Tag Archives: British Columbia

Intrepid Group and indurad partner on anti-collision, volumetric inventory and positioning solution offering

Intrepid Group Ltd and indurad have announced a new strategic partnership to provide robust anti-collision, volumetric inventory and positioning solutions for the mining and material handling industry.

The partnership will have a focus on the provinces of British Columbia, Alberta and Saskatchewan, the pair said.

Indurad calls itself the global leader in radar-based automation and productivity solutions for mine sites, train loadouts, stockyard equipment and shiploading facilities. Its patented 2D and 3D radar systems are installed at mining operations and ports worldwide to increase ore throughput and minimise downtime and collisions.

Intrepid Group says it helps its customers improve their operations through accurate and efficient measurement of their processes, partnering with manufacturers to develop solutions that achieve these goals.

“Partnerships with regional leaders like Intrepid Group allow us to enhance our market coverage,” Adriaan Goosen, Director of Engineering at indurad, said.

Campbell Adams, Chief Executive Officer at Intrepid Group, added: “We are delighted by the partnership. indurad’s solutions affords us even greater flexibility to meet the diverse needs of our customers. The synergies of this partnership will greatly benefit both our current and future customers.”

Sedgman formally awarded EPC contract for Artemis’ Blackwater gold project

CIMIC Group’s mineral processing company, Sedgman, has been awarded an engineering, procurement and construction (EPC) contract to deliver services for Artemis Gold at the Blackwater gold project in British Columbia, Canada.

The EPC contract, which supersedes the temporary interim service agreement announced on May 2, 2022, will generate revenue for Sedgman of C$318 million ($245 million).

Sedgman will design and construct the processing and non-processing infrastructure for a 6 Mt/y carbon-in-leach gold plant at the project.

Even before this announcement, Sedgman had made good headway on the project, executing an agreement with Metso Outotec to secure supply and delivery of crushing and grinding equipment for the processing plant.

The project schedule as laid out by Artemis supporting the EPC contract with Sedgman includes the following assumptions:

  • Receipt of the BC Mines Act and related permits in the Fall of 2022;
  • Construction mobilisation and major works preparations commence in the March quarter of 2023 with process plant bulk earthworks scheduled to be completed prior to the start of major works;
  • Commissioning activities of the process facility to commence in the firts half of 2024; and
  • First gold pour expected in the September quarter of 2024.

CIMIC Group Executive Chairman, Juan Santamaria, said: “Sedgman and Artemis have already commenced initial design and procurement work at the project, helping Artemis to unlock the value of this key gold project and work towards its first gold pour in 2024.”

Sedgman Managing Director, Grant Fraser, said: “We are pleased to be working with Artemis Gold on this exciting project and look forward to continuing our strong working relationship to ensure successful outcomes for both Sedgman and Artemis.”

Work is expected to be completed in the September quarter of 2024.

Artemis has said previously that Stage 1 development at Blackwater should lead to the building of a 6-9 Mt/y operation (6 Mt/y in years 1-4 and 9 Mt/y in year 5) able to produce around 312,000 oz/y of gold.

Newcrest’s Brucejack mine set for full fleet battery-electric transition in Q4

Newcrest’s Brucejack gold-silver mine in British Columbia, Canada, is set for a full battery-electric fleet transition by the end of the year, the gold miner said in its financial year 2022 results.

Following a successful site trial, seven underground battery-electric trucks are being commissioned at Brucejack, replacing the existing diesel fleet and abating approximately 65,000 t of CO2 emissions through to 2030.

The new fleet will improve truck productivity, lower unit costs and enhance operational efficiency from planning to production, according to Newcrest. Three of the Sandvik 50-t-payload Z50 battery-electric trucks are already in production, with the full switch over expected to be completed in the December 2022 quarter, it noted.

Sandvik and Pretivm previously noted that seven Z50 haul trucks would be supplied to the operation as part of the planned fleet transition.

The project is being partly funded thanks to a C$7.95 million ($6.1 million) investment from The CleanBC Industry Fund.

Brucejack, which became wholly owned by Newcrest when the acquisition of previous owned Pretivm Resources completed earlier this year, is currently the subject of Newcrest’s EDGE program, which aims to drive a culture of innovation, high performance and continuous improvement. The program has identified additional opportunities of approximately C$15-$25 million/y, with improvements in stope turnaround time and more efficient mine operations as the initial focus areas, the company said.

Run-rate benefits from this effort are expected to be fully realised by the June 2024 quarter, Newcrest says.

Newcrest said in the financial results that it was also assessing ore sorting technology at the mine, which aims to classify and separate mineralised material from non-mineralised material to deliver more consistent mill feed grades and increase operational flexibility.

Teck to trial carbon capture utilisation and storage tech at Trail Operations

Teck Resources has announced a Carbon Capture Utilisation and Storage (CCUS) pilot project at its Trail Operations metallurgical complex in southern British Columbia, Canada, in support of its Net-Zero Climate Change Strategy.

The CCUS pilot is expected to begin operation in the second half of 2023 and is expected to contribute to the company’s aim of reducing the carbon intensity of its operations by 33% by 2030 and achieve net-zero emissions by 2050.

“This carbon capture pilot is an important step towards our knowledge building for the application of carbon capture, utilisation and storage as an emissions reduction solution, as we work to evaluate pathways to reduce greenhouse gas emissions across our operations and achieve our net-zero goal,” Don Lindsay, President and CEO, said. “The pilot also provides us with a technical platform to assist our steelmaking coal customers in materially reducing the carbon intensity of their steel production.”

The pilot plant will capture carbon dioxide (CO2) from the acid plant flue gas at Trail Operations at a rate of 3 t/d. The pilot project will also evaluate options for the utilisation and/or storage of the captured CO2 at Trail Operations, Teck says.

If successful, the project could be scaled up to an industrial CCUS plant with the potential to capture over 100,000 t/y of CO2 at Trail Operations, the equivalent emissions of more than 20,000 cars.

Teck acknowledged the support of the CleanBC Industry Fund for its funding contribution towards the CCUS Pilot Plant Feasibility Study, which was an important step in advancing the pilot. The CleanBC Industry Fund highlights the alignment between industry and government in achieving Canada’s goal of net-zero emissions by 2050, it said.

Artemis awards Blackwater gold EPC contract to Sedgman Canada

Artemis Gold Inc says it has made an award for the engineering, procurement, construction and commissioning (EPC) scope of works for the processing plant and associated infrastructure at its Blackwater project in British Columbia, Canada, to Sedgman Canada Limited, a CIMIC Group company.

The award amount of approximately C$312 million ($243 million) is consistent with the prescribed budget for the process plant and selected infrastructure scope of works in the 2021 feasibility study.

Sedgman Canada Limited is a wholly owned subsidiary company of Sedgman Pty Limited, a CIMIC Group company. CIMIC Group (ASX:CIM) is an engineering-led construction, mining, services and public private partnerships leader working across the lifecycle of assets, infrastructure and resources projects.

The EPC contract is expected to be executed by June 30, 2022, with the contract supported by performance security including bank letters of credit, which will underwrite the financial performance and obligations of the contractor under the contract.

While the parties finalise the definitive EPC contract, in order to maintain the project schedule, an interim services agreement has been agreed which could cover procurement and pricing of long lead equipment and optimisation through refined scope changes, among other aspects.

The project schedule supporting the award to Sedgman includes the following assumptions:

  • Construction mobilisation and major works preparations commence in Fall 2022 with process plant bulk earthworks scheduled to be completed prior to the start of major works;
  • Commissioning activities of the process facility to commence in Q1 (March quarter) 2024; and
  • First gold pour expected in the first half of 2024.

The final EPC contract terms will provide for potential cost adjustments of certain components of construction representing approximately less than 15% of the total contract amount, including the potential for cost adjustments from further quantity definition, Artemis said. Standard adjustments, including currency exchange rates for certain equipment purchases also apply, and further optimisation of the processing plant with final engineering will occur.

Artemis is also considering awarding additional construction packages under an EPC agreement type structure to further enhance the risk management of the total capital expenditure for Blackwater, it said.

When combined with the EPC for the Power Transmission Line announced on August 18, 2021, the percentage of the estimated total capital expenditure for Blackwater under EPC is on track to target circa-60% of the initial Stage 1 development capital of C$645 million in a lump sum EPC type arrangement by the September quarter of 2022.

Stage 1 development should lead to the building of a 6-9 Mt/y operation (6 Mt/y in years 1-4 and 9 Mt/y in year 5) able to produce around 312,000 oz/y of gold.

Steven Dean, Chairman and CEO, said: “The award of the EPC job for the process plant at Blackwater is another significant milestone for Artemis, reflecting a competitive process involving multiple bidders. We are very pleased to be working with a world-class engineering firm in Sedgman. In partnership, we will work to finalise the design and engineering of the Blackwater project in advance of a start of major development activities. Blackwater remains on track for a start of major construction activities following receipt of Mines Act and other permits in Fall 2022 with a first gold pour in H1 2024.”

Metso Outotec to engineer SAF solution for MGX’s silicon project

MGX Minerals Inc has announced the engagement of global mining equipment supplier Metso Outotec for its British Columbia silicon project.

The OEM has been tasked with providing design, equipment and mechanical engineering for the processing of high-grade silica from the company’s wholly-owned Gibraltar silica deposit into silicon metal 3303# grade.

The primary piece of processing equipment related to the agreement is a submerged arc furnace (SAF). This electric arc furnace generates heat up to 1,600°C sufficient to melt the quartzite. The liquid metal is then tapped and poured into bricks and rough crushed into 3-4 in (76-102 mm) pieces for shipment.

Recent metallurgical testing on a 1 t sample from the company’s Gibraltar silica deposit, 95 km northeast of Cranbrook, British Columbia, has indicated that the material is chemically suitable as medium-quality feedstock for metallurgical-grade silicon.

MGX says the demand for silicon metal continues to grow and recent supply chain bottlenecks have limited overall supply, creating an opportunity for the distribution of silicon in Asia from North America.

Kutcho Copper outlines combined open-pit/underground plan for mine

Kutcho Copper Corp has outlined a plan to develop an open pit and underground operation at its copper and zinc project in northern British Columbia, Canada, with the publication of a feasibility study.

The results of the study highlight an 11-year mine life with metal production of 533 Mlb (241,765 t) of copper, 841 Mlb of zinc, 10.6 Moz of silver and 129,700 oz of gold at all-in sustaining costs of $1.80/lb ($3,969/t) of copper equivalent. It came with an initial capital cost of C$483 million ($388 million).

The Main deposit at Kutcho is designed to be mined primarily as a conventional shovel and truck open-pit operation, with a deeper remnant mined by underground longitudinal longhole open stoping (LLHOS) with cemented rock fill (CRF). The underground Esso deposit is also designed to be mined using LLHOS with CRF.

A total of 17.3 Mt is planned to be mined over an 11-year mine life, with 14.5 Mt coming from the open pit and 2.8 Mt from the underground mines. A steady-state crusher production rate of 4,500 t/d is expected be achieved by the end of the first year of operations.

After primary crushing at an average steady state rate of 4,500 t/d, an ore sorter using an X-ray Transmission (XRT) sensor would remove low-grade and waste material from the feed to the SAG and ball mills, followed by conventional flotation, regrind and dewatering circuits. Approximately 3,900 t/d of ore would report to the milling and flotation circuit after ore sorting. The XRT plan follows testing of Kutcho samples at TOMRA Sorting Mining facilities.

The project design includes an extensive progressive reclamation program, including the backfilling of the open pit and water treatment during operations and for the closure period.

The company also plans to use liquified natural gas for power generation as opposed to diesel, which will significantly reduce the generation of greenhouse gases and reducing the potential for fuel spills. This would see four 2.5 MW LNG generators plus one on standby used, with a 2 MW diesel generator providing occasional plant start-up assistance.

Vince Sorace, President & CEO of Kutcho Copper, said: “The feasibility study represents a major milestone for Kutcho Copper as we continue to advance the high-grade Kutcho copper-zinc project towards a development decision. The significant redesign and engineering of the project delivers a mine plan that is a predominantly open-pit mining operation with the concurrent development of two underground mines. The mine plan has resulted in a technically robust and capital efficient project with a minimised footprint.

“The results of the feasibility study highlight the attractive economics of the Kutcho project which are resilient at lower metal prices, very attractive at base case prices and exhibit significant leverage to rising prices as reflected in spot metal prices with a C$931 million after-tax NPV (7% discount) and a 41% internal rate of return. We believe that the results of the feasibility study mean that Kutcho Copper is now one of the most undervalued copper investment opportunities in North America.”

TOMRA XRT ore sorting test work delivers the goods at Kutcho’s copper-zinc project

Higher head grades and recoveries, a reduction in run-of-mine material reporting to the milling and flotation circuit, a smaller tailings management facility, and lower power and water demand are just some of the benefits to have come out of ore sorting test work at Kutcho Copper’s copper-zinc project in British Columbia, Canada.

Recent bulk sample test work was conducted to determine the effectiveness of using ore sorting technology from TOMRA Sorting Mining to improve the processed grade and reduce the mill feed tonnage of mineral resources at the project.

ABH Engineering Inc and TOMRA were commissioned to undertake this work to establish the amenability of Kutcho’s Main and Esso deposits to ore sorting using an X-ray Transmission (XRT) sensor. Two phases of test work, including a representative 0.75 t bulk sample derived from drill core, were undertaken at TOMRA Sorting Mining in Germany under the supervision of ABH Engineering.

“The ore sorting process helps concentrate the metals of commercial interest from the Kutcho deposit, which are principally associated with high density sulphide minerals,” Kutcho explained. “Rocks are individually scanned, and low grade (low density) waste material is selectively diverted away from downstream processing using compressed air jets. Preliminary test work on the sensitivity of the ore to a XRF sensor was also undertaken.”

The bulk sample tests conducted on a production-scale XRT ore sorter indicate that approximately 17% of the ROM material will be <12.5 mm in size and would therefore bypass the ore sorter and report directly to the milling and flotation circuit. Of the >12.5 mm feed, some 15% of the material reporting to the ore sorter was detected by the XRT sensors as being low grade or waste and will be rejected by the ore sorter, thereby reducing run-of-mine material reporting to the milling and flotation circuit by 13%. The overall recovery of metal (copper, zinc, silver and gold) reporting to the ore sorter is in the order of 99% (ie less than 1% of the metals of interest will be rejected by the ore sorter), Kutcho said.

Pre-sorting of the run-of-mine material by the ore sorter has the potential to reduce milling and flotation operating costs corresponding with the 13% rejection of low-grade material, it says. The commensurate increase in the head grade of the ore reporting to the flotation circuit has the potential to also result in improved metallurgical recoveries in the flotation circuit.

Additionally, it is anticipated that potential savings in capital and operating costs related to the smaller milling and flotation circuit will offset the costs associated with the ore sorter, according to the company. Savings will also be achieved by a reduction in the size of the tailings management facility. The optimally sized ore sorter reject waste material could be used as cemented rock backfill in the underground mines at both the Main and Esso deposits, resulting in further potential cost savings, Kutcho said.

Environmental benefits accruing to the project because of the introduction of ore sorting technology include a lower power and water demand, and a smaller tailings management facility, the company concluded.

Earlier this month, Kutcho said in a feasibility study progress report that it was considering open-pit mining for the majority of the Main deposit at Kutcho, allowing the company to capitalise on the high-grade, near-surface mineralisation, resulting in lower operating costs than underground mining. The remainder of the Main deposit and all the Esso deposit will continue to be evaluated assuming underground extraction by longitudinal longhole open stoping, it said.

The ore sorting test work was also being incorporated into the feasibility study design.

New Gold heads towards New Afton’s B3 Zone

New Gold is set to soon start ore extraction activities at New Afton’s B3 Zone in British Columbia, Canada, after receiving its Mines Act Permit from the Ministry of Energy, Mines and Low Carbon Innovation.

The gold-copper mine has recently been focused on development of the B3 and C-Zones, which are likely to represent the major production sources over the next decade.

Current production is coming from the B1 and B2 Zones (Lift 1) where there are two panel caves (west and east) in operation. The B3 Cave is 160 m below and immediately to the west of Lift 1. Ore from B3 will be hauled by truck to the existing gyratory crusher, with production continuing until at least late 2024.

The C-Zone block cave zone is around 550 m below Lift 1. Development towards the C-zone is underway with production planned to commence with the first of 143 planned drawbells in the second half of 2023.

On the permit award, Renaud Adams, President & CEO of New Gold, said: “This is a significant milestone for the New Afton Mine. With the receipt of the B3 permit, ore extraction activities will begin this quarter and ramp-up over the year.

“C-Zone development continues to advance with C-Zone extraction expected to begin in the second half of 2023.”

The C-Zone permitting process was initiated during the March quarter of this year with the submission of the pre-application package to the Ministry of Energy, Mines and Low Carbon Innovation, Ministry of Environment and Climate Change Strategy and Indigenous groups.

MineSense to expand XRF ore sorting presence at Copper Mountain mine

MineSense Technologies says the use of its ore characterisation and sorting technology is seeing improvements in both the ore from waste recovery and ore dilution at Copper Mountain Mining Corp’s namesake mine in British Columbia, Canada.

Having deployed the company’s ShovelSense solution on two shovels and a wheel loader in 2020, Copper Mountain now has plans to install ShovelSense on the two remaining shovels in 2021, along with the first trial installation of BeltSense to explore additional innovation concepts, Don Strickland, Chief Operating Officer at Copper Mountain Mining Corp, said.

Jeff More, President and CEO of MineSense Technologies, said: “Copper Mountain has been a fantastic partner to work with, initially to support us in our scale-up on hydraulic shovels, and then with rapid commercial deployment once the design was stabilised.

“We are thrilled that they installed three of our ShovelSense Systems in the space of five months in 2020 and will complete installation of their entire shovel fleet in 2021.”

The MineSense hardware and software went through a two-year evaluation process at Copper Mountain prior to the solution going commercial, Copper Mountain stated in a recent technical report.

The ShovelSense system improves orebody visibility bucket by bucket in real time during the loading process, according to the company. Trucks are then automatically diverted to the correct location, increasing value and revenue realised during the mining process. The technology also creates reductions of CO2 emissions per tonne of ore produced, consumption of processing chemicals and reagents, energy and water, while maximising metal recovery.

BeltSense, meanwhile, is used on conveyance at different points of the mine operation. It can be used sequentially and in conjunction with ShovelSense to maximise the ore concentrating impact, taking a first cut at the haul point and second further downstream, MineSense says.

Both systems leverage X-ray Fluorescence sensors to carry out the sorting process.