PFS detailing the oxide and enriched mineralised material is projected to take approximately 10 months to complete, with results currently expected in the December quarter of 2023. Based on the results of current metallurgical testing with Nuton, layering in the primary sulphide material into the mine plan would extend delivery into early 2024.

George Ogilvie, ASCU President and CEO, said: “As Arizona Sonoran Copper Company emerges as a mid-tier copper developer, we are thrilled to welcome the depth of experiences of both Victor and Ausenco; each rooted in quality and value-driven projects. Looking forward, Arizona Sonoran Copper Company is bolstering the technical services team, necessary team to deliver domestically produced copper into the US copper supply chain, from the third largest independent copper deposit in the US.”

Rio Tinto signs pact to test Nuton copper heap-leach tech on Cactus primary sulphides

US-based copper developer and near-term producer, Arizona Sonoran Copper Company Inc, has entered into a one-year exclusivity period with Nuton™, a Rio Tinto Venture that, at its core, is a portfolio of proprietary copper leach related technologies and capability.

The exclusivity was triggered by successfully modelling the Cactus and Parks/Salyer ore samples and achieving the previously contemplated indicative metallurgical recoveries of at least 72% (copper recovery to cathode), which included chalcopyrite, under an investor rights agreement, Arizona Sonoran said.

Nuton will continue to test the application of its copper heap-leach related technology to the primary sulphide component of the Cactus Mine and Parks/Salyer Projects, in Arizona, through column leaching and scoping out capital and operating costs and design parameters, it added.

The sulphide potential is not included in the 2021 Cactus preliminary economic assessment, which contemplated a simple heap leach and SX-EW operation over an 18-year mine life, producing an average of 28,000 t/y of LME Grade A copper cathode.

Within the current Cactus project resource base is a primary sulphide mineral resource of 77.9 million short tons (70.7 Mt) at 0.35% CuT (indicated) and 111.2 million short tons at 0.35% CuT (inferred).

George Ogilvie, Arizona Sonoran President and CEO, said: “The Nuton preliminary work results indicate optionality for unlocking the substantial primary resource at Cactus, which is currently stranded at the bottom of the pit. Although we are in the early stages of testing chalcopyrite recoverability on an economic basis, we are encouraged by the initial results and the significant potential to continue building scale at Cactus and potentially at Parks/Salyer in the longer term.”

The preliminary metallurgical testing program covered ore sample selection, preparation and mineralogical characterisation to produce CFD modelling results providing early-stage indicative recoveries in respect of various ore types and specifically the chalcopyrite ore at Cactus. Further test work underway covers test column leaching and scoping out capital and operating costs and design parameters, the company said.

Nuton is an innovative new venture that aims to help grow Rio Tinto’s copper business. At its core is a portfolio of proprietary copper leach related technologies and capability – a product of almost 30 years of research and development. The Nuton technologies offer the potential to economically unlock known low-grade copper sulphide resources, copper bearing waste and tailings, and achieve higher copper recoveries on oxide and transitional material, allowing for a significantly increased copper production outcome, according to Rio. One of the key differentiators of Nuton is the potential to deliver leading environmental performance, including more efficient water usage, lower carbon emissions, and the ability to reclaim mine sites by reprocessing mine waste, it claims.