Tag Archives: Mondium

Monadelphous Group adds to construction pipeline with Rio Tinto, BHP contracts

Engineering company Monadelphous Group Limited has been awarded new construction contracts in the iron ore and renewable energy sectors, with the revenue contribution attributable to Monadelphous expected to total approximately A$340 million ($225 million).

In iron ore, Mondium, the company’s engineering, procurement and construction joint venture with Lycopodium, has been awarded a design and construct contract by Rio Tinto for a new sampling facility at a port operation in the Pilbara region of Western Australia, with work expected to be completed in mid-2026.

In addition, Monadelphous has been awarded a multidisciplinary construction contract under BHP’s WAIO Asset Panel Framework Agreement associated with the dewatering of surplus water from Orebody 32 in Newman, Western Australia. Work is expected to be completed in the second half of 2025.

Zenviron, the company’s full-service balance-of-plant renewable energy joint venture with ZEM Energy, has, meanwhile, secured a contract with CS Energy, a Queensland State Government owned body, for the delivery of the Lotus Creek Wind Farm in Central Queensland.

Rio’s WTS2 iron ore project hits first ore milestone, Mondium says

Mondium says first ore has been achieved at Rio Tinto’s Western Turner Syncline Phase 2 project (WTS2) in Western Australia.

Rio Tinto awarded Perth-based Mondium a A$400 million ($276 million) contract to design and construct the mine in early 2020. This saw the company, a joint venture involving Monadelphous and Lycopodium, undertake all engineering and design, procurement and site construction works associated with the WTS2 development, including the process plant, overland conveyor and non-process infrastructure.

Celebrating the achievement, Mondium said it was a significant achievement for its EPC team, Rio Tinto and delivery partners.

It added: “593 days and more than two million site hours worked culminated in the first loader bucket tipping high-grade ore into the WTS2 run of mine bin. Forty minutes later, the ore was discharged to the WTS1 belt and delivered to the Tom Price stockpiles.”

Back in November 2019, Rio said it would invest $749 million in the development of WTS2 at its Greater Tom Price operations, facilitating mining of existing and new deposits and including construction of a new crusher as well as a 13 km conveyor. In addition to this, the haul truck fleet at the mine would be fitted with Autonomous Haulage System technology to enable autonomous haulage. This fleet has since been commissioned.

Mondium chooses Kerman Contracting for Rio Tinto WTS2 work

Kerman Contracting is to work on Rio Tinto’s in-development Western Turner Syncline 2 (WTS2) iron ore project, in Western Australia, following a contract award from Mondium.

Mondium was last month awarded a contract to design and construct the WTS2 mine in the Pilbara of Western Australia. It has since agreed to contract out the design, construction and commissioning of non-process infrastructure facilities and an explosives compound to Kerman as part of a circa-A$55 million ($37 million) agreement.

The construction works are due to start in the June quarter, with the contract comprising a fixed plant workshop complete with amenities and office buildings, a heavy vehicle diesel storage and refuelling facility and two remote facility buildings inclusive of offices, ablutions and crib rooms as well as an ammonium nitrate and emulsion storage facility and explosives compound.

Kerman’s Managing Director, Chris Kerman, said: “We are excited about the opportunity to work with Mondium at the WTS2 project and looking forward to building a strong and lasting business relationship with Mondium.

“This contract award builds on Kerman’s previous successful project outcomes in the Pilbara region in particular for Rio Tinto and other major mining companies.”

Back in November, Rio said it would invest $749 million in the development of WTS2 at its Greater Tom Price operations, facilitating mining of existing and new deposits and including construction of a new crusher as well as a 13 km conveyor.

Mondium secures WTS2 iron ore contract from Rio Tinto

Rio Tinto has awarded Perth-based Mondium a A$400 million ($276 million) contract to design and construct the Western Turner Syncline Phase 2 (WTS2) mine in the Pilbara of Western Australia.

Mondium, a joint venture involving Monadelphous and Lycopodium, will undertake all engineering and design, procurement and site construction works associated with the WTS2 development, including the process plant, overland conveyor and non-process infrastructure.

Back in November, Rio said it would invest $749 million in the development of WTS2 at its Greater Tom Price operations, facilitating mining of existing and new deposits and including construction of a new crusher as well as a 13 km conveyor. In addition to this, the haul truck fleet at the mine will be fitted with Autonomous Haulage System technology to enable autonomous haulage from 2021.

Mondium’s work is expected to create 450 jobs starting in the March quarter, with completion slated for 2021. Rio said Mondium and it would work closely to ensure the contract provides local and Indigenous employment as well as business opportunities in the region.

Rio Tinto Iron Ore CEO, Chris Salisbury, said: “We’re committed to supporting WA businesses, buying locally and supporting our communities through the creation of jobs. We’re pleased to award this contract to Mondium who share those values.”