Orezone Gold Corp has selected Sila Equipement ET BTP SA as its open-pit mining contractor for the Bomboré gold project in Burkina Faso.
Sila, a Burkinabé company, will initially have a contract scope that covers the mining of the Off-Channel Reservoir (OCR) pit, as well as the upfront establishment of mine site services (maintenance workshops, wash bays, warehouse, ablutions and accommodations, offices, and communications), the clearing and grubbing of the OCR footprint including topsoil relocation, as well as pit dewatering and haul road maintenance.
Orezone said mining of the OCR is an important milestone given that the pit will serve as the main water storage facility during operations.
“The mobilisation of Sila will ensure that the OCR and its related infrastructure will be ready well in advance of the onset of the 2022 rainy season,” the company explained.
Orezone says it is working in partnership with Sila to finalise certain key terms under the long-term mining contract.
Patrick Downey, President and CEO, said: “With the project financing now in place, we are rapidly advancing the engineering, procurement, and construction of the project. The early award of the mining contract will allow our project to remain on schedule.
“I am pleased that Sila, a local contractor, has been awarded this work which speaks to the depth and continued growth of the mining service industry in Burkina Faso. The company’s selection of Sila was made after a competitive tender and due diligence process including a review of safety and operational performance in free-dig oxide operations such as Bomboré. Sila has demonstrated an excellent track record in other similar Burkina Faso mining operations.”
He added: “The proposed mining fleet is brand new equipment and will be operated by Sila’s highly experienced senior operations and maintenance team.”
Since the recent appointment of Lycopodium in January as the EPCM contractor, the company says it has rapidly advanced engineering and procurement activities, and made significant progress on refining the project construction timeline. The company’s key procurement and site-based activities in the upcoming months will be focused on the following:
- Pre-production mining to commence in March 2021;
- Ball mill order (a critical long lead item) to be placed in March 2021;
- Award of power plant contract in March 2021; and
- Site-wide bulk earthworks to commence April 2021.