Rio flying high at technologically advanced Gudai-Darri iron ore project

Western Australia’s newest airport has opened at Rio Tinto’s $2.6 billion Gudai-Darri (formerly known as Koodaideri) iron ore project in the Pilbara where construction is progressing ahead of expected production ramp-up in early 2022.

The facility can accept a range of different aircraft including Boeing 737s, A320s, F100s and King Airs. The current flight schedule includes four flights a week with additional flights expected to be added to the schedule next year. The airport is expected to handle more than 600 workers in a day at peak operating times, according to Rio.

The airport will deliver significant benefits in terms of minimising employee interaction with vehicles and driving, as well as helping to manage employee fatigue thanks to a significant reduction in travel time from an alternate regional airport, Rio says. The airport will also provide a safer landing option for Rio Tinto’s long-standing partner, the Royal Flying Doctor Service.

Rio Tinto Projects General Manager, Gudai-Darri, Anthony Radici, said: “You get a real sense of the immense size and scale of our Gudai-Darri operation once you fly into this new airport.

“The construction phase of the project is progressing well with a significant amount of infrastructure at the mine now built, millions of cubic metres of material moved, a new access road, a significant amount of the rail formation installed, two new bridges constructed and now a brand new airport.”

Rio Tinto Iron Ore Acting Chief Executive, Ivan Vella, said: “The construction phase of Gudai-Darri, our most technologically advanced mine, has a strong focus on supporting local businesses with contracts valued at more than $2.3 billion awarded to date.

“These contracts have supported approximately 2,000 jobs in the construction phase and the mining operation is expected to support about 600 jobs on an ongoing basis. We are proud to support West Australian businesses as we progress a pipeline of investment opportunities in the Pilbara valued at more than A$10 billion ($7.3 billion) over the three years to 2022.”

Contracts at Gudai-Darri valued at more than $2.3 billion have been awarded to local Pilbara, Pilbara Aboriginal and West Australian Businesses including Primero Group, NRW, DTMT, Pindan, White Springs, Hicks Civil & Mining and Karratha Earthmoving & Sand Supplies.

The full construction and design of the airport will be completed by local partners Primero Group, NRW, Worley and GHD, together with NRW subcontractors Colas, Fulton Hogan, TEC services, Brookdale Contractors, Bennco and Karlka Fencewright.

Gudai-Darri is a greenfield mine development, around 35 km northwest of the Yandicoogina mine in the East Pilbara mining region. The mine will initially be developed as a nominal 43 Mt/y high-grade, dry processing operation.

Alltype Engineering goes modular for Rio Koodaideri iron ore plant deliveries

WestStar Industrial Ltd’s engineering contractor business, Alltype Engineering, is to help build an iron ore mine plant at the Rio Tinto-owned Koodaideri project in the Pilbara of Western Australia, thanks to a contract award from Laing O’Rourke.

The Phase 1 Structural, Mechanical, and Piping package for the mine plant comes with a value of around A$6 million ($4.4 million) for fabrication works plus associated modularisation scopes, WestStar says.

The execution plan developed by Laing O’Rourke, the managing contractor, is based upon substantial preassembly and modularisation of the structural steel elements at Alltype’s Naval Base facility, in Western Australia (pictured). The contract win takes immediate effect with delivery and install dates up to January 2021, it said.

“The works to be performed leverage off the core competencies of the company with similar delivery strategies utilised for oil and gas, petrochemical and infrastructure projects in the past,” WestStar said.

Koodaideri is a greenfield mine development, around 35 km northwest of the Yandicoogina mine in the East Pilbara mining region. The mine will initially be developed as a nominal 43 Mt/y high-grade, dry processing operation. First production is expected in late 2021.

WestStar acquired Alltype Engineering last year in a deal that involved an upfront payment of around A$5.9 million, along with a deferred consideration subject to Alltype achieving its 2020 financial year targets.

Alltype Engineering Managing Director, Kelvin Andrijich, said: “Alltype Engineering undertook a significant strategic shift in direction in 2017, focusing on multi-discipline construction solutions, technology partnerships with OEMs and leveraging off the well-established industry exposure developed over 35 years of operation. This strategy continues to unfold with our established local fabrication capability and by building upon successive projects delivered of increasing scale and complexity with existing and new clients.

“The support of our new owner, WestStar Industrial, allows the group to execute larger contracts previously constrained by working capital, as well as start to expand the operational footprint to the east coast of Australia where there is further market opportunity for this offering.”