Tag Archives: haul roads

MICHELIN BETTER HAUL ROAD to up the haul road monitoring ante

Michelin has collaborated with three mines around the world to develop MICHELIN BETTER HAUL ROAD, a digital solution designed to enhance safety and efficiency in mining operations.

The importance of well-maintained haul roads cannot be overstated. MICHELIN BETTER HAUL ROAD provides a solution that allows mine managers to keep a close eye on this critical infrastructure. By monitoring haul roads in real time, operators can swiftly identify incidents such as debris or road damage that may arise. The system then allows them to register the issue within the app or through dispatch with the web, track its status via the app or web, and efficiently assign a repair team to address and resolve the problem.

“With MICHELIN BETTER HAUL ROAD, mine operators gain peace of mind through improved safety, prioritised actions, and streamlined team coordination, driving better haul road conditions,” Christel Dubus, Head of Mining Digital Services for Michelin, said. “With features that allow for task prioritisation and seamless follow-up for teams or contractors, as well as improved operator recognition, it supports the continuous evolution of a mine’s pit and its goal of achieving higher speed and production with lower energy consumption and improved haul road quality.”

MICHELIN BETTER HAUL ROAD allows prioritisation of data-driven actions and supports a mine’s constant pit evolution with cleaner haul road conditions.

“This proactive approach to haul-road management ensures that any issues are quickly resolved, minimising downtime and maintaining the flow of operations while considering opportunities to reduce fuel and energy consumption,” Dubussaid . “By continuously monitoring haul-road conditions, MICHELIN BETTER HAUL ROAD helps ensure the longevity and reliability of these crucial transportation routes, ultimately supporting the overall efficiency and safety of mining activities.”

Concor Infrastructure closes in on Khoemacu copper-silver project milestones

Concor Infrastructure says it is nearing completion of a 35 km access road for the Khoemacau Copper Silver Starter project in the Kalahari region of Botswana.

The company is at the same time also busy with constructing a parallel haul road, as well as conducting earthworks and concrete civils at the Khoemacau Boseto processing plant.

The Khoemacau copper project, in the central Kalahari copper belt, is developing underground operations at its flagship Zone 5 deposit. The mine plan involves three adjacent underground mines at Zone 5, each producing over 1.2 Mt/y in their first five years of production.

The haul road in question will allow mineralised material to be trucked 35 km from Zone 5 to the Boseto processing facility, while the access road will be used by light vehicles. After processing at Boseto, the mineral concentrate will be shipped out for smelting.

Good progress has been made on construction of the access road according to Jay Juganan, Contracts Director at Concor Infrastructure. The contract for both the access and haul roads was awarded in November 2018.

“The access road was little more than a sand track when we established on site and was accessible only by 4×4 vehicles,” Juganan says. “Essentially, we are creating a corridor for both roads in parallel, and for the powerlines to be installed by another contractor.”

The planning of the haul road also had to consider the large and ancient Baobab trees that are common in the area. Preservation of these trees is a vital imperative, requiring the haul road to be diverted on occasion to avoid about half a dozen Baobabs, which are hundreds of years old.

The access road is 90% complete and due for completion in the September quarter. The haul road is also expected to be completed next quarter, the company said.

Road construction comprises a 600 mm deep cut filled with pioneer crushed rock followed by a G3 sub base and base layer. In some areas, the crushed rock is replaced by a natural calcrete.

The wearing course is a 9/19 mm double seal, according to Concor, which had to crush all aggregate on site from the old mine waste rock stockpile at Boseto.

Concor Infrastructure Contracts Manager, Tiaan Krugel, said the remote location of the site and the dry conditions are among the key challenges encountered on this project.

“The sourcing and timing of the supply of equipment, parts and construction material required careful and detailed planning,” Krugel says. “The majority had to come from the capital Gaborone – 900 km away – with the other challenge being that most of our equipment OEMs are based in Johannesburg, which is more than 1,300 km from site.”

The scope of Concor’s work at the Boseto process plant, the contract of which was awarded in November 2019, includes earthworks and concrete civils to the existing and for the new process plant structures for the crushing, milling, flotation and concentrate handling circuits. The plant had previously treated material from an open-pit copper mining operation at Boseto, under the ownership of a different company.

Krugel highlighted the challenges of working with concrete on a remote site, especially where temperatures can reach over 40°C during working hours.

“A special concrete mix was designed to accommodate on-site conditions,” he said. “This includes the use of admixtures to prolong the concrete’s workability as well as having to chill the water we use before it is added to the cement and aggregates.”

In addition to the refurbishment and upgrading work at Boseto, Concor has also contributed to preparing the infrastructure at the Zone 5 mining site, where underground development is underway.

The work included all internal roads at the Zone 5 mine, terracing for the 650-person accommodation camp, the mine administration surface infrastructure area, the mine workshops and stores area and the explosives magazine together with construction of the ROM pads.

The Khoemacau Starter project expects to produce 62,000 t of copper and 1.9 Moz of silver each year over its planned life of more than 20 years, according to the company.

“Despite the restrictions related to the COVID-19 pandemic, which saw a reduction of staff numbers on site due to individual choices, we are working hard to ensure that program schedules will be met,” Juganan said.