Tag Archives: Richard Hyde

West African moves into new phase at Sanbrado following gold pour

West African Resources says it has poured first gold at its Sanbrado gold project, in Burkina Faso, just over a week since confirming construction activities had been completed on all areas of the process plant and tailings storage facility.

The inaugural pour occurred on March 18, with gold bars weighing 23.9 kg (768 troy ounces) poured in the first smelt on site.

Since processing started up, 75,000 t of ore at 1.5 g/t Au has been processed, with indicative metallurgical recoveries of over 90%, West African said.

The process plant has also exceeded nameplate capacity for the past seven days of production, the company noted.

Open-pit ore stockpiles are also building with 250,000 t at 1.5 g/t Au on the run of mine pad, the company noted, adding that first underground development ore had been mined and stockpiled, ready to process.

West African Executive Chairman, Richard Hyde, said: “This is a major milestone for West African Resources and marks the beginning of a new phase in the WAF story. To successfully transition from an exploration company to a gold producer is without doubt a great achievement for all involved.

“I would like to thank WAF’s owners’ team and all consultants, contractors and other stakeholders for their hard work and support over the last four years to bring Sanbrado from discovery into production.”

West African a month away from first gold pour at Sanbrado

West African Resources says it has processed the first ore at its Sanbrado gold project in Burkina Faso, putting it on course to produce its inaugural gold product within the next month.

Construction activities have now been completed on all areas of the process plant and tailings storage facility, according to the company.

All four heavy fuel oil generators have been commissioned in the power station and are now operational, while the desorption and gold room circuits are undergoing commissioning in preparation for a maiden gold pour within the next four weeks.

Open-pit mining contractor, African Mining Services, a subsidiary of the Perenti Group, has ramped up mining activities to include both the M5 and M1 South pits, with day and night shifts starting in the past week, West African said.

Currently, over 360,000 t of oxide ore is stockpiled on the run of mine pad at an average grade of 1.5 g/t Au.

Underground development continues to progress on-schedule with mining contractor Byrnecut Offshore, a subsidiary of the Byrnecut Group, having completed the primary ventilation raisebore. The ventilation fan is also currently being installed. First development ore remains on track for late March and first stoping ore is forecast for the September quarter, the company said.

West African Executive Chairman, Richard Hyde, said: “This is a major milestone for West African Resources and testament to the quality of our team and contractors. Commissioning activities will continue over the next four weeks with the first gold pour on track for early Q2 (June quarter) 2020.”

An updated feasibility study on Sanbrado from 2019 envisaged an initial 10-year mine life, including 6.5 years of underground mining, with probable reserves of 1.7 Moz (21.6 Mt at 2.4 g/t gold). The project was expected to have average annual production over the first five years of 217,000 oz gold with all-in sustaining costs of less than $600/oz.

West African picks Ausdrill’s AUMS for Sanbrado open-pit mining

Ausdrill, through its wholly-owned subsidiary, African Mining Services (AMS), has been selected by West African Resources as the preferred open-pit mining contractor for the Sanbrado gold project, in Burkina Faso.

Sanbrado, a low-cost, high-grade operation only 90 km from the country’s capital, Ouagadougou, will be the 14th commercial gold mine in Burkina Faso in 14 years. It is forecast to have average annual production of 217,000 oz/y of gold at all-in sustaining costs of less than $600/oz in its first five years of mine life.

The AMS scope of work includes a full suite of open pit mining services – including site preparation, drill and blast, load and haul, and maintenance works – over a five-year term, generating approximately A$235 million ($160 million) in revenue under a schedule of rates contract, Ausdrill said.

AMS anticipates it will employ some 190 personnel at the project, with the workforce to be predominantly local, and use a mix of new and existing equipment to deliver on the project.

AMS and West African Resources are in the process of finalising the contract terms, which will include the provision of an optional deferred payment arrangement for up to $10 million at a commercial interest rate, with works expected to commence in early 2020. West African Resources said mobilisation activities were expected to commence in November, ahead of open-pit mining commencement in January 2020.

Ausdrill Group Managing Director, Mark Norwell, said: “A key focus for the new Ausdrill group has been to enhance our surface operations in Africa and target substantial growth opportunities across a range of commodities in select African countries.

“Being selected as preferred contractor at the Sanbrado gold project is a significant achievement and represents the excellent progress we are making in building on the suite of quality projects on which AMS operates in the region.”

West African Resources Managing Director, Richard Hyde, said: “Sanbrado is the highest margin gold project in construction in West Africa and we are on target for approximately 300,000 oz of gold in the first 12 months of production. We look forward to partnering with AMS to bring this fully funded project into production in mid-2020.”