Tag Archives: Séguéla

Fortuna Silver Mines readies for mid-2023 gold pour at Séguéla

The initial mining fleet has arrived at Fortuna Silver Mines’ Séguéla gold project in Côte d’Ivoire, ahead of planned commissioning in the June quarter, the company has confirmed.

The overall project is approximately 90% complete as of the end of January and remains on-track and on-budget for first gold pour in mid-2023, the company said.

Among the initial fleet are Cat haul trucks, an excavator, dozer and other ancillary equipment. The company says the next tranche of mining equipment is on-schedule for late-February availability. This includes a Cat 6020B 230 ton (224 t) hydraulic excavator, which is delivered and being assembled on-site; four Cat 777E haul trucks being assembled in Abidjan; one 50 ton excavator for rock-breaker, which has a hammer already on-site; one Cat D9 dozer; and two Cat 988 wheel loaders for crusher feed.

Mota-Engil, the mining contractor, has established its temporary facilities on site to support initial mining activities with construction of the permanent mining services area infrastructure progressing well.

With the completion of construction rapidly approaching, operational readiness has increasingly become the focus in preparation for commissioning of the 3,750 t/d processing plant, which is due to commence early in the June quarter of 2023. As a result of the dedicated efforts of the Séguéla management and site teams, the project is well positioned for this transition, which also represents a significant milestone for the company, it said.

David Whittle, Chief Operating Officer – West Africa, said: “Construction activities are nearing completion despite worldwide supply chain challenges. We are pleased to report commissioning remains on schedule for Q2 (June quarter) 2023. Our operational teams are being assembled with an experienced core leadership group already hired and preparing for first gold production. This will mark a significant milestone for Fortuna with Séguéla also exhibiting growth potential given the quantity of inferred resources and the exploration success on the property to date.”

Séguéla has a nine year mine life in reserves, with the initial six years expected to report 133,000 oz/y of gold production.

Roxgold lays Séguéla groundwork with Metso Outotec, Lycopodium contract awards

Roxgold says it has awarded a SAG mill order for the Séguéla gold project in Côte d’Ivoire to Metso Outotec as part of its efforts to advance the project through to construction in the coming months.

The move comes ahead of the release of feasibility study on the project next month, which will build on a 2020 preliminary economic assessment (PEA) that outlined an operation capable of delivering over 100,000 oz/y of gold over eight years at average all-in sustaining costs of $749/oz. This study also incorporated a single stage primary crush/SAG milling comminution circuit with 1.25 Mt/y throughput.

At the same time as selecting Metso Outotec for the SAG mill contract, Roxgold has awarded preferred contractor status to Lycopodium Minerals Pty Ltd and is currently negotiating the engineering, procurement, and construction (EPC) agreement with the company for the 1.25 Mt/y carbon-in-leach processing facility and other supporting infrastructure to be constructed at Séguéla.

The fixed price agreement increases confidence in the total capital cost for the project, as it is by far the largest scope at Séguéla, Roxgold said.

“With this agreement in the final stages of negotiation and several other key scopes now tendered and priced, approximately 65% of the pre-production capital estimate has now been fixed or finalised,” the company added. “This level of detail provides increased confidence around the pre-production capital estimate, which is expected to be in-line with the previous estimate of $142 million, as outlined in the PEA.”

In terms of progressing work on long-lead time items, Roxgold said it had awarded the plant site bulk earthworks tender, with a contract expected to be executed and works commenced in the June quarter to support the project critical path.

The company has continued to advance its early works program at site including upgrading of the site access road and construction of the accommodation village. Contracts were awarded for camp bulk earthworks and camp construction, with first concrete poured last month, it said.

Surveying has been completed for the 33 kV and 90 kV power lines to tie into the existing 90 kV transmission line running across the property, which is connected to the 225 kV ring main system around the country. These early work activities will enable a rapid ramp up to full construction upon completion of the feasibility study and mine financing in the June quarter of this year.

Roxgold says it has undertaken a competitive tender process and has conducted a detailed assessment of the contract mining proposals received. It is currently completing diligence on the shortlisted parties and plans to award the mining contract later this year to allow for contractor mobilisation, site establishment,and commencement of pre-production mining early next year.

John Dorward, President and Chief Executive Officer, said: “The Séguéla project has rapidly become a cornerstone asset for Roxgold, and we believe that the project will provide significant value to all our stakeholders.

“The feasibility study is on track to be announced in the second (June) quarter, which we believe will demonstrate the ongoing evolution of the Séguéla PEA with an enhanced mine life and project economics with the inclusion of the high-grade Koula deposit into the mine plan.”