Tag Archives: Geoff Jones

GR Engineering to take on Woodlark gold process plant in PNG

GR Engineering Services looks like being rewarded for all of its hard work in Papua New Guinea (PNG) with the engineering, procurement and construction (EPC) contract for Geopacific Resources’ Woodlark gold project.

The ASX-listed mine developer says it has issued GR Engineering with an EPC letter of intent for the 2.4 Mt/y carbon in leach (CIL) process plant (modelled above), tailings line and other supporting infrastructure at the PNG project.

The final EPC contract is expected to be in the form of a guaranteed maximum price and will be signed following agreement of the final terms and conditions, Geopacific said.

“The company has selected an EPC contracting structure to de-risk the largest component of the capital expenditure requirement. Other remaining establishment capital costs also include site-based infrastructure and a mining fleet,” the company added.

In the meantime, Geopacific says it may instruct GR Engineering to commence an early works program to procure tenders and pre-order long lead time items such as the SAG and ball mills.

The processing plant will be constructed between the Kulumadau and Busai pits which are around 4 km apart. The project currently has 1 Moz in gold reserves, with significant upside from the 600 km² exploration licence, Geopacific said. The grade for the first five years is over 1.5 g/t Au with all-in sustaining costs estimated at A$866/oz ($586/oz).

GR Engineering is currently finishing off work on a crusher replacement project for Ok Tedi Mining in PNG.

Geopacific Managing Director, Ron Heeks, said: “GR Engineering has a strong reputation in successfully designing and constructing processing plants on time for a guaranteed maximum price. Geopacific is confident that their recent experience in PNG and strong track record in constructing similar projects will greatly de-risk the construction of Woodlark. We look forward to finalising the EPC contract, and advancing the development of Woodlark.”

GR Engineering Managing Director, Geoff Jones, said: “Our clients are increasingly seeking certainty and a track record of performance and GR Engineering has been able to demonstrate this to Woodlark, including by reference to its successful project outcomes in the turnkey design and construction of mineral processing plants in the gold sector.”

GR Engineering secures EPC contract with Tellus at the Sandy Ridge kaolin project

GR Engineering Services has entered into an engineering, procurement and construction (EPC) contract with Tellus Holdings Ltd for its Sandy Ridge kaolin project in Western Australia.

Tellus, a public unlisted infrastructure development company in the business of developing geological repositories that provide waste storage, recovery and permanent isolation solutions and complementary salt and clay products, says it is after a fully integrated facility for the long-term storage, recovery and permanent isolation of hazardous and intractable waste and an associated kaolin mining operation, some 75 km northeast of Koolyanobbing, in Coolgardie.

The contract price is around A$50 million ($36 million), with the works to be delivered under a guaranteed maximum price model, GR Engineering said.

The company’s scope of work under the contract includes the EPC and commissioning of the waste cell infrastructure, access roads, raw water supply and other key facility infrastructure for the Sandy Ridge underground waste facility.

The contract is expected to be carried out in two stages, with stage one comprising engineering and design and long-lead procurement activities for the work. This stage is anticipated to commence in the coming weeks, subject to the satisfaction of conditions precedent, which primarily relate to Tellus’ proposed financing facilities.

Stage two execution of the works is intended to commence mid-year, subject to Tellus satisfying additional conditions relating to the balance of the Sandy Ridge project approvals, GR Engineering said. Stage two includes mining of the first open-pit kaolin pit (waste cell), plus container yards, site warehouses and offices, roads, a 71-room accommodation village and associated services and utilities.

Tellus said the facility commissioning and full operations are scheduled from early-2020.

GR Engineering’s Managing Director, Geoff Jones, said: “We are pleased to progress this opportunity with Tellus, which has followed GR Engineering’s involvement to date in the Sandy Ridge project’s feasibility study and preliminary design work.”

In addition to this contract, Tellus has signed a circa-A$2 million PMC contract with Turner & Townsend providing project management services that support the Tellus owners team in managing all development phase contracts including the EPC contract (above); ancillary construction and equipment supply contracts; and key operational contracts.

Tellus is proposing to develop the Sandy Ridge facility, Australia’s first dual open-pit kaolin mine and arid near-surface geological waste repository in a 70 million-year-old kaolin clay bed with a 25-year operating licence. The proposal would involve mining up to 290,000 t/y of kaolin clay and receiving up to 100,000 t/y of Class IV and V waste at the facility gate over 25 years.