Tag Archives: Kiruna

LKAB to bring GHH LF-19EB tethered-battery electric loader to Malmberget

LKAB is set to add to its electric fleet at the Malmberget mine in northern Sweden after agreeing to acquire a LF-19EB tethered-battery electric loader from Germany-based GHH.

The manufacturer welcomed a team of LKAB team experts to its factory and testing ground in Gelsenkirchen, Germany, this month, with a successful Factory Acceptance Test of the LF-19EB taking place.

The LF-19EB is a 19-t-payload LHD initially designed for feeder breaker loading in the soft rock, salt and potash mining industries. It has a 34 kWh on-board battery for panel-to-panel electric tramming, with a tractive effort force of 380 kN and an average of 250 kVA under permanent load and 315 kVA peak. It has a maximum cable length of 310 m, which provides loading flexibility when plugged into the mine grid.

The loader heading to Malmberget has been upgraded for hard-rock applications with input from the customer, GHH says.

LKAB has tested and used several pieces of battery-electric equipment from different vendors at its Malmberget mine, while its Kiruna mine was among the industry’s earliest adopters of cable-electric loading, trialling its first Sandvik unit in 1985.

LKAB bolsters automated, electric Sandvik loading fleet at Kiruna iron ore mine

LKAB has ordered 12 Toro™ LH625iE cable-electric loaders and five Toro™ LH621i loaders, all equipped with Sandvik’s AutoMine® solution, for its Kiruna iron ore mine in northern Sweden.

The order will more than double Kiruna’s electric Toro LH625iE fleet to 20, all of which will now be automated, and its total Sandvik loader fleet to 28 by the end of 2025, the OEM said.

The orders were booked in the June and December quarters of 2023, with deliveries scheduled from January 2024 through the end of 2025. The investment follows a study by Sandvik’s Trans4Mine team and calculations by Polymathian that identified opportunities for Kiruna to increase production by as much as 15% through automation of its large electric loader fleet.

“Sandvik and LKAB have a shared goal to boost production at the Kiruna mine,” Magnus Backe, General Manager LKAB Kiruna, said. “This is a true partnership to increase tonnage and improve safety through automation.”

Developed in 2020 as a collaboration between LKAB and Sandvik to replace Kiruna’s ageing fleet of 17 Sandvik LH625E loaders, the 25-t-payload Toro LH625iE is a revamped version of the industry’s largest-capacity underground loader.

“This investment supports our strategy towards a more electrified, autonomous and safer mine,” Joel Kangas, Mine Manager at LKAB, said. “We need to excavate an enormous volume of rock from depths of up to 1,300 m, and we will mine even deeper in the future. These depths present a prohibitive ventilation challenge for conventional equipment of the size we need to meet production demands. We worked closely on a daily basis with the Sandvik experts on site to ensure a seamless implementation.

“Ever since we put the first Toro LH625iE straight into a production environment more than three years ago, these loaders have been the backbone in our production system, exceeding our expectations, and we look forward to incorporating these new automated units into our operation.”

Kiruna was among the industry’s earliest adopters of cable-electric loading, trialling its first Sandvik unit in 1985. The oldest of Kiruna’s Sandvik LH625E loaders was 13 years old and had more than 40,000 production hours when what began as a project to modernise the loader and a side project to enhance its cable reeling system ultimately evolved into a completely upgraded loader model with the latest technology and new components.

Sandvik collaborated closely with LKAB to customise the design of Toro LH625iE to meet Kiruna’s needs. These included better energy efficiency than the original model with the same payload capacity and a larger, more ergonomic operator’s cabin with a turning seat that swivels 180°.

Mats Eriksson, President of Sandvik Mining and Rock Solutions, said: “[The] Toro LH625iE has proven itself at the Kiruna mine, delivering an unrivalled production capacity of up to 500 metric tons per hour. Not only are these automated loaders extremely productive, they improve underground conditions and operator comfort with less heat, fewer vibrations and lower noise levels. Our partnership will create value for LKAB for years to come, and we look forward to continuing to support LKAB’s goals to mine more sustainably and productively.”

The Toro LH625iE is 14 m long and features a 4-m-wide, 9 cu.m bucket and an energy-efficient, IE4 classified electric motor to deliver a low cost per tonne. It connects to Kiruna’s mine network via a 350-m trailing cable that enables an operating range of up to 700 m.

LKAB-DurocRail

LKAB invests in Ore Railway supply chain in northern Sweden

LKAB is looking to shore up its iron ore rail operations in northern Sweden by acquiring a stake and investing in new facilities for Duroc Rail AB.

The iron ore company has acquired a 49% interest in Duroc Rail from the Nasdaq-listed Duroc AB group, which retains majority ownership of 51%. The preliminary purchase price is approximately SEK75 million ($6.9 million), with LKAB also agreeing to invest up to SEK200 million to build a new industrial property for Duroc Rail at Hertsöfältet in Luleå.

Duroc Rail is a certified operator with unique expertise in wheel maintenance for locomotives and wagons with experience of the climate in northern Sweden, LKAB says.

The Ore Railway runs between the port of Luleå and the port of Narvik, passing by the iron ore fields in northern Sweden. Almost half of all goods transported by rail in Sweden and Norway is currently being transported on the Ore Railway, with LKAB’s volumes accounting for the largest share.

For LKAB, the Ore Railway is an integrated part of the production system that starts in the mine and ends at the steel and mineral customers via the railway and ports. High capacity and availability of the Ore Railway and rolling stock in the form of locomotives and wagons is therefore business critical.

LKAB said: “The investment is a further step for LKAB to strengthen its capacity and flexibility to meet the growing challenges of the Ore Railway. In the past year alone, LKAB has invested in a new locomotive workshop in Kiruna, ordered 100 new wagons and started major work to modernise and upgrade the IORE locomotives used to transport iron ore, totalling an estimated value of SEK600 million.”

Linda Bjurholt, Logistics Manager at LKAB and CEO, LKAB Malmtrafik, said: “Duroc Rail has unique expertise in wheel maintenance for locomotives and wagons. LKAB is entering into this partnership to ensure that Duroc Rail remains and develops its operations in Luleå. They are part of a larger system and a prerequisite for efficient and predictable rail transport. Rail transport is completely dependent on effective maintenance of the railway wheels. This is important for LKAB and other railway operators today, and in the future.”

The wheel maintenance business was established in Luleå more than 100 years ago. Duroc Rail currently rents premises from SSAB on Svartön, in Luleå, but due to SSAB’s planned transformation from blast furnace to electric arc furnace operations, which requires access to more land, the lease will not be renewed. New buildings, equipment, certifications and other measures mean that the move will be a major investment.

John Häger, CEO Duroc AB, said: “Duroc Rail needs new industrial properties, and with LKAB as shareholder we can ensure development and capacity for the future, where we see that the green transformation that is taking place will require more efficient maintenance of wagon and locomotive wheels. We will therefore continue to invest and develop our offering for all customers in the region. We are pleased that our more than 100-year-old company with 50 employees in Luleå will continue to develop.”

Within Business Area Special Products, LKAB is developing new businesses in addition to the iron ore production, such as industrial minerals for external customers, as well as key services such as concrete, drilling, explosives, rock work, mechanical-engineering services and maintenance for LKAB’s own operations.

Leif Boström, Senior Vice President Business Area Special Products, LKAB, said: “LKAB’s long-term strategy is to secure key services and products for efficient, safe, and sustainable operations. We work with partnerships and subcontractors, but also by developing or acquiring companies that have specific expertise, for example in managing supply risks. Duroc Rail is an important investment for us, it is a well-managed company with good development potential in several areas and will be an important part of LKAB.”

The transaction is formally subject to the completion of the property transfer for the new industrial property, which is expected to take place before the end of the year.

Epiroc equipping LKAB Kiruna personnel with new Mobilaris safety solutions

LKAB is further increasing its safety capabilities by implementing several solutions from the Mobilaris Mining Intelligence platform at its Kiruna mine in northern Sweden, Epiroc says.

The platform, now 100% incorporated into Epiroc following the consolidation of its ownership in Mobilaris MCE AB in 2021, allows all employees to receive alarm and crisis information and confirm directly on their mobile phones in an emergency situation, Epiroc says. Employees can also obtain position support and the ability to navigate faster to rescue chambers with the help of applications on their mobile phones.

This means rescue personnel will now have the tools and means to manage emergencies better and faster, according to the OEM.

Joel Kangas, LKAB’s Kiruna Mine Manager, said: “We want to shorten the time from when an alarm goes off to when everyone is safe, and we believe this digital solution can help us with that.”

Hans Wahlquist, Global Director of Product Management at Epiroc, said: “LKAB already has a high level of safety, but now there are new technologies and new opportunities, and they have the infrastructure required for this installation. This project will give everyone in the mine more information about the situation in real time.”

LKAB is setting a new world standard for mining where digitalisation forms an important step towards easier, safer and more efficient work in the mine. The mobile safety solution project is a collaboration between LKAB and Epiroc, involving both existing products from Epiroc and new developments. The project began in the autumn of 2022 and the goal is to start rolling out the solution in the spring of 2023 at the Kiruna mine.

Andreas Ericson, General Manager Epiroc Mining Intelligence, said: “Collaborations with customers are crucial for finding innovative solutions. This project demonstrates the potential for digital transformation in the mining industry, bringing us one step closer to a smarter and more efficient future.”

The following four modules from the Mobilaris Mining Intelligence portfolio are included within the project:

  • Location of people with the ability to receive alarm and crisis messages on their mobile phones through Mobilaris Situational Awareness and Mobilaris Virtual Tag;
  • Distribution of emergency messages and support provision for getting people to safety through Mobilaris Emergency Support;
  • Three dimensional map in vehicles for navigation assistance, increased traffic safety and the ability to quickly find the nearest rescue chamber through Mobilaris Onboard; and
  • Three dimensional map on the employee’s mobile phone for navigation assistance and the ability to quickly find the nearest rescue chamber through Mobilaris PocketMine.

Epiroc makes the ‘impossible possible’ with launch of Boltec ABR

Epiroc has taken another significant step forward in its rock reinforcement automation journey with the release of the Boltec Auto Bolt Reload (ABR).

Combining the company’s ground support nous with its mechanisation and automation knowledge has resulted in a solution able to remove operators from the front end of the bolter – where personnel are most at risk of rock falls from unsupported ground – and increase bolting productivity, especially in poor ground conditions.

With mining operations steadily going deeper as they develop existing and newly discovered orebodies, the rock stresses associated with mining these orebodies are typically increasing, too. This often results in more challenging rock conditions with fractured rock mass, rock burst and squeezing ground, requiring more regular rehabilitation work. The Boltec ABR, with improved operator safety, flexibility and productivity, is the obvious choice for such conditions, Epiroc says.

Epiroc claims the Boltec ABR is the first ever underground rock reinforcement drill rig designed in such a way that the bolt type and machine work together in synergy to deliver optimal safety, performance and quality. The machine can also be equipped with a mesh delivery system.

This synergy also leads to improved accuracy in bolt installations and a reduced need for re-bolting, according to Peter Bray, Global Product Manager, Rock Reinforcement at Epiroc’s Underground division.

“By using a Boltec ABR, you are better able to install bolts and mesh correctly with high quality, reducing the need for re-bolting, re-meshing…and rehab work in the future,” he told attendees of a webinar announcing the product launch today.

The mechanisation of the bolting process – in tandem with the use of self-drilling anchors (SDAs) and pumpable resin – should provide operations with the comfort to follow recommended bolting patterns, reducing the need for the installation of additional bolts that go above and beyond optimal industry practice.

The main design feature of the Boltec ABR is the fully mechanised bolt reloading system. The system automatically feeds bolts from a large carrier magazine – able to hold 44 bolts in 2.4-m or 3-m lengths – to the feed magazine – able to hold eight bolts – all while the operator remains safe inside the cabin. This innovation removes the need for manually reloading the feed magazine, thereby reducing the associated risk to the operator.

The fast auto reloading sequence speeds up the production cycle, with a total of 52 bolts able to be installed in a heading before manual reloading of the carrier magazine. The carrier magazine is mounted on a swing arm that lowers the magazine to ground level for easy reloading behind the machine’s front support jacks – where ground support should already be in place.

Productivity can be further boosted with the operator carrying out the reloading process when bolting is being carried out in multi-bolt auto mode, according to Bray.

The Boltec ABR opens the door to other safety and productivity-enhancing autonomous functionalities previously not compatible with underground bolting machines, according to Epiroc. Tele-remote control and the aforementioned multi-bolt auto are now available options that can provide bolting potential during shift changes or when conditions preclude having an operator physically on the machine. The machine is also available with a battery-electric driveline.

Bray said the development and integration of SDAs and pumpable resin on conventional Boltec machines have been integral to achieving this new functionality.

“If you think about our face drills and long hole production rigs, they have had automation for many years,” he said. “There hasn’t been a mechanical reason why we couldn’t automate a bolting machine; the stopping point has been the type of legacy rock bolts used.”

SDA bolts, which, according to Epiroc, offer faster bolting times and higher quality installation, are not sensitive to varying conditions and will achieve consistently fast installation. This provides easier scheduling accuracy for mine planning and forecasting.

The pumpable resin, developed to address inconsistent and unreliable bolt installations as mines go deeper and rocks become less competent under added pressure, offers fast setting times and full bolt encapsulation, ensuring speed and quality of installation, the OEM says. An added plus is the resin’s insensitivity to wet ground conditions, which can be a desirable characteristic for many deep underground operations.

“Given that it is much cleaner and easier to use than traditional cement, the pumpable resin reduces hours spent on cleaning the machine,” Bray said. “Hence, it is increasing productivity by providing more bolting time.”

Like other Boltecs in the range, the Boltec ABR comes with a boom-mounted bolting system, providing flexibility in terms of coverage and bolt installation angles, according to Bray.

“It’s very rare that you have perfect straight drive profiles in underground mining,” he said. “The boom-mounted bolting system offers the flexibility to address this.”

LKAB, along with the European Institute of Innovation & Technology, have been key partners in the development of this machine, with the prototype tested out at both the Kiruna and Malmberget mines in northern Sweden.

Kiruna suffered a significant seismic event during May 2020 where several areas underground were adversely affected, providing a good test case for the new machine.

These affected areas required rehabilitation with bolts and mesh to make them safe for production again, according to Bray – a process the iron ore miner is continuing to carry out at Kiruna with the prototype Boltec ABR unit.

“The Boltec ABR was the perfect machine for the challenge; it has proven to allow safer operation and significant productivity increases when compared to LKAB’s conventional bolting fleet,” he added.

Epiroc said that up to double productivity gains were achieved in a trial with the Boltec ABR in LKAB’s Malmberget mine when compared with the miner’s conventional bolting fleet.

Bray concluded: “This solution has made the impossible possible. We can now install bolts where it used to be extremely difficult. Giving some relief to the bottleneck that rock reinforcement had become.”

Orica’s wireless blasting tech overcomes magnetite challenges at LKAB Kiruna

A four-year collaboration between Orica and LKAB has resulted in the first production blasts using wireless initiation technology at the Kiruna iron ore mine in northern Sweden.

These blasts – charged in the middle of May and blasted in early June – are going some way to support LKAB’s safety, productivity and long-term automation objectives, according to Abhisek Roy, EMEA Head of Marketing for Orica.

It has involved an extensive amount of work to get to this blasting milestone, according to Ingemar Haslinger, Technical Services Lead Europe at Orica.

He explained: “It all started in 2018 when LKAB showed interest in our new WebGen™ wireless technology. They could see the benefits in both safety and productivity with the new way of producing the ore.”

This saw Orica go to site at the Kiruna mine in March 2018 to begin with a signal survey, testing if the company could obtain a good signal between the antenna and the in-hole receivers.

WebGen provides for groups of in-hole primers to be wirelessly initiated by a firing command that communicates through rock, water and air. This removes constraints often imposed by the requirement of a physical connection to each primer in a blast. The wireless blasting system not only improves safety – by removing people from harm’s way – but improves productivity – by removing the constraints imposed by wired connections.

It is, therefore, considered, a critical pre-cursor to automating the charging process.

To this point, WebGen has fired over 100,000 units in over 3,000 blasts globally across customer sites, Orica says.

At Kiruna, however, the process from testing to technology on-boarding was less than straightforward.

“In the area of the mine where the signal survey was completed in 2018, it was discovered that the signal could not penetrate the magnetite ore at all,” Haslinger said. “This was the first time we had encountered this and was a setback for Orica and LKAB.”

At that time, Orica did not have the localised field equipment or advanced diagnostic tools to diagnose the antenna issue, making it difficult to ascertain the root cause.

“We had to go back to our global WebGen specialists and try to understand why this was happening, which we were successfully able to do,” Haslinger said.

After dedicated work from the global team, Orica went back to Kiruna in September 2020, looking to replicate the signal survey from 2018 and use its advanced diagnostic tools to measure the antenna performance and output.

“We also had the opportunity to test the signal behaviour in the holes, as well as measure the rock properties around the antenna and the in-hole receivers,” Haslinger added.

The survey proved successful, explaining why the signal could not go through the orebody. This allowed the global WebGen team to start developing solutions to overcome the signal problem, which it was able to do in short order.

In December 2020, the Orica team was back at the underground iron ore mine to test the new solution.

“The first trials with the new solution showed positive results and the global team continued to develop that further,” Haslinger said. “In May 2021, we tried the solution in many different conditions and applications to be sure that it would work in the mine. These trials gave us a lot more knowledge about the environment and how the new solution worked.

“In 2022, we were ready to test the system in active mine operations and it has been an extensive amount of work to get us to that point.”

Development of the WebGen wireless underground blasting technology is ongoing at the Kiruna mine

Michal Gryienko, Engineer at LKAB in Kiruna, said the first two production rings were charged using WebGen in the middle of May before blasting occurred in early June. This is one of the benefits of the system, with the wireless primers able to sit dormant in the blasting profile for around 30 days prior to blast initiation.

“The results look good so far,” Gryienko said. “In total, we will blast five production rings, and the final three are planned to be blasted in September.”

Among the benefits Gryienko highlighted were the reduction in risk associated with hole priming and the possibility of detonating more blast holes due to the ability overcome damaged or unstable blasting applications.

Orica’s Roy said the collaboration between the two companies has been “fantastic”.

“Despite the challenges around transmission of signal across the magnetite orebody that is a prerequisite for a successful wireless initiation, both companies have worked as partners for the last four years, finding practical and creative solutions,” he said.

“This hopefully is the start of a long-term sustainable wireless blasting solution that supports LKAB’s safety and productivity objectives and long-term automation goals.”

LKAB starts core logging automation, digitalisation process with Minalyzer CS

LKAB has become the first iron ore miner in the world to implement the continuous XRF scanner Minalyzer CS, starting the process of automating and digitalising its drill core logging workflow.

By collecting data in an automated system, LKAB is aiming to improve the consistency and efficiency of its core logging process, Minalyze said.

LKAB and Minalyze initiated the collaboration in March 2020 when the first scanner was installed at the Kiruna iron ore mine for a test. It was then expanded to Malmberget where data from the Minalyzer CS was used to help geological logging of the drill core. The focus for the tests was to assess the datasets: geochemistry, high resolution images, RQD and specific gravity generated by the scanner and to determine how these datasets can assist in the core logging process.

Following these developments, the two companies plus Sentian, in May 2021, said an artificial intelligence application developed by the trio would be trialled to make drill core analysis faster, with the time to evaluate a drill core reduced from weeks to minutes, with increased accuracy.

LKAB Senior Vice President Exploration, Strategy and Business Development, Pierre Heeroma, said: “The tests with the Minalyzer in Kiruna and the more complex Malmberget geology confirmed that this Swedish technology is disrupting the core logging process – now we have fast access to rich data as guidance when classifying the rocks. Our core logging is now consistent and efficient.”

Annelie Lundström, CEO Minalyze AB, said: “The rest of the iron ore industry should closely follow the transformation LKAB is undergoing. With the Minalyzer they have one of the more automated and digitalised core logging workflows in the world. And they are setting a new world standard for sustainable mining with the fossil-free iron ore and steel making.

“We are very proud to be part of LKAB’s transition into the future.”

LKAB to boost remote drilling operations with new Epiroc Boomer, Boltec and Simba rigs

Epiroc says it has won a large order for a variety of underground mining equipment including Boomer face drilling rigs, Boltec rock reinforcement rigs and a Simba production drilling rig from LKAB in Sweden.

LKAB, Europe’s largest iron ore producer, is set to use the rigs at its Malmberget and Kiruna underground iron ore mines in northern Sweden. The order is valued at SEK105 million ($12.2 million) and was booked in the third (September) quarter of 2021.

“Epiroc and LKAB have a long history together as partners around innovative technologies, always aimed at optimising operations in the most productive and sustainable way,” Epiroc’s President and CEO, Helena Hedblom, said.

The machines include many advanced automation features, according to Epiroc.

For example, the Simba production drill rig will be operated remotely from a control room in the Kiruna mine. This rig adds to LKAB’s existing fleet of six Simba production drill rigs that are remotely controlled from the control room and two that are remotely controlled in the mine environment.

One of the Boltec machines (an example pictured) will also be equipped with a new automated pumpable resin system, a key component in Epiroc’s automated bolting development. All the machines come with Epiroc’s telematics system Certiq, which allows for intelligent monitoring of machine performance and productivity in real-time.

LKAB to trial AI-backed XRF drill core logging with help of Minalyze and Sentian

LKAB, Minalyze AB and Sentian say they have joined forces in a consortium to develop the latest technology for scanning drill core.

In March 2020, LKAB started a test with the Minalyzer CS drill core scanner where the goal was to improve the workflow for core logging – ie how the results of exploration drilling are analysed. The test led to a permanent installation in Kiruna (Sweden) and expansion to Malmberget where data from the Minalyzer CS is used to help geological logging of the drill core.

The consortium of LKAB, Minalyze and Sentian are now set to take the use of data to the next level when boreholes in LKAB’s deposits are to be investigated. The new artificial intelligence application being developed by the trio will make the analysis much faster, with the time to evaluate a drill core reduced from weeks to minutes, with increased accuracy.

This could see Minalyze’s X-ray Fluorescence-backed CS scanner analyse LKAB drill core while leveraging Sentain’s industrial artificial intelligence solutions to make real-time decisions relating to drilling and exploration activities.

The technology development driven by the consortium will be a world first, changing the entire industry, the companies say.

Jan-Anders Perdahl, Specialist at LKAB’s Exploration Department, said: “With the collaboration, the core logging takes a big step through machine learning and artificial intelligence. The geologist can, at an early stage, place greater focus on the parts of the core that show chemical or other changes. Opportunities are opened up to gain increased knowledge about ore formation processes and alterations in a completely different way than before. One can also get indications that you are close to mineralisation and where it may be located, and thereby streamline exploration.”

The technological leap will give LKAB’s staff increased competence, increased quality in and efficiency of the work, as well as reduced need for other analysis methods, according to the companies.

Annelie Lundström, CEO of Minalyze AB, said: “We are at an interesting time when the hardware to extract consistently high-resolution data from drill cores is available and we can now take the next step and generate value from data together with our customers. In this collaboration, we will develop algorithms that can map rock layers in so-called lithological logs with very high confidence. This can only be done by combining expertise from all three parties.

“The results from our collaboration will forever change how drill core logging takes place everywhere and will result in a more efficient, non-subjective and consistent process.”

Martin Rugfelt, Sentian CEO, added: “We see great power in the application of modern artificial intelligence to data from the mining industry and there is major potential in further combining our machine learning technology with Minalyze’s unique capabilities in data collection and analysis.”

LKAB welcomes more autonomous LHDs at Kiruna ahead of electric machine arrivals

LKAB says it is now running six autonomous LHDs at its Kiruna iron ore mine, in northern Sweden, with battery-powered and cable-electric machines set to arrive at the operation later in the year.

The company has been stepping up its automation efforts at the underground mine, going from three autonomous loaders in November to five in December and, now, six as of this month.

These loaders have come from both Sandvik and Epiroc, with at least three of these being 21 t Sandvik LH621i LHDs and two being 18 t Epiroc Scooptram ST18 LHDs.

“For the time being, the loaders are diesel-powered, but battery-powered Epiroc machines and Sandvik’s larger electric loaders will be delivered this year,” the company said. “Safety and loading capacity will be tested and assessed, so that the vision of a carbon-dioxide-free LKAB can be realised.”

Magnus Lindgren, Production Manager for the remote-control centre at level 1365 in the Kiruna mine, said: “Our operators work in close collaboration with both Sandvik and Epiroc and, thereby, take part in these suppliers’ development. We test the systems and provide feedback, so we can eventually take delivery of a better product.”

LKAB conducts blasting at the mine each night. When the blasting gases have been evacuated and rock stresses have decreased, personnel can access the production area. With remote-control machines, LKAB can load, haul and dump crude ore without having to worry as much about these considerations.

Roger Lärkmo, Engineering Developer at LKAB, added: “Autonomous loading at night is optimal in terms of both safety and work environment, and from a productivity perspective. That doesn’t mean manually-operated machines are a thing of the past; it just means that we have more tools in the toolbox. Many parameters have to be taken into the equation for our loading operations to deliver an even flow of ore to the processing plants.”

This summer, the Konsuln mine will take delivery of its first battery-powered loader, the 14 t ST14 from Epiroc. Epiroc said last month it will also deliver a Minetruck MT42 Battery for use at the main Kiruna iron ore mine for production, and in the Konsuln test mine.

Preparations are now under way for the ST14 Battery’s arrival at Konsuln, from planning of the drifts where batteries will be exchanged, to risk analyses and simulations, LKAB said.

During 2021, three of Sandvik’s larger 625IE electric loaders, which have a 25-t payload capacity, will also be delivered to LKAB in Kiruna. The company took delivery of a “renewed” Sandvik LH625iE electric loader for field testing in 2020.

Lindgren said: “LKAB has been running loaders with electric power cables for more than 20 years, both manually operated and with remote control. Now we are going to test the new generation of electric loaders. These tests will begin in the autumn.”

Anita Oraha Wardi, Project Manager for autonomous, smart and carbon-dioxide-free machines at LKAB, said the company was participating in development work early on, so it can understand and influence performance, loading capacity and, not least, the safety aspects.

“We are going to test to see how battery-driven and electric loaders compare with diesel-powered machines, and how remote-control machines function in comparison with manually-operated loaders,” she said.

“One of several objectives is that operators, regardless of the make or model of the vehicle, should be able to run remote-control vehicles via the same system and in the same production area. Then, we will be approaching a world standard.”