News

Panoramic, Primero and Barminco get to work on restarting Savannah nickel operation

Posted on 6 Apr 2021

Panoramic Resources Ltd, after a 12-month review process, has approved the restart of the Savannah Nickel Operation, in the Kimberley region of Western Australia.

The decision hinges on a 12-year mine life with an average annual production target of 9,072 t of nickel, 4,683 t of copper and 676 t cobalt in concentrate; as well as an offtake agreement with Trafigura that will also see the trading company provide a loan facility of up to A$45 million to cover the A$41 million of upfront capital cost required to restart the mine.

Savannah is set to operate at average site all-in costs of A$6.36/lb of payable nickel, net of copper and cobalt by-product credits and royalty payments. This equates to roughly $4.86/Ib or $10,714/t.

Savannah, with more than A$100 million already invested, has been maintained since the suspension of operations in April 2020 with a view towards operational readiness and project optimisation. This includes the recent completion of the FAR#3 ventilation raise, underground capital development on four mining levels at Savannah North and ancillary capital works on surface and underground infrastructure, which are currently being completed, Panoramic said.

The restart decision has led to divisions of Perenti and NRW Holdings being awarded significant contracts related to the resumption of mining activities.

Barminco, a subsidiary of the Perenti Group, has been awarded a four-year underground mining contract under a binding letter of intent and is scheduled to mobilise to site in July 2021. The contract will be serviced by new underground mining equipment including the use of tele-remote mining equipment, expected to deliver both safety and productivity benefits, Panoramic said.

The contractor was formally awarded the A$200 million contract back in February.

“Based on Barminco’s previous working knowledge at Savannah, opportunities to increase ore production and reduce dilution have also been identified,” the company added, explaining that underground mining is planned to commence in August, with ore to initially be sourced from both the Savannah and the Savannah North deposits.

Following an evaluation of an owner-operator model for the processing plant and a competitive contract tender process, Panoramic has also signed a non-binding letter of intent worth A$35 million with Primero (owned by NRW Holdings), which envisages a three-year agreement. The agreement relates to all processing and maintenance work at the Savannah processing plant, which has been maintained in “excellent condition” during the suspension, Panoramic said.

“A number of opportunities for improved recoveries through enhanced operating practices and minor capital projects have been identified,” the company added. As a result, the non-binding letter of intent with Primero has been structured to incentivise achieving higher than budget recoveries.

Panoramic is working with Primero to complete a binding contract in the coming months, but ore processing is set to restart in November 2021, allowing ore stockpiles to build for around three months (100,000 t) to de-risk ore supply issues.

The process plant at Savannah was commissioned in August 2004 and comprises a single stage crusher, SAG mill, flotation, thickening and filtering stages to produce a bulk nickel, copper, cobalt concentrate. Over the 2004 to 2016 initial operating period, metallurgical recoveries averaged 86-89% for nickel, 94-97% for copper and 89-92% for cobalt. The plant was originally designed for a throughput of 750,000 t/y, but consistently outperformed the design specifications with rates exceeding 1 Mt on an annualised basis, Panoramic said.

First concentrate shipment from the Wyndham Port is targeted for December 2021.