Tag Archives: Gordon Stothart

Wood to deliver EPCM contract at IAMGOLD’s Côté Gold project

Wood, the global engineering and consulting company, has confirmed it will deliver the engineering, procurement and construction management (EPCM) contract for the $1.3 billion Côté Gold open-pit mine for operator IAMGOLD Corp, supported by JV partner Sumitomo Metal Mining.

Côté is a world-class deposit located in northern Ontario, with estimated contained gold reserves of over 7 Moz. IAMGOLD wants to develop the site to be a model of a modern Canadian mine as it seeks to efficiently unlock the reserves, with Wood providing EPCM services for the project. This project is anticipated to generate over 1,000 jobs during construction and 450 during operations.

Dave Lawson, President, Mining & Minerals at Wood, said: “This project strengthens our relationship with IAMGOLD as a trusted full life cycle delivery partner and it solidifies Wood’s position as a global leader in the development of gold mines.

“Beginning with work on the initial scoping study in 2011, we have worked closely with IAMGOLD to guide the project toward successful execution, helping to identify more than $450 million of improvements in net present value. We were able to do so because of our unrivalled expertise in gold extraction technology having worked on some of the largest and most technically complex gold projects in the world.”

Over the last eight years, Wood has been working with IAMGOLD in every aspect of the project, adding, it says, value at every stage with innovative design and project delivery solutions. Wood’s latest scope of work includes engineering, procurement and construction management for the 36,000 t/d conventional gold processing plant, tailings and water management.

Gordon Stothart, President and CEO of IAMGOLD, said: “We are pleased to move to construction on the Côté Gold Project with our long-time engineering partner Wood. We look forward to bringing this project from concept to reality with their team.”

The Côté project is expected to expand IAMGOLD’s production profile for future growth, by bringing greater geographic diversity and a reduction in costs – enabling sustainable reserve growth and supply stability as demand factors shift in an uncertain environment, Wood said.

Construction of the gold mine commenced in late 2020, and is expected be completed in mid-2023. It is expected to leverage both autonomous drilling and haulage technology.

IAMGold weighs autonomous drilling, haulage at Côté gold project

IAMGold has provided an update on its majority-owned Côté gold project in Ontario, Canada, which included confirmation of a key approval and the mention of studies on implementing autonomous haulage and drilling technologies.

The late 2018 feasibility study on the project demonstrated its potential to produce 460,000 oz/y of gold at all-in sustaining costs of around $700/oz for the first six years of a 16-year mine life.

It said this week that the project has received approval for its application under Section 36 of the Fisheries Act (Canada). This is a key milestone in attaining permits relating to impacts on fish habitats and tailings management, according to the company.

Since the feasibility study was published in late 2018, IAMGold says it has been very active in “de-risking” the project.

As of the end of May, the company says it has:

  • Completed additional resource and geotechnical studies, and advanced mine planning;
  • Completed over 60% of detailed project engineering, including the tailings facility;
  • Following this level of engineering, obtained firm bids and secure prices on all major equipment. To date, 55% of project cost has firm pricing, further reducing technical and cost risks for the project leading to a refinement in costs and metrics as IAMGold works toward a construction decision;
  • Completed a pre-construction camp on the adjacent Chester site;
  • Completed all tree clearing needed for initiating construction – work was carried out with a First Nations partner firm earlier in 2020, before standing down in respect of the COVID-19 pandemic;
  • Carried out detailed implementation studies on technology, including automated truck haulage and drilling, and commenced discussions with regulators regarding the use of automated equipment;
  • Advanced development of construction protocols in consideration of COVID-19; and
  • Completed 4,700 m of drilling at the Gosselin Zone, a potential satellite pit 1.5 km northeast of Côté.

The company has also signed Impacts and Benefits Agreement with First Nations partners, approved the Environmental Assessment and Closure Plan, and advanced permitting.

The 2018 feasibility study envisaged a truck-shovel operation, assuming 220 t autonomous trucks and 34 m3 shovels, and a 36,000 t/d mineral processing circuit incorporating primary crushing, secondary crushing, tertiary high pressure grinding roll crushing, ball milling, vertical stirred milling, gravity concentration and cyanide leaching, followed by gold recovery using carbon-in-pulp, stripping and electrowinning.

Gordon Stothart, IAMGold President and CEO, said: “A key part of the future of IAMGold is our organic growth pipeline, starting with the Côté Gold Project in northern Ontario.

“The transformative impact of Côté Gold on IAMGold’s production profile and global cost structure, in addition to its long mine life in an attractive jurisdiction, establishes clear and compelling reasons for this project to proceed.

“Our current financial position supports our proposed growth plans, with over $800 million in cash on hand, access to a currently undrawn $500 million committed revolving credit facility, and expected stronger operating cash flows from our current mining operations, including anticipated contributions from Saramacca at Rosebel and steady performance from Essakane and Westwood.”

A formal decision on the construction of the Côté Gold Project will be made in conjunction with IAMGold’s partner, Sumitomo Metal Mining, given a satisfactory environment for construction to proceed with appropriate work protocols in light of COVID-19 and without risk of interruption.

IAMGold said: “The company is currently working with SMM toward a formal decision. A decision in the coming months would allow construction to commence later this year with a targeted completion date of mid-2023.”