Tag Archives: Aurizona

Equinox Aurizona gold mine ramp up continues

Equinox Gold says it has achieved commercial production at the Aurizona gold mine, in Brazil.

The milestone, which occurred on July 1, follows the processing plant, in the month of June, operating at an average throughput of around 90% of nameplate capacity (8,200 t/d), exceeded 90% average recovery and producing more than 7,000 oz of gold. It also follows the first gold pour in May.

Gold production is expected to continue to increase through the September and December quarters of 2019, with average life-of-mine production estimated at 136,000 oz/y.

Christian Milau, Equinox Gold’s CEO, said: “Achieving commercial production at Aurizona is a significant milestone, making Equinox Gold a multi-mine producer and bringing us one step closer to our near-term target of having three mines in production in 2020.”

With commercial production at Aurizona achieved, the final condition pursuant to the previously announced corporate revolving credit facility has been completed and the remaining $30 million of the total $130 million has been made available to the company.

The mining contractor at the Aurizona operation is U&M Mineração e Construção S/A (U&M) and the EPCM contractor is Ausenco Engineering Canada.

Equinox Gold hits first pour milestone at Aurizona

Equinox Gold says it has poured first gold at its Aurizona gold mine, in Brazil.

Christian Milau, CEO of Equinox Gold, said: “Pouring first gold at Aurizona is a significant milestone for the company and the result of the hard work and dedication of the Equinox Gold team and our contractors.

“That we accomplished this milestone with no lost-time injuries is another important achievement for the Aurizona team.”

The company has also received its License to Operate, the final operating permit for Aurizona, from the Maranhão State Environmental Agency (SEMA).

Aurizona is expected to become a low-cost open-pit gold mine, with average annual production estimated at 136,000 oz/y, according to Equinox Gold.

Equinox, late last year, reported that the new primary jaw crusher at Aurizona had been energised and dry tested with the expectation of putting first ore through the system in early-January.

The mining contractor at the operation is U&M Mineração e Construção S/A (U&M) and the EPCM contractor is Ausenco Engineering Canada.