Tag Archives: Lycopodium

Monadelphous Group adds to construction pipeline with Rio Tinto, BHP contracts

Engineering company Monadelphous Group Limited has been awarded new construction contracts in the iron ore and renewable energy sectors, with the revenue contribution attributable to Monadelphous expected to total approximately A$340 million ($225 million).

In iron ore, Mondium, the company’s engineering, procurement and construction joint venture with Lycopodium, has been awarded a design and construct contract by Rio Tinto for a new sampling facility at a port operation in the Pilbara region of Western Australia, with work expected to be completed in mid-2026.

In addition, Monadelphous has been awarded a multidisciplinary construction contract under BHP’s WAIO Asset Panel Framework Agreement associated with the dewatering of surplus water from Orebody 32 in Newman, Western Australia. Work is expected to be completed in the second half of 2025.

Zenviron, the company’s full-service balance-of-plant renewable energy joint venture with ZEM Energy, has, meanwhile, secured a contract with CS Energy, a Queensland State Government owned body, for the delivery of the Lotus Creek Wind Farm in Central Queensland.

Lycopodium engaged by Barrick for Lumwana copper expansion study

Lycopodium has been awarded a contract from Barrick for the feasibility study and basic engineering for the expansion of its Lumwana copper mine in Zambia.

The study and basic engineering contract is valued at approximately A$19 million ($12.5 million), with the project having a capital cost investment of almost $2 billion. Work has commenced, with the accelerated development program targeting completion of the feasibility study by the end of 2024 and expanded process plant production anticipated in 2028.

The expansion of the mine will increase Lumwana’s annual production from 150,000 t of copper at a 26-28 Mt/y process plant production rate, to an estimated 240,000 t of copper at a 50 Mt/y process plant production rate, with an estimated 36-year mine life.

Lumwana is a conventional open-pit (truck and shovel) operation, about 100 km west of Solwezi in Zambia’s Copperbelt. Lumwana ore, which is predominantly sulphide, is treated through a conventional sulphide flotation plant, producing copper concentrate.

Lycopodium Limited’s Managing Director, Peter De Leo, said: “The expansion of Lumwana within Zambia’s world-class copper region supports the country’s commitment to its copper industry, and we are very pleased to have the opportunity to continue our partnership with Barrick and be part of this significant development that will have a material impact on the Zambian economy.”

This engagement follows the award earlier this year of the feasibility study and basic engineering contract for Barrick’s Reko Diq copper-gold project in Pakistan.

West African secures Lycopodium and Metso Outotec mills for Kiaka gold project

West African Resources Limited is heading towards construction at its 90%-owned Kiaka gold project in Burkina Faso, having registered strong funding interest, awarded an engineering, procurement and construction management (EPCM) contract and booked the mill package for the development.

Kiaka, an asset with 7.7 Moz of reserves and resources on its books, is the company’s second gold mine in the country on top of its operating Sanbrado asset.

WAF’s feasibility study, released in August 2022, outlined pre-production capital costs of $430 million and a 2.5-year pre-tax pay back at a $1,750/oz gold price for the project. Kiaka was expected to operate over an 18.5-year life of mine, producing, on average, 219,000 oz/y of gold (on a 100% basis).

West African Executive Chairman, Richard Hyde, said strong competitive bids from its debt finance process supported the company’s targeted debt of $300 million for the project.

In the meantime, WAF has signed a notice of award with Lycopodium based on the engineering company’s priced proposal for the EPCM of a new carbon-in-leach treatment plant for Kiaka. This award incorporated Lycopodium’s early commencement of the engineering and procurement portion of the contract to complete the engineering and tendering of the long-lead mill package.

Lycopodium was also the contractor on the Sanbrado construction project.

In line with this, Lycopodium and WAF have undertaken a competitive tender process for the supply and delivery of the SAG and ball mill package for Kiaka.

Following the evaluation of tenders, the company selected Metso Outotec to supply the 18 MW SAG mill and 9 MW ball mill. Metso Outotec also provided the SAG and ball mills at Sanbrado (construction of the comminution circuit, pictured). WAF has signed the order with Mesto Outotec, which contains a firm pricing and delivery schedule for the mill package components that fits well into the Kiaka construction schedule, it said.

The mining company says it has mobilised earthworks equipment to the Kiaka project site. The initial areas to be cleared include the permanent camp area and the process plant area. Access road upgrades are also planned to be undertaken during the current dry season.

The construction schedule for Kiaka remains on track, with major works expected to commence in the March quarter and first gold in 2025.

WAF says it also remains on target to meet 2022 production and cost guidance of 220,000-240,000 oz of gold produced at an all-in sustaining cost of less than $1,100/oz.

Rio’s WTS2 iron ore project hits first ore milestone, Mondium says

Mondium says first ore has been achieved at Rio Tinto’s Western Turner Syncline Phase 2 project (WTS2) in Western Australia.

Rio Tinto awarded Perth-based Mondium a A$400 million ($276 million) contract to design and construct the mine in early 2020. This saw the company, a joint venture involving Monadelphous and Lycopodium, undertake all engineering and design, procurement and site construction works associated with the WTS2 development, including the process plant, overland conveyor and non-process infrastructure.

Celebrating the achievement, Mondium said it was a significant achievement for its EPC team, Rio Tinto and delivery partners.

It added: “593 days and more than two million site hours worked culminated in the first loader bucket tipping high-grade ore into the WTS2 run of mine bin. Forty minutes later, the ore was discharged to the WTS1 belt and delivered to the Tom Price stockpiles.”

Back in November 2019, Rio said it would invest $749 million in the development of WTS2 at its Greater Tom Price operations, facilitating mining of existing and new deposits and including construction of a new crusher as well as a 13 km conveyor. In addition to this, the haul truck fleet at the mine would be fitted with Autonomous Haulage System technology to enable autonomous haulage. This fleet has since been commissioned.

Lycopodium builds on Talison Lithium relationship with CGP3 EPCM contract

Lycopodium says it has been awarded the engineering, procurement and construction management (EPCM) services contract for Talison Lithium Australia’s Chemical Grade Processing Plant #3 (CGP3), to be developed at its Greenbushes site in Western Australia’s southwest.

Talison Lithium and its predecessor companies have been producing lithium minerals from the Greenbushes lithium operations since 1983, with the area recognised as the longest continuously operated mining area in Western Australia (circa-1888).

The mining and processing operations at Greenbushes have been upgraded and expanded over the decades to increase production and incorporate new technologies as demand for lithium minerals has grown.

The development of this third chemical grade lithium processing plant at Greenbushes will enable Talison to continue to supply the downstream lithium processing facilities of its shareholders currently being established in Western Australia and its facilities in China, Lycopodium says.

Lycopodium’s EPCM services on CGP3 incorporate engineering and design, including earthworks, civil, structural, mechanical, piping, electrical and instrumentation, as well as providing overall project management, including procurement and contracts management, expediting logistics and materials management, and construction and commissioning management services through handover of operational facilities to Talison Lithium.

Lycopodium is very familiar with the Greenbushes site and has an established relationship with Talison Lithium in the development of its Greenbushes operations including the previously awarded EPCM services for the new Mine Services Area project where Lycopodium is currently in the detailed engineering design, critical equipment procurement and pre-mobilisation phase for the project.

Lycopodium’s incorporated joint venture with Monadelphous (Mondium) is also currently delivering the Tailings Retreatment project at the mine.

Lycopodium Limited’s Managing Director, Peter De Leo, said: “We have been working in partnership with Talison for a number of years now, and having supported them through the development phases to optimise the CGP3 project, it is very pleasing to see it is now progressing to implementation.”

Talison Lithium is owned by two companies under a joint venture arrangement Tianqi Lithium Corp/IGO Limited JV (51%) and Albemarle Corporation (49%).

Roxgold lays Séguéla groundwork with Metso Outotec, Lycopodium contract awards

Roxgold says it has awarded a SAG mill order for the Séguéla gold project in Côte d’Ivoire to Metso Outotec as part of its efforts to advance the project through to construction in the coming months.

The move comes ahead of the release of feasibility study on the project next month, which will build on a 2020 preliminary economic assessment (PEA) that outlined an operation capable of delivering over 100,000 oz/y of gold over eight years at average all-in sustaining costs of $749/oz. This study also incorporated a single stage primary crush/SAG milling comminution circuit with 1.25 Mt/y throughput.

At the same time as selecting Metso Outotec for the SAG mill contract, Roxgold has awarded preferred contractor status to Lycopodium Minerals Pty Ltd and is currently negotiating the engineering, procurement, and construction (EPC) agreement with the company for the 1.25 Mt/y carbon-in-leach processing facility and other supporting infrastructure to be constructed at Séguéla.

The fixed price agreement increases confidence in the total capital cost for the project, as it is by far the largest scope at Séguéla, Roxgold said.

“With this agreement in the final stages of negotiation and several other key scopes now tendered and priced, approximately 65% of the pre-production capital estimate has now been fixed or finalised,” the company added. “This level of detail provides increased confidence around the pre-production capital estimate, which is expected to be in-line with the previous estimate of $142 million, as outlined in the PEA.”

In terms of progressing work on long-lead time items, Roxgold said it had awarded the plant site bulk earthworks tender, with a contract expected to be executed and works commenced in the June quarter to support the project critical path.

The company has continued to advance its early works program at site including upgrading of the site access road and construction of the accommodation village. Contracts were awarded for camp bulk earthworks and camp construction, with first concrete poured last month, it said.

Surveying has been completed for the 33 kV and 90 kV power lines to tie into the existing 90 kV transmission line running across the property, which is connected to the 225 kV ring main system around the country. These early work activities will enable a rapid ramp up to full construction upon completion of the feasibility study and mine financing in the June quarter of this year.

Roxgold says it has undertaken a competitive tender process and has conducted a detailed assessment of the contract mining proposals received. It is currently completing diligence on the shortlisted parties and plans to award the mining contract later this year to allow for contractor mobilisation, site establishment,and commencement of pre-production mining early next year.

John Dorward, President and Chief Executive Officer, said: “The Séguéla project has rapidly become a cornerstone asset for Roxgold, and we believe that the project will provide significant value to all our stakeholders.

“The feasibility study is on track to be announced in the second (June) quarter, which we believe will demonstrate the ongoing evolution of the Séguéla PEA with an enhanced mine life and project economics with the inclusion of the high-grade Koula deposit into the mine plan.”

Sila Equipement to take on contract mining task at Orezone’s Bomboré gold project

Orezone Gold Corp has selected Sila Equipement ET BTP SA as its open-pit mining contractor for the Bomboré gold project in Burkina Faso.

This follows the January appointment of Lycopodium Minerals Pty Ltd as the lead EPCM contractor for the project.

Sila, a Burkinabé company, will initially have a contract scope that covers the mining of the Off-Channel Reservoir (OCR) pit, as well as the upfront establishment of mine site services (maintenance workshops, wash bays, warehouse, ablutions and accommodations, offices, and communications), the clearing and grubbing of the OCR footprint including topsoil relocation, as well as pit dewatering and haul road maintenance.

Orezone said mining of the OCR is an important milestone given that the pit will serve as the main water storage facility during operations.

“The mobilisation of Sila will ensure that the OCR and its related infrastructure will be ready well in advance of the onset of the 2022 rainy season,” the company explained.

Orezone says it is working in partnership with Sila to finalise certain key terms under the long-term mining contract.

Patrick Downey, President and CEO, said: “With the project financing now in place, we are rapidly advancing the engineering, procurement, and construction of the project. The early award of the mining contract will allow our project to remain on schedule.

“I am pleased that Sila, a local contractor, has been awarded this work which speaks to the depth and continued growth of the mining service industry in Burkina Faso. The company’s selection of Sila was made after a competitive tender and due diligence process including a review of safety and operational performance in free-dig oxide operations such as Bomboré. Sila has demonstrated an excellent track record in other similar Burkina Faso mining operations.”

He added: “The proposed mining fleet is brand new equipment and will be operated by Sila’s highly experienced senior operations and maintenance team.”

Since the recent appointment of Lycopodium in January as the EPCM contractor, the company says it has rapidly advanced engineering and procurement activities, and made significant progress on refining the project construction timeline. The company’s key procurement and site-based activities in the upcoming months will be focused on the following:

  • Pre-production mining to commence in March 2021;
  • Ball mill order (a critical long lead item) to be placed in March 2021;
  • Award of power plant contract in March 2021; and
  • Site-wide bulk earthworks to commence April 2021.

Orezone makes Bomboré headway with Lycopodium EPCM award

Orezone Gold is moving closer to the construction phase at its 90% owned Bomboré project in Burkina Faso after awarding an EPCM contract for the gold asset, completing a Phase I Resettlement Action Plan (RAP) with nearby communities, and making progress on awarding both mining and power plant Build-Own-Operate contracts.

The company has awarded the engineering, procurement, and construction management contract to Lycopodium Minerals Pty Ltd, a company, Orezone says, has an excellent track record of delivering projects on time and on budget in West Africa.

When it comes to the Phase 1 RAP, Orezone said all villages and infrastructure have now been completed.

“Relocation of households is proceeding smoothly with relocation substantially complete,” it noted. “This opens access to all areas required for the preparation of the process plant, surface infrastructure, and key mining areas including the off-channel reservoir and tailings storage facility.”

Alongside this work, Orezone has undertaken a competitive tender process for the contract mining agreement at Bomboré, including bidder site visits and a detailed assessment of proposals received.

The company plans to award the open-pit mining contract in early 2021 to allow for contractor mobilisation, site establishment, and commencement of pre-production mining by the end of the March quarter.

Bids for the Build-Own-Operate power plant, meanwhile, have recently been received from companies specialising in providing power solutions in West Africa, Orezone said. The company expects to award this contract in the current quarter.

Orezone’s 2019 feasibility study on Bomboré envisaged a 5.2 Mt/y throughput operation able to produce, on average, 117,760 oz of gold over a 13-year mine life where both oxide and sulphides would be mined and processed.

The company said negotiations for conventional project debt covering a major portion of the initial project construction budget of $153 million were advancing “rapidly and smoothly”, with expectations of binding debt commitments being announced later this month.

As currently planned, first gold is scheduled for early in the September quarter of 2022.

Patrick Downey, President and CEO, said: “Awarding the EPCM contract to Lycopodium is a key step to ensure the continued successful development and construction of the Bomboré project. With more than 12 mines built in West Africa, Lycopodium’s track record of building efficient mines on time and on budget is unparalleled.

“Lycopodium is very familiar with Bomboré, having performed the 2018 Feasibility Study, the 2019 Updated Feasibility Study, and the previously completed front-end engineering and design.”

Downey said Lycopodium will be able to immediately build on its past work and progress the project in a cost effective and timely manner.

Mondium secures WTS2 iron ore contract from Rio Tinto

Rio Tinto has awarded Perth-based Mondium a A$400 million ($276 million) contract to design and construct the Western Turner Syncline Phase 2 (WTS2) mine in the Pilbara of Western Australia.

Mondium, a joint venture involving Monadelphous and Lycopodium, will undertake all engineering and design, procurement and site construction works associated with the WTS2 development, including the process plant, overland conveyor and non-process infrastructure.

Back in November, Rio said it would invest $749 million in the development of WTS2 at its Greater Tom Price operations, facilitating mining of existing and new deposits and including construction of a new crusher as well as a 13 km conveyor. In addition to this, the haul truck fleet at the mine will be fitted with Autonomous Haulage System technology to enable autonomous haulage from 2021.

Mondium’s work is expected to create 450 jobs starting in the March quarter, with completion slated for 2021. Rio said Mondium and it would work closely to ensure the contract provides local and Indigenous employment as well as business opportunities in the region.

Rio Tinto Iron Ore CEO, Chris Salisbury, said: “We’re committed to supporting WA businesses, buying locally and supporting our communities through the creation of jobs. We’re pleased to award this contract to Mondium who share those values.”

Mali Lithium enlists Lycopodium for Goulamina spodumene DFS

Australia-listed Mali Lithium has appointed Lycopodium Minerals Pty Ltd to complete the definitive feasibility study (DFS) for the Goulamina lithium project, in Mali.

A July 2018 prefeasibility study on Goulamina outlined an open-pit hard rock mining operation with a 2 Mt/y concentrating plant. The project was scoped to produce 362,000 t/y of 6% Li2O spodumene concentrate over a 16-year mine life.

Mali Lithium, formerly Birimian, said Lycopodium was an obvious fit for Goulamina given the over 25 years of experience the company had with the development and execution of projects in Africa. “Lycopodium is a recognised leader in the delivery of mining projects with an exceptionally strong capability in the development of projects in West Africa,” the company added.

In Africa in the past two years alone, Lycopodium has designed, constructed and commissioned seven greenfield projects, and is also currently developing a further three process plants, according to Mali Lithium.

“Lycopodium’s appointment for this critical piece of project development work is testament to both the company’s commitment to, and the prospectivity of, the Goulamina lithium project,” Mali Lithium said, adding that its own in-house team will work closely with Lycopodium to develop the DFS.

Mali Lithium Managing Director, Chris Evans, said: “We are pleased to have secured a company of Lycopodium’s calibre, with a proven track record of delivering important pieces of work like the Goulamina DFS in a timely and efficient manner.

“We look forward to working closely with Lycopodium over the coming period and we are excited by what the outcomes of this DFS will be.”