Fortescue employs SRG Global for maintenance and shutdown services

SRG Global has been awarded a five-year term contract from Fortescue Metals Group to initially provide rope access and electrical maintenance requirements across the company’s mine, rail and port locations throughout Western Australia.

The A$150 million ($117 million) term contract, which has already commenced, is a Master Agreement for Maintenance and Shutdown Services, the company said.

Locations for SRG’s work include the Christmas Creek (pictured), Cloudbreak, Firetail, Kings Valley and Eliwana mine sites, along with its supporting rail and port infrastructure.

SRG Global Managing Director, David Macgeorge, said: “We are delighted to be selected as a key partner to FMG and to provide critical maintenance and shutdown services across their Pilbara operations for the next five years. This is another significant step forward in our strategy to build a portfolio of annuity earnings, with quality clients, to deliver long-term sustainable growth.”

Fortescue breaks ground at $1.275 billion Eliwana iron ore development

Fortescue Metals Group says it has officially broken ground on the Eliwana iron ore mine and rail project in the Pilbara of Western Australia.

FMG Founder and Chairman, Andrew Forrest, was today joined by Mark McGowan, Premier of Western Australia, FMG CEO, Elizabeth Gaines, and the company’s core leadership team, for the official sod turning.

The $1.275 billion project includes the construction of 143 km of rail, a new 30 Mt/y dry ore processing facility (OPF) and infrastructure. First ore on train is expected in December 2020, the company says.

FMG says contracts to the value of A$330 million ($232 million) to date have been awarded to more than 250 Australian business entities as part of the Eliwana development, of which 80% are Western Australia-owned businesses. As further approvals are progressed, it is expected over A$500 million in additional contracts will be awarded by the end of 2019, FMG said.

Contract recipients include BGC Contracting for bulk earthworks and roads, NRW Holdings, also for bulk earthworks, and SIMPEC for electrical, communications and dry fire systems testing.

“Eliwana underpins the sustainable production of West Pilbara Fines and provides the flexibility for Fortescue to deliver products at greater than 60% Fe grade,” FMG said. “The development will utilise the latest technology, autonomous trucks and design efficiency, further cementing Fortescue’s world leading use of innovation across its mining operations.”

Forrest said: “This is a proud day for Fortescue as we celebrate the largest project since the Kings Valley mine in 2014.

“Since Fortescue was founded 16 years ago, we have held community and family at our core and continued to deliver on our commitment to be the safest, lowest cost company. Eliwana is the next great step into the Western Hub, enhancing our profitability and extending our mine life.”

The project will generate up to 1,900 jobs during construction and 500 full-time site positions once operational, according to Forrest.

Gaines said: “The Eliwana project will build on Fortescue’s unparalleled track record and capability in safely developing and operating major iron ore projects in the Pilbara. Eliwana is core to the next phase of development in Fortescue’s world class, innovative operations. The project will see us maintain our low-cost status, provide us with greater flexibility to deliver on our integrated operations and marketing strategy and, when combined with the Iron Bridge Magnetite development, it will increase Fortescue’s average product grade and provide the ability to deliver the majority of our products at greater than 60% Fe, consistent with our long term goal.”