Civmec to replace car dumper at BHPs Nelson Point, carry out new work for Roy Hill

Civmec Limited says it has recently secured circa-A$120 million ($86 million) of new contracts across multiple operating sectors, including three new agreements with BHP and Roy Hill.

Among these new assignments is a Car Dumper Replacement project for BHP, which has instructed Civmec to replace Car Dumper 3 (CD3) at the Nelson Point facility in Port Hedland, Western Australia, was commissioned in 1998. The new CD3 has a design life of 30 years and is intended to fit in the existing concrete vault with minimal structural modifications, Civmec said.

Procurement activities for this project have commenced, with fabrication commencing in the first quarter of its 2023 financial year (September quarter) and completion of fabrication in Q4 FY2023 (June quarter of 2023). At peak, this contract will employ approximately 85 people, Civmec said.

Roy Hill, meanwhile, has instructed Civmec to perform two contracts.

The first one is a capital upgrades project where it has been awarded the SMP&E (Structural Mechanical Piping and Electrical) works for the ROM4 Crusher 5 project at Roy Hill’s mine in the Pilbara of Western Australia. This is a follow on from the current SMP&E contract for the WHIMS project for Roy Hill, which is nearing completion and will see the same project management team transitioning to the ROM4 project.

The scope includes SMP&E plus communications works for the Crushing Station 5 and transfer conveyor, including installation of client-supplied modules and equipment. Mobilisation will commence in the June quarter of this year with completion by the end of the year.

Civmec has also received an extension of its Shutdown and Maintenance Support Services Agreement with Roy Hill, being granted an additional five years through to March 2027.

“This contract extension demonstrates a significant commitment from Roy Hill and will enable Civmec to support the Roy Hill Operation with multi-disciplined shutdown and maintenance services for the fixed plant assets across the port (facility) and PSA (mine),” Civmec said.

“As one of Civmec’s long term customers, Roy Hill is an important stakeholder for our maintenance business. Our investment in the local community and our commitment to building our Port Hedland Workshop facility is evidence of our pledge to being a long-term partner to Roy Hill and our intent is to further strengthen this relationship.”

Civmec banks new work from BHP, Roy Hill and Rio Tinto

Civmec Ltd says it has received three notices of award from several repeat mining customers for maintenance and capital works projects collectively worth approximately A$130 million ($97 million).

These orders – from BHP, Roy Hill and Rio Tinto – bring its total order book to about A$1.05 billion as at September 30, 2021.

For BHP, Civmec is to carry out a civil and earthworks job as part of the miner’s Port De-bottlenecking Project Stage 1, which includes a new stockyard planned for the South Yard at Nelson Point, in Port Hedland, Western Australia.

The scope of work includes dewatering, piling, ground improvement, associated earthworks, concrete foundations, new roads, high voltage poles and underground power works.

Civmec says mobilisation will commence this quarter, with completion expected in the March quarter of 2022.

With Roy Hill, Civmec is due to carry out a greenfield construction package related to an extension of the existing Wet High Intensity Magnetic Separation (WHIMS) plant at Roy Hill’s mine site north of Newman, in Western Australia’s Pilbara region.

The scope of work includes greenfield installation and pre-commissioning of pre-assembled modules, piping, electrical and tie-in works. Mobilisation will commence immediately and completion is scheduled for the March quarter of 2022.

At Rio Tinto’s Boyne Island Smelters operation, Civmec is to supply refractory trades and other associated disciplines for maintenance, rebuild and reduction cell reconstruction works on carbon bake furnaces. The contract term is for three years with two one-year extension options.

Civmec’s Chief Executive Officer, Patrick Tallon, said: “We are delighted to secure these project wins with three of our long-term Tier 1 customers. The projects combine multi-year maintenance works along with two projects within our newly formed Maintenance and Capital Works – Resources and Energy area. With the BHP PDP1 project located in the Port Hedland region, it provides an ideal opportunity for Civmec’s newly opened regional branch to support the project, validating Civmec’s recently announced plans to invest in a purpose-built facility in Port Hedland.”

Primero completes WHIMS project at Fortescue’s Christmas Creek iron ore op

Primero Group says it has completed the construction of a Wet High Intensity Magnetic Separation (WHIMS) processing plant at Fortescue Metals Group’s Christmas Creek iron ore mine in Western Australia.

The plant is expected to improve product grade and mass recovery from the desands unit at the Christmas Creek Ore Process Facility #2.

The flowsheet is based on a simple and robust configuration, where wet screen undersize at a nominal -1 mm is treated in open circuit through a low intensity magnetic stage, followed by a vertical WHIMS stage to produce a concentrate stream and a tailings stream, which can be integrated with the existing process and auxiliary equipment. The vertical WHIMS project entails the redirection of the wet screen undersize stream from the existing scrubbing circuit to feed the brownfield magnetic separation plant.

“We can proudly say that despite the impacts of COVID-19 and the fast-tracked nature of the project, the plant was successfully delivered and commissioned in less than 12 months – meeting all safety and project key performance indicators,” the company said.

Primero put the project’s success down partly to the “enhanced opportunity for collaboration early contractor involvement (ECI) provides”.

It added: “A flexible approach to project development that ensures the needs of all project stakeholders can be met prior to detailed design and implementation in a lump sum engineering procurement and construction (EPC) environment. This constructive, relationship-based contracting continued throughout construction, commissioning and now operation – demonstrating the power of the ECI contracting model when coupled with Primero’s unique, vertically integrated EPC capability.”