Newcrest’s Brucejack mine set for full fleet battery-electric transition in Q4

Newcrest’s Brucejack gold-silver mine in British Columbia, Canada, is set for a full battery-electric fleet transition by the end of the year, the gold miner said in its financial year 2022 results.

Following a successful site trial, seven underground battery-electric trucks are being commissioned at Brucejack, replacing the existing diesel fleet and abating approximately 65,000 t of CO2 emissions through to 2030.

The new fleet will improve truck productivity, lower unit costs and enhance operational efficiency from planning to production, according to Newcrest. Three of the Sandvik 50-t-payload Z50 battery-electric trucks are already in production, with the full switch over expected to be completed in the December 2022 quarter, it noted.

Sandvik and Pretivm previously noted that seven Z50 haul trucks would be supplied to the operation as part of the planned fleet transition.

The project is being partly funded thanks to a C$7.95 million ($6.1 million) investment from The CleanBC Industry Fund.

Brucejack, which became wholly owned by Newcrest when the acquisition of previous owned Pretivm Resources completed earlier this year, is currently the subject of Newcrest’s EDGE program, which aims to drive a culture of innovation, high performance and continuous improvement. The program has identified additional opportunities of approximately C$15-$25 million/y, with improvements in stope turnaround time and more efficient mine operations as the initial focus areas, the company said.

Run-rate benefits from this effort are expected to be fully realised by the June 2024 quarter, Newcrest says.

Newcrest said in the financial results that it was also assessing ore sorting technology at the mine, which aims to classify and separate mineralised material from non-mineralised material to deliver more consistent mill feed grades and increase operational flexibility.