Tag Archives: SAG mill

Weir Group highlights energy, emission reduction opportunities in comminution study

The Weir Group has completed a comprehensive study that highlights a significant opportunity to reduce energy use and emissions in comminution by leveraging three alternative technology combinations.

The study, presented by Paula Cousins, Chief Strategy and Sustainability Officer at Weir, during a COP28 panel discussion hosted by the Ministry of Economy, Trade and Industry of Japan and moderated by the World Business Council for Sustainable Development (WBCSD), showed that replacing conventional technology with innovative new solutions can cut energy use by 40% while also avoiding 50% of CO2e emissions.

Weir’s study focuses on comminution – the crushing process that turns big rocks into tiny particles to expose the entrapped mineral so that it can be extracted later in the mining process. Comminution is the most energy intensive stage of a typical mine site process. It is already electrified and is responsible for at least one-third of an average mine’s energy use and CO2e emissions1 and globally consumes around 3% of the world’s electrical power, according to studies.

The study is the first to use WBCSD’s Avoided Emissions Guidance to study mining processes and the avoided emissions results have been independently assured by SLR Consulting Limited, Weir says. Three of Weir’s technology combinations were evaluated against a conventional comminution circuit design for an archetypal mine processing 15 Mt/y of copper ore in Chile. All three of the technology combinations are shown to yield sizeable benefits versus the traditional circuit.

In the optimal combination, the comminution process consumes around 40% less energy and can avoid up to 50% of CO2e emissions. Importantly, there is no trade off elsewhere, as the redefined process uses less water too, according to the study.

Each circuit is based on a ‘rock to recovery’ system boundary – reducing rock direct from the mine to a size that enables the mineral to be recovered. The four configurations are:

  • Conventional comminution circuit based on a Semi-Autogenous Grinding (SAG) mill and ball mill (SABC circuit);
  • Weir High Pressure Grinding Roller (HPGR) replacing the SAG mill at the initial grinding stage (2C HPGR BM);
  • HPGR, plus vertical stirred mill (VSM) replacing the ball mill (2C HPGR VSM); and
  • Addition of a coarse particle flotation (CPF) unit (2C HPGR VSM and CPF).

These assessments focus on the use-phase of the life-cycle only; other life-cycle phases have been excluded because previously studies have shown these to be immaterially small across all comparisons (<1% of energy and emissions impact). Assessments have been made using a “year-on-year” timeframe approach. Comparative impacts have been assessed only in terms of energy use, grinding media consumption, and associated emissions, since other environmental trade-offs were deemed immaterial for comparison.

Given its energy intensity, the decarbonisation opportunities in comminution are huge, with the basic comminution process not having changed significantly for many decades, Weir says.

The company is collaborating with customers and other partners to redefine the process, developing innovative combinations of proven technologies to make significant improvements to efficiency and environmental performance.

Cousins said: “The need for technology solutions in mining is compelling – the world needs more transition metals to achieve net zero, but the mining industry needs to extract these using significantly less energy and water.

“By adopting a systems-based approach to technology collaborations, we can help the mining industry scale up and clean up at the same time.”

 

GR Engineering receives LoI for EPC process plant build at K92’s Kainantu gold mine

GR Engineering Services has received a Letter of Intent from K92 Mining Ltd, a subsidiary of TSX-listed K92 Mining Inc, for the engineering, procurement and construction (EPC) works associated with a 1.2 Mt/y process plant at the Kainantu gold mine in Papua New Guinea.

K92 Mining owns and operates Kainantu, a producing gold mine that has existing infrastructure at site. The EPC works are being performed as part of K92 Mining’s Stage 3 Expansion plans.

K92 Mining has successfully executed multiple expansions at the Kainantu Gold Mine, after restarting operations at the site in 2016.

In addition to the award of the contract, all process plant long-lead item contracts have already been awarded on a fixed price (excluding freight), to CITIC HIC Australia Pty Ltd for the SAG and ball mills, Jord International Pty Ltd for the filter press and Metso for the tank flotation cells, flash flotation cells and high-rate thickeners, K92 says.

The contract sum for the EPC contract is $81 million, with GR Engineering having commenced engineering works on an agreed scope and cost basis. The contract is expected to be finalised by the end of August 2023.

Tony Patrizi, Managing Director, said: “GR Engineering is a leading gold EPC contractor and has previous experience on PNG projects through our Brisbane office. We are looking forward to assisting K92 Mining achieve their expansion plans and to delivering a safe outcome for the project.”

K92 says commissioning of the 1.2 Mt/y Stage 3 Expansion process plant is targeting the end of the March quarter of 2025.

Metso to supply SAG mills and mill liners to Origin Mining’s Mineral Park project

Metso says it has been awarded orders for the delivery of grinding plant equipment to Origin Mining Company’s brownfield Mineral Park Mill Restart project in the US.

Origin Mining is managed under the Waterton Global Resource Management umbrella of investments, with Mineral Park in a historic, copper-rich mining district next to Kingman, Arizona. The total value of the order is €16 million ($17.4 million).

Metso’s scope of delivery includes two Planet Positive Premier® SAG mills and Skega Poly-Met™ mill liners, and the possibility to supply other comminution and beneficiation process equipment technologies later.

Jack McMahon, President of Origin Mining, said: “We have been impressed with Metso’s commitment to support our vision to grow the USA copper supply. Metso’s leading comminution and beneficiation process equipment technologies will help us do our part to contribute to the transition to an electrified future.

“Metso has actively supported the project in a time responsive, technical and open manner, allowing for ’fit for purpose’ process solutions. We also value Metso’s ability to provide the necessary value added after-sales services in Arizona to support our operation.”

Tim Robinson, Vice President, Minerals Sales in North and Central America at Metso, said: “We are very excited to support Origin Mining in their drive to develop and supply locally key battery minerals, like copper, in the USA. Our industry-leading products and large service team in Arizona is committed to supporting them in this quest.”

FLSmidth to deliver MissionZero comminution equipment to KCGM gold operations

Northern Star Resources Ltd has placed an order for a wide range of FLSmidth mineral processing technologies for its Kalgoorlie Consolidated Gold Mines (KCGM) Operations’ mill expansion project, according to the Denmark-headquartered OEM.

KCGM Operations are east-northeast of Perth in Western Australia, part of one of the richest goldfields in the world, the so-called Golden Mile close to the city of Kalgoorlie-Boulder.

The order is valued at approximately DKK 515 million ($75.1 million) and was booked in the June quarter of 2023. The equipment is due to be delivered during 2024.

Under the agreement, FLSmidth will supply a range of MissionZero products covering most of the flowsheet, including SAG mill, ball mill, primary crusher, pebble crushers, flotation cells and a pre-leach thickener. In addition to these technologies, the order also includes spare and wear parts. Upon installation, these technologies will substantially reduce the mine’s energy consumption.

The 20 MW grinding mills will be the highest power, gear-driven mills in the world and the ball mill will be the first gear driven 28 ft (8.5 m) diameter ball mill, according to FLSmidth.

“This order is yet another important milestone in our ambition to enable zero emission mining by 2030, and we are very pleased with Northern Star Resources’ contribution to fulfilling this ambition,” Mikko Keto, CEO at FLSmidth, said.

This week, Northern Star announced the final investment decision on the KCGM Mill Expansion project, agreeing to invest A$1.5 billion ($1 billion) to boost the mill’s capacity to 27 Mt/y, from 13 Mt/y.

Northern Star Resources’ Managing Director, Stuart Tonkin, said of the FLSmidth order: “Northern Star’s purpose is to generate superior returns for our shareholders, while providing positive benefits for our stakeholders through operational effectiveness, exploration and active portfolio management. Being a responsible producer for the benefit of our shareholders, employees, other stakeholders and the communities in which we operate is key to our sustainable operations. We are pleased to partner with globally leading technology suppliers like FLSmidth in advancing our five-year profitable growth strategy.”

West African secures Lycopodium and Metso Outotec mills for Kiaka gold project

West African Resources Limited is heading towards construction at its 90%-owned Kiaka gold project in Burkina Faso, having registered strong funding interest, awarded an engineering, procurement and construction management (EPCM) contract and booked the mill package for the development.

Kiaka, an asset with 7.7 Moz of reserves and resources on its books, is the company’s second gold mine in the country on top of its operating Sanbrado asset.

WAF’s feasibility study, released in August 2022, outlined pre-production capital costs of $430 million and a 2.5-year pre-tax pay back at a $1,750/oz gold price for the project. Kiaka was expected to operate over an 18.5-year life of mine, producing, on average, 219,000 oz/y of gold (on a 100% basis).

West African Executive Chairman, Richard Hyde, said strong competitive bids from its debt finance process supported the company’s targeted debt of $300 million for the project.

In the meantime, WAF has signed a notice of award with Lycopodium based on the engineering company’s priced proposal for the EPCM of a new carbon-in-leach treatment plant for Kiaka. This award incorporated Lycopodium’s early commencement of the engineering and procurement portion of the contract to complete the engineering and tendering of the long-lead mill package.

Lycopodium was also the contractor on the Sanbrado construction project.

In line with this, Lycopodium and WAF have undertaken a competitive tender process for the supply and delivery of the SAG and ball mill package for Kiaka.

Following the evaluation of tenders, the company selected Metso Outotec to supply the 18 MW SAG mill and 9 MW ball mill. Metso Outotec also provided the SAG and ball mills at Sanbrado (construction of the comminution circuit, pictured). WAF has signed the order with Mesto Outotec, which contains a firm pricing and delivery schedule for the mill package components that fits well into the Kiaka construction schedule, it said.

The mining company says it has mobilised earthworks equipment to the Kiaka project site. The initial areas to be cleared include the permanent camp area and the process plant area. Access road upgrades are also planned to be undertaken during the current dry season.

The construction schedule for Kiaka remains on track, with major works expected to commence in the March quarter and first gold in 2025.

WAF says it also remains on target to meet 2022 production and cost guidance of 220,000-240,000 oz of gold produced at an all-in sustaining cost of less than $1,100/oz.

FLSmidth to supply gearless overland conveyor technology to Southeast Asia mine

FLSmidth says it has been chosen to supply an overland conveyor (OLC) for a large, established copper-gold mine in Southeast Asia, which follows a large equipment order from the same customer and site earlier in 2022.

The pit-to-plant conveying system, which is over 5 km in length, has gearless drive technology. The order, including design and supply, was booked in the September quarter of 2022 and is valued at approximately DKK330 million ($44 million).

The conveyor order follows the March quarter 2022 announcement that FLSmidth had been chosen to supply two gearless SAG mills, two gearless ball mills and thickener technology to the same site. This new FLSmidth overland conveyor will deliver the ore from the pit to the new FLSmidth SAG and ball mills at the process plant.

The conveying system, part of the newly acquired tk Mining portfolio, is expected to deliver a significant reduction of operating expenditure due to its gearless drive technology, which uses less energy and results in less maintenance and higher availability during operations.

Mikko Keto, Group CEO at FLSmidth, said: “This overland conveyor system order not only continues our robust relationship with this customer, but it also demonstrates the strength of our portfolio following the acquisition of the tk Mining business. This is evidence that FLSmidth is a global leader in overland conveyors and gearless drive technology. The customer will benefit from our full flowsheet coverage, and we are proud to have provided the majority of the equipment to this mine site expansion.”

The order supports FLSmidth’s MissionZero ambition to enable customers to mine in a more sustainable manner, it said. Overland conveyors significantly reduce the need for diesel-powered truck fleets on mine site and makes material transportation more cost-effective and resource efficient.

FLSmidth to highlight full flowsheet expertise with ShalkiyaZinc project delivery

FLSmidth has signed a contract, valued at around DKK950 million ($130 million), to supply a range of mineral processing equipment to ShalkiyaZinc, the operator of a zinc-lead mine in the Kyzylorda Region of Kazakhstan.

The equipment will transform the plant into a world-class facility that efficiently separates minerals with a minimised environmental impact, the OEM says.

Under the agreement, FLSmidth will supply two underground crushing stations with a materials handling system to the process plant; a full package of comminution and separation equipment, including SAG and ball mills, mill circuit pumps and cyclones; the zinc-lead concentrate flotation and regrinding circuit, including nextSTEP, VXP vertical mills, concentrate thickeners and Pneumapress filters; and reagents preparation and dosing area. Full plant automation is also included, as well as installation and commissioning supervision services.

The new concentrator will be supported from FLSmidth’s new in-country service Supercentre in Karaganda, Kazakhstan.

The equipment delivery is to be completed during 2024, with commissioning to start before the end of that year.

Mikko Keto, Group CEO at FLSmidth, said: “We are excited to receive this first order from ShalkiyaZinc, which highlights our full flowsheet expertise. The wide range of equipment included in the order will help ShalkiyaZinc save on both capital expenditure and operating expenditure; our new nextSTEP flotation technology will improve the quality of the concentrates, the SAG mill will provide more flexibility, while the automation and digital solutions will further enable water and energy savings alongside safer operations.

“We look forward to making this a success on so many levels.”

Assel Rakhimova, Chief Project Director of Tau-Ken Samruk, which owns ShalkiyaZinc, said: “After testing and basic design work executed by FLSmidth, we are pleased to enter this new phase of collaboration with the procurement of critical technologies to improve the productivity and sustainability of our plant. We believe in successful execution and look forward to receiving the ordered equipment according to the schedule for installation and to continue working with FLSmidth on commissioning services and spare parts.”

Metso Outotec to deliver world’s largest Premier grinding mills to Kansanshi copper mine

First Quantum Minerals (FQM) has awarded an order to Metso Outotec for two very large horizontal grinding mills for the company’s copper mine expansion at Kansanshi in Zambia.

Metso Outotec’s delivery includes two Planet Positive Premier™ grinding mills with a total installed power of 50 MW – the largest Premier grinding mills Metso Outotec has delivered to date.

To meet the need for efficient and fast replacement of the lining systems, as well as ensuring a long wear life, the ball mill will be equipped with the Metso Outotec Megaliner™ and the SAG mill will be equipped with Metso Outotec metallic mill lining and a high-performance discharge system, it explained.

FQM’s Kansanshi mine, located near Solwezi in the North-western Province of Zambia, is among the largest copper mines in the world and the largest in Africa.

First Quantum Minerals is currently working on its further expansion (the Kansanshi S3 Expansion), which includes a standalone 25 Mt/y processing plant that will increase copper production substantially.

Once the expansion is completed, copper production from Kansanshi is expected to average approximately 250,000 t/y for the remaining life of mine to 2044.

The Premier horizontal grinding mills are customisable solutions built on state-of-the-art grinding mill technology, process expertise, and design capability, Metso Outotec says. The Premier horizontal grinding mills are engineered to “excel and create vast possibilities” for customers and applications.

Earlier this week, Metso Outotec was awarded what it says was a major contract for the delivery of sustainable crushing, screening and grinding technologies to a greenfield iron ore project in South America.

Liontown secures Metso Outotec SAG mill ahead of Kathleen Valley lithium FID

Liontown Resources Ltd says it has awarded a key contract to Metso Outotec for the design, fabrication and delivery of a SAG mill for its flagship Kathleen Valley lithium project in Western Australia.

Following the completion of the definitive feasibility study (DFS) for Kathleen Valley in November 2021, the company has completed further engineering optimisation to confirm the scope and duty of the SAG mill to a sufficient level of detail to enable it to place the order with the OEM.

The contract, which has a value of circa-A$10 million ($7.2 million) and is in accordance with DFS estimates, is for the design, fabrication and delivery of a 7.9 m diameter and 4.4 m effective grinding length 5.5 MW SAG mill. This is inclusive of all lining, lubrication, cooling, electrical and mechanical drive systems necessary for installation and commissioning.

The SAG mill, from Metso Outotec’s Premier™ range (an example above), will accommodate both base production of 2.5 Mt/y and the planned expansion to 4 Mt/y in year six of the mine plan, Liontown said.

The SAG mill is one of several critical long-lead items identified for early award and represents the largest single piece of equipment required to be purchased for the project by size, value and lead time, the company added.

“Detailed engineering and design for the A$473 million Kathleen Valley project continues and Liontown is targeting the award of all key equipment packages over the next six months to maintain schedule and meet its target of first production of lithium concentrate in 2024,” it said.

Other key project deliverables including final permitting and securing the engineering, procurement and construction management partner to build and commission the Kathleen Valley project are progressing to meet the targeted Final Investment Decision milestone by the end of the June quarter.

Liontown’s Managing Director and CEO, Tony Ottaviano, said: “The SAG mill contract is the first of the long-lead items to be ordered and represents an important milestone for the Kathleen Valley project. Placing this significant order with a world-class partner in Metso Outotec is a great way to start the year and reflects our commitment to advance the Kathleen Valley project rapidly towards first production.”

The November 2021 DFS outlined base production of 2.5 Mt/y, producing around 500,000 t/y of spodumene concentrate with a 4 Mt/y expansion planned in year six, to deliver circa-700,000 t/y of spodumene concentrate.

The Metso Outotec Premier horizontal grinding mills are customisable solutions built on state-of-the-art grinding mill technology, process expertise and design capability, the OEM says. They are engineered to “excel and create vast possibilities” for customers and applications.

Metso Outotec set for SAG mill Premier at Northern Star’s Thunderbox

Metso Outotec says it will deliver a high-capacity, high-powered Premier™ SAG mill to Northern Star Resources Limited’s Thunderbox gold mine expansion project in Western Australia.

The typical value of such a delivery is approximately €15 million ($17.7 million) depending on the final scope, according to the OEM. The order has been booked in the company’s Minerals’ first half of 2021 orders received.

On award of Northern Star Resources’ largest mill to date, Northern Star’s General Manager Processing, Simon Tyrrell, said: “The Thunderbox expansion increases the operation’s hard-rock processing capacity to 6 Mt per annum from the current 3 Mt/a, and decreases processing costs as outlined in our 2021 Investor Day Presentation.

“Northern Star’s selection of Metso Outotec for the mill supply is supported by their locally-based expertise, large mill supply history and ongoing collaboration with Northern Star.”

Earlier this month, GR Engineering Services executed an engineering, procurement and construction contract with Northern Star Resources in relation to the expansion project.

Christoph Hoetzel, Head of Grinding Business Line at Metso Outotec, said: “We are pleased to be chosen as a supplier for the Thunderbox expansion. The gear-driven Premier SAG mill to be delivered will feature 18 MW of motor power.

“With the Premier mill range, we advance our unrivaled innovation legacy providing our customers with most reliable technology, engineered to exceed their specific requirements. We are looking forward to continue the collaboration with Northern Star Resources and to be part of their success story.”

The Premier horizontal grinding mills are customisable solutions built on state-of-the-art grinding mill technology, process expertise and design capability, the company says. The Premier horizontal grinding mills are engineered to “excel and create vast possibilities” for customers and applications.

These mills can be integrated with Metso Outotec mill reline equipment and are supported by the company’s extensive services network to ensure optimisation during the mills’ lifetime, the company says.