Sedgman formally awarded EPC contract for Artemis’ Blackwater gold project

CIMIC Group’s mineral processing company, Sedgman, has been awarded an engineering, procurement and construction (EPC) contract to deliver services for Artemis Gold at the Blackwater gold project in British Columbia, Canada.

The EPC contract, which supersedes the temporary interim service agreement announced on May 2, 2022, will generate revenue for Sedgman of C$318 million ($245 million).

Sedgman will design and construct the processing and non-processing infrastructure for a 6 Mt/y carbon-in-leach gold plant at the project.

Even before this announcement, Sedgman had made good headway on the project, executing an agreement with Metso Outotec to secure supply and delivery of crushing and grinding equipment for the processing plant.

The project schedule as laid out by Artemis supporting the EPC contract with Sedgman includes the following assumptions:

  • Receipt of the BC Mines Act and related permits in the Fall of 2022;
  • Construction mobilisation and major works preparations commence in the March quarter of 2023 with process plant bulk earthworks scheduled to be completed prior to the start of major works;
  • Commissioning activities of the process facility to commence in the firts half of 2024; and
  • First gold pour expected in the September quarter of 2024.

CIMIC Group Executive Chairman, Juan Santamaria, said: “Sedgman and Artemis have already commenced initial design and procurement work at the project, helping Artemis to unlock the value of this key gold project and work towards its first gold pour in 2024.”

Sedgman Managing Director, Grant Fraser, said: “We are pleased to be working with Artemis Gold on this exciting project and look forward to continuing our strong working relationship to ensure successful outcomes for both Sedgman and Artemis.”

Work is expected to be completed in the September quarter of 2024.

Artemis has said previously that Stage 1 development at Blackwater should lead to the building of a 6-9 Mt/y operation (6 Mt/y in years 1-4 and 9 Mt/y in year 5) able to produce around 312,000 oz/y of gold.

Artemis awards Blackwater gold EPC contract to Sedgman Canada

Artemis Gold Inc says it has made an award for the engineering, procurement, construction and commissioning (EPC) scope of works for the processing plant and associated infrastructure at its Blackwater project in British Columbia, Canada, to Sedgman Canada Limited, a CIMIC Group company.

The award amount of approximately C$312 million ($243 million) is consistent with the prescribed budget for the process plant and selected infrastructure scope of works in the 2021 feasibility study.

Sedgman Canada Limited is a wholly owned subsidiary company of Sedgman Pty Limited, a CIMIC Group company. CIMIC Group (ASX:CIM) is an engineering-led construction, mining, services and public private partnerships leader working across the lifecycle of assets, infrastructure and resources projects.

The EPC contract is expected to be executed by June 30, 2022, with the contract supported by performance security including bank letters of credit, which will underwrite the financial performance and obligations of the contractor under the contract.

While the parties finalise the definitive EPC contract, in order to maintain the project schedule, an interim services agreement has been agreed which could cover procurement and pricing of long lead equipment and optimisation through refined scope changes, among other aspects.

The project schedule supporting the award to Sedgman includes the following assumptions:

  • Construction mobilisation and major works preparations commence in Fall 2022 with process plant bulk earthworks scheduled to be completed prior to the start of major works;
  • Commissioning activities of the process facility to commence in Q1 (March quarter) 2024; and
  • First gold pour expected in the first half of 2024.

The final EPC contract terms will provide for potential cost adjustments of certain components of construction representing approximately less than 15% of the total contract amount, including the potential for cost adjustments from further quantity definition, Artemis said. Standard adjustments, including currency exchange rates for certain equipment purchases also apply, and further optimisation of the processing plant with final engineering will occur.

Artemis is also considering awarding additional construction packages under an EPC agreement type structure to further enhance the risk management of the total capital expenditure for Blackwater, it said.

When combined with the EPC for the Power Transmission Line announced on August 18, 2021, the percentage of the estimated total capital expenditure for Blackwater under EPC is on track to target circa-60% of the initial Stage 1 development capital of C$645 million in a lump sum EPC type arrangement by the September quarter of 2022.

Stage 1 development should lead to the building of a 6-9 Mt/y operation (6 Mt/y in years 1-4 and 9 Mt/y in year 5) able to produce around 312,000 oz/y of gold.

Steven Dean, Chairman and CEO, said: “The award of the EPC job for the process plant at Blackwater is another significant milestone for Artemis, reflecting a competitive process involving multiple bidders. We are very pleased to be working with a world-class engineering firm in Sedgman. In partnership, we will work to finalise the design and engineering of the Blackwater project in advance of a start of major development activities. Blackwater remains on track for a start of major construction activities following receipt of Mines Act and other permits in Fall 2022 with a first gold pour in H1 2024.”

Artemis Gold locks in Blackwater EPC processing plant price with Ausenco

After a competitive bidding process, Artemis Gold has executed a binding memorandum of understanding with Ausenco Engineering Canada Inc providing for a guaranteed maximum price (GMP) for a fixed-price engineering, procurement and construction (EPC) contract to construct a 5.5 Mt/y processing facility and associated infrastructure at the Blackwater gold project in British Columbia, Canada.

The selection of Ausenco as the successful bidder was based on a proposal to engineer and construct the facilities for a GMP of $236 million ($188 million), subject to any technical or commercial changes requested by Artemis.

The MoU outlines the terms under which Ausenco will undertake further detailed engineering, which will form the basis of a final fixed EPC price that will not exceed the GMP. This Ausenco GMP is consistent with capital estimates in the company’s 2020 prefeasibility study on Blackwater.

A fixed price EPC contract on the processing facility and associated infrastructure represents by far the largest single component of the capital cost of Blackwater at approximately 40% of the PFS estimate of C$592 million ($470 million), Artemis says.

Ausenco has already undertaken a significant amount of detailed engineering work on the plant and will be working towards a final fixed-price EPC contract for the facilities scheduled for completion in the September quarter.

Artemis is also conducting a competitive bidding process for a GMP proposal in connection with a fixed price EPC contract for the construction of the electricity transmission line and associated offsite infrastructure, with an expected GMP award in the June quarter, it said.

Steven Dean, Chairman and CEO, said: “The execution of this MoU represents a significant investment of time and effort from management and multiple GMP bidders over the past several months. The Ausenco GMP bid serves as further validation of the initial capital costs estimated in the 2020 PFS with respect to the process plant and associated facilities, further de-risking the development of the project.

“Following a rigorous adjudication process of a number of competitive proposals, we are very pleased to be working with a world-class engineering firm such as Ausenco. Ausenco was also involved in the successful development at Atlantic Gold and the award of the GMP should give investors and potential project debt lenders greater confidence in the proposed schedule and initial capital cost to develop Blackwater on time and on budget.”

The 2020 prefeasibility study on Blackwater envisaged a three-stage development starting at 5.5 Mt/y from years 1-5, shifting to 12 Mt/y in years 6-10 and rising to 20 Mt/y in years 11-23. This would see gold production go from 248,000 oz/y to 420,000 oz/y, to 316,000 oz/y, respectively.