Kışladağ and Weir Minerals on the HPGR-backed gold recovery trail

The story that led to the installation of a Weir Minerals Enduron® high pressure grinding roll (HPGR) at Eldorado Gold’s Kışladağ heap leach operation in Turkey is a fascinating read, as well as a great example of the benefits of using such technology.

Back in March 2018, Eldorado announced it would suspend mining to evaluate processing options for the operation. This decision followed extensive laboratory tests that indicated gold recoveries would continue to trend downwards around the base of the open pit where mining was underway.

This suspension, plus further engineering and test work, led to the company advancing the potential development of a mill project. The transition away from its heap leaching roots to a possible mill and carbon-in-leach (CIL) process would have added significant capital costs and shortened the mine life significantly.

Before making this significant capital decision, Eldorado paused to take time to undertake the necessary technical work and sought the technical collaboration of Weir Minerals on a solution.

“It was a very challenging period,” George Burns, President & CEO of Eldorado Gold Corporation, told IM. “Kışladağ is a cornerstone asset in our portfolio. It required collaboration with our geologists, metallurgists, site teams and technology providers, including Weir, working together on a solution.”

(Credit: Eldorado Gold)

In late 2018, results showed increased recoveries from an extended leach cycle. Following a deeper understanding of the geometallurgical drivers of the sulphide component of the deposit, improved heap leach recoveries were realised by optimising the metallurgical conditions. With these improved recoveries confirmed, the heap leach plan was revised in early 2019. Eldorado announced plans to resume mining, crushing, stacking and heap leaching at Kışladağ, and suspended plans to build the processing plant.

The decision came following metallurgical test work on the material placed on the heap leach pad in 2018. Gold recovery had increasingly exceeded expectations throughout the year, providing a new, positive heap leaching outlook beyond the near term. At the same time, Eldorado worked with Weir Minerals on the potential use of an HPGR at the operation.

HPGR creates a finer particle size, which helps to liberate the gold particles, resulting in increased recoveries.

An improved understanding of the leaching process on its low-grade ore and the potential of this cost-effective grinding addition provided it with the confidence to continue heap leaching beyond the short-term time horizon previously envisaged.

“Our collaboration with Weir on this effort is an excellent example of how Eldorado collaborates with technology leaders and seeks out solutions,” Burns said. “We believe this is a strength of the company’s core business values. We are agile and flexible ‒ a good example in both business and operations to find innovative, technical solutions and demonstrate prudent capital discipline. Ultimately, the solution was the best technical and economic decision for Eldorado.”

Testing, testing, testing

“The relationship between Weir Minerals’ and Kışladağ goes back to 2013,” Bjorn Dierx, Global Product Manager Enduron HPGR, told IM.

The OEM had been provided with samples on several occasions to investigate different flowsheet possibilities.

“The benefits of HPGR in heap leaching recovery were known by the site’s crew,” he said.

Enduron technology was tested at the quaternary crushing stage before heap leaching, in the quaternary crushing stage before ball milling and at the tertiary crushing directly before heap leaching.

All the time, the mine operator, Tuprag, Eldorado Gold’s subsidiary in Turkey, was evaluating the impact on gold recovery.

Although HPGR in closed circuit with screening was also tested, most of the test campaigns were focused on a configuration with so-called ‘Partial Product Recycling’ (PPR), according to Serhat Onol, Weir Minerals Senior Process Engineer.

“This system includes splitter plates underneath the rolls which ‘cut’ a proportion of the product discharge and reverts this back to the HPGR head feed,” he explained. “This recycle stream can be adjusted online to adapt the product grind towards the downstream requirements.”

PPR is not an option for every application but for Tuprag – due to the feed and desired product size – all specifications showed it was the best route.

“The hybrid solution with screening serves to increase the flexibility and to control the circulating load to the HPGR,” Onol said.

With capacity rates of around 4,200 t/h at Kışladağ, the screening area requirement was reasonably high, he explained.

“The hybrid solution uses screening only for the recirculating stream: the centre product of the HPGR reports to downstream leaching, whereas the rest is recirculated,” he said. This not only removes the fines re-entering the HPGR and, thus, reduces the circulating load, but also avoids the over-grinding of fines before leaching.

The PPR option, itself, is a very flexible operation, with the adjustable discharge splitter plates providing the best circuit flexibility in terms of throughput and product size, according to Onol.

(Credit: Eldorado Gold)

Great expectations

With the main driver of the HPGR installation being an improved gold recovery scenario, leading to an increased heap leach life, the pressure has been on Weir Minerals to come up with the goods.

The final flowsheet, which includes a 2.4 m diameter by 2.2 m long Enduron HPGR with the capacity to process 4,200 t/h, is much simpler than the existing circuit, according to Dierx, with less equipment to maintain, control and monitor.

“A single Enduron HPGR will replace all of the five existing tertiary crushers of which liners would have an average lifetime of circa-one month with a crusher availability of 85%,” he said. “The HPGR tyres have a wear life close to 18 months, with the HPGR achieving a high asset availability of more than 95%.

“Additionally, as a result of the HPGR combined with the hybrid PPR system, the existing four tertiary screens are also being decommissioned.”

Not only has the HPGR alleviated the use of this equipment, it is also set to boost that bottom line gold recovery.

“During testing, it was determined that the circuit configuration and HPGR operating conditions, such as pressure, have a direct influence on the gold recovery,” Dierx said. “The current expectation is that the average recovery increase after the commissioning of the Enduron solution will be approximately 4%.”

This could bring gold recovery to approximately 56%, as was declared in a 2020 press release from Eldorado that highlighted a 15-year mine life at Kışladağ with an average annual production of 160,000 oz.

In action

One of the largest brownfield HPGRs Weir Minerals has ever installed has just processed its first material at Kışladağ, which is testament to the hurdles both the Weir Minerals and Tuprag teams overcame during the height of the COVID-19 pandemic.

“Despite the challenges we faced during the pandemic, we were able to fully install the machine, including pre-commissioning, in only 22 weeks,” Dierx said.

(Credit: Eldorado Gold)

This was achieved by minimising the amount of work carried out on site via pre-site testing and modular HPGR assembly.

“As the available footprint in existing sites is limited, the unique Enduron design (length:diameter ratio) not only improves the grinding efficiency but also allows for easier implementation with less civil requirements,” Dierx said.

The machine has the potential to be digitally connected to the Weir Synertrex® IoT platform where operators can benefit from direct access to maintenance specialists, who will be monitoring performance and provide necessary operating guidance.

And the Weir Minerals team is confident more Enduron HPGR installations will follow the one at Kışladağ.

“We are very proud of the product’s recognition by our customers as the Enduron HPGR has been selected for all major greenfield HPGR projects in the hard-rock space,” Dierx said. “Despite all the key Enduron differentiators, it is not only merely about the product but particularly the wider experience across Weir Minerals in both the upstream and downstream processes via our wide product portfolio.

“Particularly in these brownfield applications, the system is not operating in a vacuum and every process change influences how the overall circuit works. This requires tacit knowledge, which Weir Minerals holds across their global teams.”

Eldorado’s Burns concluded: “We are pleased to implement a solution that increases gold recovery and supports a 15-year mine life at Kışladağ, allowing Eldorado to continue to provide employment and economic opportunity in the region, as well as provide a solid foundation for future growth.

“Kışladağ has been the cornerstone asset of Eldorado for over a decade, producing over 3 Moz of gold and generating significant value for all stakeholders during that period. This project is a testament to our exceptional team and technology partners working together to execute in challenging circumstances during the pandemic.”

Eldorado Gold green lights underground decline at Lamaque mine

Eldorado Gold is commencing construction of a 3 km decline at its Lamaque underground gold mine in Quebec, Canada.

The fully permitted decline will go from the Sigma mill to the 405 m level of the Triangle mine, where resources and reserves reside.

Eldorado said the $24 million investment was expected to provide multiple near-term and long-term benefits as the company continues to grow production at Lamaque. Earlier this year, it was granted Certificate of Authorization from the Quebec Ministry of Environment to expand underground production from Triangle from 1,800 t/d to 2,650 t/d.

“Detailed engineering and site preparations for the decline will commence this month and surface construction on the portal will begin in Q3 (September quarter) 2020,” the company said.

The decline is expected to be completed by the first half of 2021, but Eldorado is also evaluating the possible addition of an underground crushing and conveying system as well as a potential mill expansion, it said.

Late last year, then-COO, Paul Skayman, told IM the company was considering the use of battery-electric vehicles, or vertical haulage with conveyors, as part of its mine expansion plans.

And, since then, the company has started trialling the SAMS™, or the shallow angle mining system, from Minrail, a system that could allow the company to further enhance Lamaque’s economics, improve safety and develop technical expertise that could potentially be leveraged at some of Eldorado’s other mines.

While an update outlining the path forward at Lamaque is expected in the December quarter of this year, the company said the benefits of the construction of this decline include:

  • Eliminating surface re-handling and haulage (around 26 km round trip) of the ore from the Triangle mine to the Sigma mill, reducing carbon emissions, costs, and removing haulage traffic from the public road network;
  • Reducing the energy requirements for mine ventilation;
  • Supplying a means of secondary egress and ventilation to the Triangle mine, increasing safety underground;
  • Providing underground access for lower cost exploration in the prospective area between the Triangle mine and the historic Sigma and Lamaque mines – including further drilling of the Plug 4 and Parallel deposit and the Ormaque zone; and
  • Facilitating increased future production from the Triangle mine (contingent on continued reserve expansion) and allowing for mining of the Parallel deposit.

George Burns, Eldorado President and CEO, said: “We are pleased to begin construction of the decline at Lamaque this summer. This is a project that we have been advancing for nearly a year and is another step towards further production growth and continued value creation at Lamaque.”

Eldorado Gold to continue heap leaching operations at Kisladag

Eldorado Gold has decided to resume mining, crushing, stacking and heap leaching at its Kisladag gold mine, in Turkey, and suspended plans to build a $500 million processing plant.

The decision comes following the receipt of metallurgical test work on material placed on the heap leach pad last year.

Not only will this move defer a significant amount of capital expenditure for the company, it is also expected to help production rise to 390,000-420,000 oz in 2019, compared with 349,147 oz in 2018, a year when Eldorado suspended mining operations at Kisladag due to lower than expected gold recoveries.

Eldorado’s President and CEO, George Burns, said: “The decision to restart mining and heap leaching at Kisladag is supported by improved heap leach recoveries and confirmed by a revised heap leaching plan developed in early 2019. The revised heap leaching plan results in favourable economics when compared to milling, without the risks associated with the construction and financing of a $500 million project.”

On October 23, 2017, the company provided an update on Kisladag operations based on laboratory testwork undertaken during the September quarter of that year, which indicated that lower recoveries were expected from the zone of mineralisation located around the base of the open pit where mining was underway.

Based on available information, in the March quarter 2018, Eldorado elected to suspend mining in order to evaluate processing options. Following a year of engineering and testwork, in October 2018 the company announced that the Board of Directors had approved the advancement of a mill project. Subsequent to that announcement, gold recovery from the leach pad increasingly exceeded expectations. The company then focused testwork and analysis on the viability of resuming mining and heap leaching at Kisladag.

In parallel to mill engineering and analysis, testwork to extract maximum value from material already placed on the heap leach pad and the remaining reserves was ongoing throughout 2018.

Approximately 900,000 t of ore was placed on an inter-lift lined test pad in the March quarter of 2018. Late in the year, results from this pad were showing recoveries of approximately 58% from an extended leach cycle approaching 250 days (compared with around 40% recoveries from the original 90-day column tests).

In early 2019, the company analysed the new data and developed revised heap leaching plans, showing improved economics for the heap leaching scenario, hence the recent decision.

Eldorado said mining was expected to recommence by the end of this quarter, with the three-year guidance of 145,000-165,000 oz (2019), 240,000-260,000 oz (2020) and 75,000-95,000 oz (2021) based on mining and stacking an initial 22 Mt of ore grading over 1.1 g/t over this period, as well as continuing to leach the material currently on the pad.

This would help overall group production go to 390,000-420,000 oz in 2019, 520,000-550,000 oz in 2020 and 350,000-380,000 oz in 2021.

Eldorado said on Kisladag: “While the mill project has been suspended, the project remains viable in the short-term. The viability of the mill project will continue to be assessed in light of the results from ongoing heap leach metallurgical testwork on deeper material and in view of other investment opportunities within the portfolio,” the company said.

The other piece of exciting news within the company’s results was developments at its Lamaque mine in Quebec, Canada.

The company poured first gold from the Sigma mill at Lamaque in December and, in the March quarter, the mine is expected to declare commercial production. This should set the operation up to produce 100,000-110,000 oz of gold in 2019 from the mining and processing of over 500,000 t of ore at an average grade of 7 g/t Au.

Burns said: “At Lamaque, we are very pleased with the performance of our project team who delivered the first gold pour from the Sigma mill in less than 18 months since acquisition.”

In addition, exploration success at Lamaque – which includes significant resource conversion in the C5 orebody, in particular – has led the company to review options to increase throughput at the Sigma mill.

Eldorado said: “The mill has a refurbished nameplate capacity of 2,200 t/d and the potential to expand to its former capacity of 5,000 t/d with a purchase and installation of a SAG mill. Based on planned drilling and the potential conversion of inferred resources in C4, C5 and C6, the company expects to explore options to increase mill feed.”

The Lamaque underground mine is currently expected to produce 125,000-135,000 oz of gold in both 2020 and 2021.