Tag Archives: Madsen

MacLean ANFO loader goes underground at Pure Gold’s Madsen project

The ramp up to first production at Pure Gold Mining’s Madsen gold project in Red Lake, Ontario, continues, with the company having recently taken delivery of an ANFO loader from MacLean Engineering.

The ANFO loader, which has just headed underground for the first time at the project, is one of several new pieces of kit the company has added to its fleet as it heads towards its goal of pouring first gold at Madsen by the end of the year.

In a June 21 update, Pure Gold said procurement of major equipment was now 94% complete; a total of 1,285 m of underground mine development had been completed, with an advance rate 60% better than the mine plan; initial access development to longhole stopes had commenced; and an alimak had been installed in the existing shaft to support dewatering and shaft rehabilitation.

In the update, the company said new mine equipment delivered to date included four underground LHDs, two jumbo drills, two haul trucks, two scissor lifts, multiple utility vehicles and the ANFO loader.

One of these haul trucks is a DUX DT-26N articulated truck, while at least one Epiroc jumbo drill has been commissioned at Madsen.

Based on the 2019 feasibility study, Madsen is expected to produce an average of 80,000 oz/y at an all-in sustaining cost of $787/oz over a 12-year mine life. The operation will feature a combination of diesel and battery-powered load and haul equipment, with first gold production planned for the December quarter.

DUX dump truck makes its way to Pure Gold Mining’s Madsen project

New underground mining equipment has been arriving at Pure Gold Mining’s Madsen gold project in Red Lake, Ontario, with the company recently taking delivery of a DUX DT-26N articulated truck.

Despite the impact of the COVID-19 pandemic, Pure Gold has continued to progress the construction of Madsen, with Pure Gold President and CEO, Darin Labrenz, saying at the end of March that underground development had commenced safely and ahead of schedule.

In the same update, the company said detailed engineering was on track to support the completion of the project as scheduled for late 2020.

“To date the company has placed equipment purchase orders representing approximately 74% of the long lead items by value, including electrical equipment packages, key gold room equipment, gravity and intensive leach systems as well as the new ball mill to provide for planned processing rates of 800 t/d,” Pure Gold said.

One of the more recent pieces of equipment to arrive in Red Lake is a 26 t capacity articulated dump truck from DUX Machinery (pictured). This underground four-wheel drive truck is well suited for hauling ore, waste and backfill on level and steep grades, according to DUX. It also has the highest power to weight ratio in its class the company said, adding that it permits efficient chute, side and end loading in narrow drifts with low headings.

From mid-December to late March, some 740 m of development had been completed at Madsen, with Pure Gold saying early initiation of ramp development through the company’s test mining program and, to date, a 50% improvement on development productivity from underground, had provided an opportunity to access key stopes ahead of schedule, optimise the mine plan, and provide a larger ore stockpile in advance of mill start-up.

Based on the 2019 feasibility study, Madsen is expected to produce an average of 80,000 oz/y at an all-in sustaining cost of $787/oz over a 12-year mine life. The operation will feature a combination of diesel and battery-powered load and haul equipment.

Pure Gold makes its electric investment case

Newmont Goldcorp’s Borden development may have stolen the mine electrification limelight in the last 12-24 months in Ontario, Canada, but with this all-electric mine close to starting up, another project in the province is laying the groundwork to follow in its footsteps.

The Madsen project is a former-operating underground gold mine situated in the renowned Red Lake region. Since acquisition, Pure Gold Mining has been adding ounces to the 43-101 reserve and resource categories, while rehabilitating the old workings to generate a viable plan to re-start mining.

The February feasibility study outlined an economically sound project, costing C$95 million ($72 million) in upfront capital and returning an after-tax net present value (5% discount) of C$247 million using a gold price of $1,275/oz. This study included details of a mining and development fleet made up of a combination of diesel and battery-powered load and haul equipment.

With mine electrification still high on IM’s agenda following the inaugural Electric Mine conference in April, in Toronto, Dan Gleeson spoke with Pure Gold President and CEO, Darin Labrenz, to find out more about the company’s electric equipment plans.

IM: You recently raised C$47.5 million to continue development work and carry out further exploration at Madsen. Can you breakdown how much will go towards exploration/development?

DL: We’ve closed two raisings this year. The one earlier in the year was a C$5.2 million flowthrough raise designated for exploration. Those funds will go towards a drilling program in the order of 12,000 m directed towards those resources and discoveries that lie outside of the feasibility study mine plan…with the goal of being able to bring them into a future mine plan.

The C$47.5 million is what I would call the ‘equity component’ of a project financing package. Some of it may ultimately go into exploration.

Then, in August, we announced the $90 million project financing package with Sprott Resource Lending Corp comprised of a credit facility for $65 million, and a $25 million callable gold stream. This allows us even more flexibility on how we want to explore the exciting tenement as well as other opportunities.

IM: What type of development work is going on at Madsen currently?

DL: Last year, we conducted some trial mining, which involved extending the ramp a short distance; lateral development underneath the base of two stoping areas (as well as a couple of raises into those areas); and rehabilitation of the historical Number 2 level back to the existing shaft to provide secondary egress to the mine. We also initiated dewatering last year and have brought the water level down; right now, we’re holding it constant at about 250 m below surface. We’ve also done a lot of surface work to clean up and prepare the site for future activities.

With the debt financing now complete and a decision to construct by the board, detailed engineering in advance of site development work will commence immediately. We expect surface works and underground development to commence in Q4 (December quarter) of 2019.

IM: Based on current progress, when do you expect to produce first gold at Madsen?

DL: With access to the capital provided by the recently announced financing, the construction of the Madsen Red Lake mine is now fully funded. Combined with the equity financing, this secured approximately C$90 million of immediate funding enabling us to initiate construction and put us on track for first gold pour by late 2020.

IM: What factors came into play when deciding on the use of battery-electric equipment at Madsen?

DL: The key drivers for us were operating costs, environmental benefits and improved working conditions.

The use of electric equipment underground really eliminates a large component of the operational greenhouse gases that would be emitted from the mining operation, but also key is the reduction in ventilation requirements: the use of an electric fleet is going to require about 50% less ventilation. When you look at the life of mine at Madsen – with the combination of power and propane that would be used – you’re looking at savings of around C$41 million by going down the electrification route.

The ventilation benefits really increase with depth as you continue to push the mine down. Electrification allows the mine to push ramps down more efficiently, while reducing operating costs at the same time.

From a social, community and regulatory perspective, the move to a more environmentally friendly operating environment is also being well received.

IM: How did the company balance the capex issues with the opex benefits when choosing battery-electric haulage equipment over conventional diesel?

DL: The capex is higher for electric fleets – these costs are reducing, and I would expect to see them to continue to reduce into the future as that technology advances. Saying that, the increases in capital over diesel equipment are more than covered by the operating cost improvements that come with the reduced ventilation and heating requirements.

In an earlier study we completed we had a more pronounced combination of diesel and electric equipment. One of the things that has allowed us to further electrify this operation is the use of the existing shaft on the property. With this existing shaft, we will be transitioning to an operation that hoists ore and waste up the shaft, which reduces the haulage distance for the electric equipment. From an operational standpoint, in terms of the battery capacity and the need to recharge/replace batteries, it really advances our potential use of electric equipment.

One of the limiting factors in ramp-supported operations is ventilation. As you go deeper and deeper in a mine, you need to drive more and more air down to these depths. Ultimately, you get to a point with deepening a mine where you just cannot push enough air to clean out the diesel from the operating environment. With an electrified fleet, you can have narrower openings and you can push those ramps much deeper as the ventilation requirements are reduced.

IM: Have any investors raised concerns about this planned mine electrification?

DL: While we haven’t received any specific concerns, we have been asked about the technology’s availability and reliability. We can now point to several operations in Canada that are transitioning to electrical equipment. Many of the major equipment suppliers are also transitioning and starting to provide electrified versions of existing diesel equipment. That technology has been rapidly advancing and will continue to do so.

For us, looking to go into operations in the near-term, initially starting with the diesel equipment and transitioning into the electrical equipment reduces any risk from an availability and operating perspective.

IM: Is the move to start with diesel and go into electric also predicated on the flexibility required during development/production?

DL: It’s a few things. Primarily, when you look at the early years of mining, we are mining much shallower and the ventilation requirements are that much lower, so you see limited operational cost benefits when using electric equipment. From a capital perspective, initiating operations with diesel equipment allows us to be capital efficient, as well as equipment availability being high.

As we continue to deepen the mine, we transition into electric technology and then see operational cost improvements. This strategy also allows the industry more time to advance the electric technology.

IM: What was the reason behind the plan to use a tethered 6 t LHD close to the loading station and 6 t diesel LHDs elsewhere?

DL: The use of tethered equipment is a function of how much this 6 t LHD has to travel in the mine plan. Its purpose is to transfer muck into the loading pocket shoot, so it has a limited travel path.

On the other large LHDS, obviously we would use electric equipment should it be available at the time we need to procure it.

IM: Are you looking to use any other battery-powered or tethered equipment underground?

DL: We would look at electric equipment wherever it is practical and available. Currently utility vehicles such as man carriers, telehandlers, etc are available and will be utilised.

It will be something we consider at the time of the purchasing. We would look to use electric equipment as much as possible.

IM: Do you envisage other juniors going down a similar mine electrification route in the near-term?

DL: I believe so.

My perspective on this is that electrification of underground equipment is one of the great innovations in underground mining technology over the last decade. It has a very pronounced impact on operating costs, it obviously improves working conditions underground without the occurrence of diesel particulate matter and improves the ability to move your mine system deeper. It, importantly, also results in a real reduction in greenhouse gases, which reduces the environmental impact of underground mining.

Electrification is one of those rare cases where we see not only a strong operational reason for a move to that technology, but also a pronounced positive impact on the workforce and surrounding community.

Pure Gold looks at mine electrification options for Madsen underground project

In another sign that the underground mining space is increasingly going electric, Pure Gold Mining has said it intends to use a combination of diesel and battery-powered load and haul equipment at its Madsen underground gold project in Ontario, Canada.

The company said all ramp and level waste development would be performed by an owner-operated fleet of one- and two-boom electric hydraulic drill jumbos, 3 cu.m capacity LHDs, 20-t haul trucks, scissor lift/bolters and other rubber tyred support equipment.

Pure Gold said: “Mining will be facilitated by a combination of diesel and battery-powered equipment, with diesel equipment being utilised for upper levels of the mine prior to refurbishment of the existing shaft and installation of a new double-drum production hoist.”

Following the refurbishment, battery-powered equipment is likely to be used, with the company explaining that its use will “eliminate emissions associated with the movement of ore and waste and will result in materially reduced ventilation and heating requirements”.

This information came out in the company’s press release announcing a feasibility study on Madsen, a former operating gold mine in the renowned Red Lake district.

Based on a probable mineral reserve of 3.5 Mt at 9 g/t, containing 1 Moz of gold, the company outlined a 12-year operation at Madsen, producing an average of 80,000 oz/y at an all-in sustaining cost of $787/oz.

The initial capital requirement of C$95 million ($71 million) would be paid back with an after-tax net present value (5% discount) of C$247 million (using a gold price of $1,275/oz), the company said.

Darin Labrenz, President and CEO of Pure Gold, said: “The Madsen-Red Lake orebody is an exceptional foundation on which to build a gold mining company. With access to existing infrastructure, a high-grade reserve, and exceptional growth potential, Madsen is one of the outstanding gold deposits in Canada.”

He added: “The completed study outlines a long life high-margin mine, with low initial capital requirements and a fast timeline to production. In addition, specific exploration targets and satellite resources not considered in the feasibility study suggest an opportunity for near-term growth to potentially further enhance the economics of the project.”

The feasibility study supports a high-grade 800 t/d underground mining operation with designed stopes containing 1 Moz of probable reserves, the company said. Madsen benefits from significant mining, milling and tailings infrastructure already in place, resulting in one of the lowest capital intensity, undeveloped gold projects in the world, according to Pure Gold.

Mining will be conducted from new ramp development using a combination of cut and fill and longhole mining methods. A new hoist house and double drum production hoist will use the existing shaft infrastructure to hoist ore and waste from the mine, commencing in year four of operations.

The Madsen implementation schedule spans a period of 13 months, with underground mine development commencing approximately nine months before the first gold pour. The initial capital outlay of C$95 million (including contingency) supports the construction of an underground mine and associated infrastructure, including the expansion of existing milling capacity to 800 t/d of ore.

Assuming the project execution starts in April, the first gold production would be expected in May 2020.

JDS Energy and Mining led the feasibility study, which included contributions from consultants such as Knight Piésold, Nordmin Engineering, MineFill Services, Integrated Sustainability, Lorax Environmental Services, Ginto Consulting and Equity Exploration Consultants.