Tag Archives: CIL plant

Macmahon, GR Engineering on board Calidus Resources’ Warrawoona gold project

Calidus Resources has started construction ahead of schedule at its Warrawoona project, as well as made two key appointments to deliver on its gold mine development in Western Australia.

It has appointed Macmahon Holdings as the preferred mining contractor for the project, while GR Engineering Services has been awarded preferred tenderer status for the process plant engineering procurement and construction.

While construction activity has already commenced ahead of the main project construction activities, which are expected to kick off in the March quarter of 2021, these contract tenders will allow finalisation of major contracts as part of the ongoing feasibility study at Warrawoona, due for completion this month, Calidus said. It will also help facilitate front end engineering and design for the project and the placing of orders for long lead items.

This project involves the development of a new open-pit mine in the Pilbara region, with the scope of work for Macmahon to include all open-pit mining activities, and potentially some early stage civil works.

Macmahon estimates the open-pit mining work will generate around A$220 million ($160 million) in revenue over 54 months and require capital expenditure of circa-A$30 million. There is also potential for the Warrawoona project to include underground mining, which could represent a further opportunity for Macmahon when this is developed, it said.

Macmahon expects it will start work on site in the first half of 2021, with the project to eventually employ more than 120 of its personnel.

GR Engineering, which has completed the last two gold plants in Western Australia, according to Calidus, will work on the design and construction of the process plant and associated infrastructure, meanwhile.

A prefeasibility study on Warrawoona completed in July 2019 outlined average gold production of 97,000 oz/y at an all-in sustaining cost of $1,159/oz over an initial six-year mine life via a 2 Mt/y conventional CIL processing circuit with single stage crush and SAG mill.

Among the initial works the company has started are 7 km-long access road to the village and process plant (pictured); the installation of the 240 room village that has been previously purchased by Calidus; the installation and operation of communications by Telstra; and the installation and equipping of water bores.

Caledonia breathes new life into Blanket gold mine

Caledonia Mining says it has successfully installed and commissioned a new oxygen plant at its 49%-owned Blanket gold mine in Zimbabwe.

The new oxygen plant is expected to improve metallurgical recoveries and reduce cyanide consumption at Blanket. Test work indicates the plant will improve overall metallurgical recoveries at Blanket to around 94%, up from the 93% average recorded for 2019 so far.

Steve Curtis, Caledonia Chief Executive Officer, said the oxygen plant commissioning was the latest in a series of investments to increase production and improve operating efficiency at Blanket as it looks to reach 80,000 oz/y capacity by 2022. One of the other projects that will contribute to this increased output is the sinking of the Central Shaft, which was completed earlier this year.

Curtis said: “The new oxygen plant will provide up to 6 t of improved oxygen supply to the Blanket carbon-in-leach plant, which is expected to increase recoveries to approximately 94%.

“We also anticipate that the oxygen plant will result in slightly lower operating costs as cyanide consumption is expected to be reduced as a result of the improved oxygen supply; and the operating costs of the new oxygen plant are predicted to be lower than those of the previous two tonne plant.”

Blanket produced 54,512 oz of gold in 2018 and is expected to produce 53,000-56,000 oz in 2019.