BHP looks to halve WA Iron Ore port facility emissions with Alinta Energy pact

BHP says it expects to halve emissions from the generation of electricity used to power its WA Iron Ore port facilities in Port Hedland by the end of 2024, following the signing of a large-scale renewable Power Purchase Agreement with Alinta Energy.

The halving of reported emissions, based on current forecast demand and compared with financial year 2020 (FY2020) reported emissions, will contribute to BHP’s medium-term target to reduce operational emissions by at least 30% from FY2020 levels by 2030 and the company’s long-term goal of achieving net zero operational emissions by 2050.

This agreement between BHP and Alinta will see the construction and connection of a 45 MW solar farm and 35 MW battery energy storage system into Alinta Energy’s existing Port Hedland power station, approximately 14 km from BHP’s port facilities, BHP says.

The construction of the solar farm, subject to final regulatory approvals, is expected to begin in December 2022 and create 200 jobs.

Once completed, it is expected that 100% of the forecasted average daytime energy requirements for BHP’s port facilities will be powered by solar generation, with the remaining power requirements to be met through the integrated battery energy storage system and market access to Alinta Energy’s existing gas fuelled power station facilities.

BHP is the foundation customer of Alinta’s solar battery hybrid project, which is expected to be the first large-scale renewable facility at Port Hedland and will support the expansion of the renewable energy industry in Western Australia.

In addition, BHP and Alinta Energy have entered into a memorandum of understanding in relation to the development of the Shay Gap Wind Farm. The Shay Gap Wind Farm is currently planned to be 45 MW, with a potential first-generation date of 2027.

The PPA is the latest milestone in BHP progressing its plan to reduce operational emissions in line with BHP’s climate targets and goals.

In recent years, it has signed power purchase agreements to provide renewable energy to BHP’s Nickel West operations in Western Australia, Olympic Dam operations in South Australia, BMA operations in Queensland and the Escondida copper mine in Chile.

BHP’s WA Iron Ore Asset President, Brandon Craig, said: “The world needs WA’s high quality iron ore to support economic development and decarbonisation, and we are committed to supplying iron ore more sustainably while investing in WA and creating local jobs. We are delighted to expand our partnership with Alinta Energy as we seek to lower emissions from our WA iron ore business.”

Alinta Energy MD and CEO, Jeff Dimery, said that BHP was once again demonstrating strong leadership in the transition to net zero.

“This is exactly the kind of leadership, progress and smart use of renewables and storage that we need from companies like BHP to show the way forward for Australia,” he said. “We’re excited to get the project underway and thank BHP for their partnership and vision.”

Fortescue’s Chichester Hub iron ore operations hit solar power milestone

Fortescue Metals Group’s Chichester Hub operations are now being powered by solar energy following the completion of the 60 MW Alinta Energy Chichester Solar Gas Hybrid Project in Western Australia’s Pilbara region, the miner confirmed.

Completion of the project with Alinta Energy marks a major milestone in the delivery of Fortescue’s decarbonisation strategy, as the company works towards its ambitious target of being carbon neutral by 2030 for Scope 1 and 2 emissions.

The solar farm will power up to 100% of daytime operations at Fortescue’s Christmas Creek and Cloudbreak iron ore sites, displacing around 100 million litres of diesel every year. The remaining power requirements will be met through battery storage and gas generation at Alinta Energy’s Newman Power Station, FMG said.

Fortescue Chief Executive Officer, Elizabeth Gaines said: “The completion of this project is a practical example of Fortescue delivering on its ambitious carbon neutrality target and demonstrates that renewables can power the energy needs of Australia’s mining and resources sector.

“As Fortescue transitions from a pure-play iron ore producer to a green energy and resources company, this milestone is a critical part of our Pilbara Energy Connect project which, together with the Chichester solar farm, will see 25% of Fortescue’s stationary energy powered by solar.”

Alinta Energy’s MD & CEO, Jeff Dimery, said: “Together, we’ve built a benchmark renewable project with an ambitious partner and, given the abundance of high quality renewables resources in the Pilbara, we look forward to supporting others to do the same.

“I’m very proud of the team and thank Fortescue, our partners, contractors and suppliers, NAIF, ARENA, and, in particular the Nyiyaparli People, on whose country the solar farm sits.”

The project also includes the construction of approximately 60 km of new transmission lines, linking Fortescue’s Christmas Creek and Cloudbreak mines to the solar farm and Alinta Energy’s existing energy generation infrastructure in Newman.

FMG to lead from the front in Pilbara renewable energy pursuit

Fortescue Metals Group (FMG) has signed an agreement with Alinta Energy that will see up to 100% of daytime stationary energy requirements at its Chichester Hub iron ore operations, in the Pilbara of Western Australia, powered by renewable energy.

The Chichester Solar Gas Hybrid project will see the construction of a 60 MW solar photovoltaic generation facility at the Chichester Hub, comprising Fortescue’s Christmas Creek and Cloudbreak iron ore mining operations.

In addition, an approximately 60-km transmission line linking the Christmas Creek and Cloudbreak mining operations with Alinta Energy’s Newman gas-fired power station and a 35 MW battery facility will be constructed, with completion due mid-2021.

FMG said: “Once completed, up to 100% of daytime stationary energy requirements at the Chichester Hub will be provided by solar generation, with the remaining power requirements to be met through the integrated battery storage and gas power station facilities.”

The project is expected to displace around 100 million litres annually of diesel used in the existing Christmas Creek and Cloudbreak power stations, according to FMG.

Fortescue Chief Executive Officer, Elizabeth Gaines, said: “Reliable and competitive energy generation remains an important consideration for the mining sector in Western Australia and as a significant consumer of energy, we continue to identify opportunities that have the potential to lower our costs while also improving our carbon footprint.

“This landmark project is a first on this scale for the Pilbara and will reduce carbon emissions from stationary generation by around 40% at Fortescue’s Christmas Creek and Cloudbreak mining operations, while driving long-term sustainable cost reductions to maintain Fortescue’s global cost leadership position.”

Gaines added that the agreement with Alinta Energy represented a further step in the creation of Fortescue’s Pilbara Energy Connect project, which builds on the company’s previous energy initiatives, including the construction of the Fortescue River Gas Pipeline, the conversion of the Solomon Power Station from diesel to gas generation, as well as a partnership agreement with the Commonwealth Scientific and Industrial Research Organisation to develop and commercialise hydrogen technologies.

As part of the agreement, FMG will invest an estimated $250 million in energy transmission infrastructure to complete the integration of Fortescue’s iron ore operations in the Pilbara into an efficient energy network.

Alinta Energy Managing Director and Chief Executive Officer, Jeff Dimery, said: “We’d like to thank Fortescue and our Chichester Hub project partners for helping to make the company’s long-held vision for a cleaner and more connected energy supply for the Pilbara a reality.

“There’s a lot to be proud of in this project. Working together, we are on the cusp of demonstrating that renewables can drive Australia’s economic powerhouses forward–even for remote and complex industrial applications.”

Alinta Energy will receive federal funding of A$24.2 million ($16.5 million) from the Australian Renewable Energy Agency (ARENA) and A$90 million from the Northern Australia Infrastructure Facility (NAIF), upon satisfaction of standard conditions.

The NAIF loan remains subject to ratification from the Western Australian Government.

NAIF Chief Executive Officer, Laurie Walker said: “NAIF’s A$90 million loan for this project will help provide low emission renewable energy generation for large off-grid customers and paves the way towards the creation of a more interconnected regional energy grid in the Pilbara.

“The project innovatively combines solar and gas fired power to compensate for the variability of solar sourced energy. This investment by NAIF offers the opportunity to make a long-term difference to the Pilbara.”

ARENA Chief Executive Officer, Darren Miller, said: “The project could unlock further investment in renewable energy in the mining sector and other remote and energy intensive operations.

“Alinta’s project will demonstrate how renewable energy solutions can deliver critical energy requirements for major mining operations and help reduce emissions. This will also show how interconnection of loads and different generation and storage -including solar, gas and battery storage -can provide secure and reliable electricity.”