Tag Archives: Prominent Hill

Byrnecut assigned to Wira shaft sinking at OZ Minerals’ Prominent Hill operation

OZ Minerals, in its latest quarterly results, has confirmed that Byrnecut Group will sink the Wira shaft at its Prominent Hill copper-gold operation in South Australia.

Byrnecut has extensive experience of shaft sinking in the Asia-Pacific region, according to OZ. It is also the underground mining contractor at its Prominent Hill and Carrapateena mines, which, the miner says, will assist in the integration of activities as it continues to increase production rates from Prominent Hill.

Back in August, the OZ Minerals Board approved construction of a hoisting shaft at Prominent Hill, paving the way for a mine life extension and throughput expansion.

Coming with a pre-production capital expenditure of A$600 million ($449 million), the Wira Shaft expansion project will see the underground production rate increase to 6 Mt/y from 2025. At this point, the average annual copper and gold production is expected to be circa-54,000 t and circa-108,000 oz, respectively, some 23% more than expected in the current trucking operation.

Back then, OZ said sinking of the shaft was expected to commence in the March quarter of 2022. Mining and installation of underground and surface infrastructure was scheduled for completion along with commissioning of the Wira shaft at the end of 2024, with nameplate capacity expected in the first half of 2025.

In an update last week, OZ said the shaft collar construction site works had commenced and were due for completion in January 2022.

“The award of the shaft sink contract followed after a lengthy period of Early Contractor Involvement working through various contractors’ proposals and then selecting the best for project outcome with reduced risk and an effective delivery period at an economic cost,” it said. “The designs for the shaft sinking equipment are progressing well. Orders have been placed on the mill runs for the headframe steel with delivery scheduled for December 2021.”

The shaft design comprises a 1,329-m-deep, concrete-lined shaft with a diameter of 7.5 m. Construction of the shaft will be via conventional strip and line method, with the sinking period approximately two years.

The shaft mine expansion also enables generational province potential with further mine life extensions possible as 67 Mt of resource remains outside the shaft expansion mine plan, OZ Minerals says. Further, an exploration program has also identified that mineralisation remains open at depth beyond the current resource boundary, potentially accessible via the shaft.

Prominent Hill produced 17,565 t of copper and 41,245 oz of gold in the September quarter.

ERM on executing the mining sector’s sustainability strategies

With sustainability close to the number one topic shaping the business landscape, the mining industry faces perhaps more scrutiny today than ever before. From stakeholder engagement to employee welfare and the emissions generated from using mined commodities, there is a spectrum of issues on which mining companies are judged. Not just by traditional critics such as NGOs, but increasingly by policymakers, investors and consumers themselves.

As a result, mining companies are seeking the advice of consultants that live and breathe environmental, social and governance (ESG) issues to adapt to this evolving backdrop (see the mining consultants focus in IM October 2021 for more on this).

In this regard, they don’t come much bigger than ERM, which calls itself the largest global pure play sustainability consultancy. With a remit that goes into strategic, operational and tactical challenges, the company’s services have been in serious demand of late.

Louise Pearce, ERM Global Mining Lead; Jonathan Molyneux, ERM Mining ESG Strategy Lead; Peter Rawlings, Low Carbon Economy Transition Lead; and Geraint Bowden, Regional Client Director – Mining, were happy to go into some detail about how the company is serving the industry across multiple disciplines.

In demand

According to the four, there is increasing demand for services from miners interested in energy/battery minerals (lithium, cobalt, nickel, copper, platinum, palladium and rhodium (PGMs)) on the back of rising numbers of new mines coming onto the scene, “shorter supply chains to customers”, the perceived need to secure domestic supply of these minerals, and requirements of “evidence of responsibly-produced certifications from industry organisations such as the Initiative for Responsible Mining Assurance (IRMA)”.

Such trends have been underwritten by a shift in both the requirements and considerations around the extraction of these minerals, according to Molyneux.

“In the last five to seven years, the main ESG incentives for change have come from access to capital (ie investor ESG preferences, especially in relation to catastrophic incidents),” he said.

“Over the last three years, we have seen a strong rise in expectations from downstream customers, particularly leading brands.”

Jonathan Molyneux, ERM Mining ESG Strategy Lead

Automotive original equipment manufacturers like BMW and Daimler are placing sustainability at the centre of their brands, according to ERM. Their initial focus has been on ‘net-zero’ driving/electrification – and they have made progress on this with several major electric car launches. They then shifted to examining the carbon emissions and ESG, or responsible practices, of tier-one and tier-two component manufacturers. The last step has been a full analysis of the ESG credentials of input materials right back to source, ie the mine.

“We see a shift from the historic lens of customers managing supply risk by sourcing from organisations which ‘do little/no harm’ (eg human rights compliance, catastrophic incident avoidance) to supply partners that can contribute to the ‘do net good’ or ‘create value for all stakeholders’ (ie communities, workforce, nature positive),” Pearce said.

Such a shift has resulted in more clients considering “circular thinking” in their operational strategy, as well as carrying out risk reviews and transformation projects focused on a company’s social or cultural heritage. Tied to this, these same companies have been evaluating their water use, biodiversity requirements and, of course, decarbonisation efforts.

It is the latter on which the steel raw materials companies predominantly have been looking for advice, according to ERM.

The focus has been on ‘green’ iron ore, low-carbon steel and ‘circular’ steel, according to Molyneux and Bowden, with ERM providing input on how companies in this supply chain can integrate sustainability into their strategy and operations.

On the thermal coal side, meanwhile, it is a very different type of ERM service in demand: mine retirements, closure/local/regional regeneration transitions and responsible disposals.

Delivering on decarbonisation

The mining industry decarbonisation targets have come thick and fast in the last 18-24 months, with the latest announcement from the International Council on Mining and Metals (ICMM) seeing all 28 mining and metals members sign up to a goal of net zero Scope 1 and 2 greenhouse gas (GHG) emissions by 2050 or sooner, in line with the ambitions of the Paris Agreement.

Many have gone further than Scope 1 (direct emissions from owned or controlled sources) and Scope 2 (indirect emissions from the generation of purchased electricity, steam, heating and cooling consumed by the reporting company) emissions, looking at including Scope 3 (all other indirect emissions that occur in a company’s value chain) targets.

Fortescue Metals Group, this month, announced what it said is an industry-leading target to achieve net zero Scope 3 emissions by 2040, for example.

These are essential goals – and ones that all interested parties are calling for – in order to deliver on the Paris Agreement, yet many miners are not yet in the position to deliver on them, according to Pearce, Molyneux, Rawlings and Bowden.

“Miners need to look at decarbonisation at a holistic level across their operations and value chain, and cannot just delegate the net zero requirements to individual assets,” Rawlings said. “The solutions needed require investment and are often at a scale well beyond individual assets/sites.”

Much of this decarbonisation effort mirrors other industries, with the use of alternative fuels for plant and equipment, accessing renewable electricity supplies, etc, they said.

Process-specific activities can present challenges and is where innovation is required.

“These hard to abate areas are where a lot of efforts are currently focused,” Rawlings said.

Tied into this discussion is the allowance and estimates made for carbon.

There has been anecdotal evidence of miners taking account of carbon in annual and technical reports – a recent standout example being OZ Minerals inclusion of a carbon price in determining the valuation of its Prominent Hill shaft expansion project in South Australia – but there is no current legislation in place.

“We are seeing a broad spectrum of price and sophistication (targeted audience, knowledge level), but it is an active board level discussion for most clients,” Bowden said on this subject. “Most clients view this as market-driven requirements as opposed to a voluntary disclosure.”

This has been driven, in part, from the recommendations of the Task Force on Climate-Related Financial Disclosures, which many miners – including all the majors – are aligning their reporting with.

Some clients are also looking into scenarios to work around carbon regimes such as the Carbon Border Adjustment Mechanism, which proposes a carbon-based levy on imports of specific products.

Having acquired several companies in recent months focused on the low carbon economy transition – such as E4tech, Element Energy and RCG – ERM feels best placed to provide the technical expertise and experience to deliver the sustainable energy solutions miners require to decarbonise their operations.

“With these companies, combined with ERM’s expertise, it means we can support clients on the decarbonisation journeys from the initial strategy and ambition development through to implementation and delivery of their roadmaps,” Rawlings said. “We can support clients from boots to boardroom as they assess decarbonisation options and technologies; help them understand the financial, policy and practical aspects linked to deployment of solutions; and access the financing necessary to support deployment.”

ESG dilemmas

There is more to this evolving backdrop than setting and meeting ambitious environmental goals, yet, in ERM’s experience, the advice provided by consultants – and requested by miners – has historically been focused on individual ESG domains.

“This has often been driven by their realisation that their (miner’s) in-house policies and standards require updating,” Pearce said.

Louise Pearce, ERM Global Mining Lead

A siloed or disaggregated approach to ESG strategy development often reduces risk, but rarely generates value for the enterprise at hand, according to Pearce.

“What we have learned is that in order for organisations to create value, they need to focus on value drivers for the corporation,” she said. “These value levers are typically influenced by an integrated suite of ESG dimensions. For example, this could be looking at carbon emissions, connected with water use and nature, connected with local socio-economic development.”

“Sustainability and ESG are about understanding the inter-relationships between our social, natural and economic environments over the longer term. It cannot be about addressing one topic at a time or responding to the loudest voices.”

This is where ERM’s ‘second-generation’ ESG advice, which is driven by data and opportunities to create value as well as manage risk, is fit for the task.

“We are also finding that, at its heart, the central issue to second-generation ESG performance delivery/improvement for our clients is not just the strategy, but a willingness of organisations to reflect on their core values, how these have driven their traditional approaches and decisions and how they will need to evolve these if they want to achieve a genuine brand and reputation for ESG and achieve impact on the value drivers they have selected,” she added.

Such thinking is proving definitive in ERM’s mining sector mergers and acquisition due diligence.

“We have multiple experiences where clients have asked us to carry out an ESG review of a target portfolio, only to find that there is too great a gap between the target’s ESG asset footprint to align them with the client’s standard – or, that the carbon, water, closure or tailings profile of the target carries a too high-risk profile,” Molyneux said.

This is presenting clients with a dilemma as they want to increase their exposure to certain minerals, but are, in some instances, finding M&A is a too high-risk route. At the same time, the lead time to find and develop their own new assets is longer than they would wish for building market share.

Such a market dynamic opens the door for juniors looking for assets early in their lifecycles, yet it places a high load on the management teams of these companies to think strategically about the ESG profile of the asset they are setting the foundations for to eventually appeal to a potential acquirer.

“This is, in itself, a dilemma because, typically, the cash scarcity at the junior stage leads management teams to focus on the immediate technical challenges, sometimes at the cost of also addressing the priority non-technical challenges,” Bowden said.

Those companies who can take a strategic view on the ESG requirements of the future – rooted in a deep understanding of how to deliver change on the ground – will be best placed in such a market, and ERM says it is on hand to provide the tools to develop such an appropriate approach.

(Lead photo credit: @Talaat Bakri, ERM)

OZ Minerals Board gives go ahead for shaft expansion at Prominent Hill

The OZ Minerals Board has approved construction of a hoisting shaft at the Prominent Hill copper-gold mine in South Australia, paving the way for a mine life extension and throughput expansion.

Prominent Hill mine began operation in 2009 as an open pit and is now an underground mine producing 4.5 Mt/y, moving to 4.5-5 Mt/y from 2022 via a trucking operation.

Coming with a pre-production capital expenditure of A$600 million ($436 million), the Wira Shaft expansion project will see the underground production rate increase to 6 Mt/y from 2025. At this point, the average annual copper and gold production is expected to be circa-54,000 t and circa-108,000 oz, respectively, some 23% more than expected in the current trucking operation.

The study leverages close to 100 Mt of mineral resources outside the previous Prominent Hill ore reserves of 38 Mt of underground material.

Sinking of the shaft is expected to commence in the March quarter of 2022. Mining and installation of underground and surface infrastructure is scheduled for completion along with commissioning of the Wira shaft at the end of 2024, with nameplate capacity expected in the first half of 2025.

The shaft design comprises a 1,329-m-deep, concrete-lined shaft with a diameter of 7.5 m. Construction of the shaft will be via conventional strip and line method, with the sinking period approximately two years.

The shaft mine expansion also enables generational province potential with further mine life extensions possible as 67 Mt of resource remains outside the shaft expansion mine plan, OZ Minerals says. Further, an exploration program has also identified that mineralisation remains open at depth beyond the current resource boundary, potentially accessible via the shaft.

Announcing the expansion today, OZ Minerals Chief Executive Officer, Andrew Cole, said: “We are thrilled to see a long and productive future for Prominent Hill with the Wira shaft mine expansion enabling access to areas previously thought uneconomic and opening up potential new prospects.

“Prominent Hill is a quality orebody and remains open at depth. The reliable performance of the operation and its consistent resource to reserve conversion rate were all influential in the decision.”

For the first time, the company has used a carbon price in determining the project valuation, a practice it plans to adopt in other OZ Minerals projects going forward, Cole said.

The company plans to reduce its underground loading fleet to eight vehicles, from nine after the shaft expansion, with its trucking fleet going from circa-14 to five, post-shaft.

Scope 1 emissions intensity per tonne of concentrate are also expected to drop from 0.47 t CO2-e/t to 0.28 t CO2-e/t after the shaft installation.

The pre-production capital of A$600 million, which was an increase on the A$450 million outlined in the November 2020 expansion study, enables transformation of the site in line with the strategic aspirations of OZ Minerals, it said.

Provisions have been included in site capital projections to support this transformation, including progressing underground fleet electrification, upgrading some of the existing infrastructure, remote operation capability and automation.

The company expanded on this: “A battery-powered mining fleet is part of the future vision as OZ Minerals moves towards its zero-carbon emission aspiration. For this study, diesel trucks were assumed. However, installation of enabling infrastructure is included in the Prominent Hill Expansion case to minimise future disruptions when the switch to an electric fleet occurs. This, implemented as part of the asset’s site-wide electrification aspiration, would contribute to a further reduction in Scope 1 emissions.”

A pilot study is also being undertaken to review a low-energy dry grinding option. The Prominent Hill Expansion Study is not directly connected to, nor dependent on this ongoing work, however, the work presents potential future cost reduction and other opportunities, OZ Minerals said.

OZ Minerals, Titeline investigate hydrogen-powered surface diamond drilling opportunities

OZ Minerals, in partnership with Titeline Drilling, has commenced a trial to test a hydrogen direct injection system to improve engine combustion efficiency for surface diamond drill rigs.

The system has the potential to reduce emissions of greenhouse gases and particulates, as well as improve fuel consumption, according to the company.

The news came out with the release of the company’s June quarter results, which saw a 22% quarter-on-quarter uplift in copper production following a strong performance from the company’s South Australian operations (Prominent Hill and Carrapateena).

In addition to the trial of hydrogen-powered surface drill rigs, OZ Minerals said the mining tri-alliance it has in place with Byrnecut and Sandvik – designed to identify and introduce smart and innovative ideas – had progressed during the quarter, with in-roads made on several associated projects.

Significant work was undertaken towards trialling the use of tele-remote loading of trucks, which has now been implemented in a key stope in July, it said.

OZ Minerals previously said it was working with Byrnecut and Sandvik to roll out Sandvik’s AutoMine® platform at its Prominent Hill copper-gold mine in South Australia. This followed a project between the two to implement an automation upgrade for a Sandvik DD422i development drill at the operation.

OZ Minerals, Byrnecut, Sandvik working on remote LHD operation at Prominent Hill

OZ Minerals says it is working with Byrnecut and Sandvik to roll out Sandvik’s AutoMine® platform at its Prominent Hill copper-gold mine in South Australia.

As part of these efforts, a new system has been installed in the company’s Adelaide office that allows an operator to remotely to control a Sandvik LHD underground at Prominent Hill – over 600 km away – as if they were directly onsite.

Back in April when announcing the delivery of its 100th loader connected to AutoMine in the Asia Pacific region, Sandvik Mining and Rock Solutions said it had recently demonstrated the capability to simultaneously control or monitor multiple machines from the comfort and safety of a remote control room in a successful trial of a LH621i LHD at Prominent Hill.

“The LH621i was successfully operated from the Remote Operating Centre in OZ Mineral’s Adelaide office, taking OZ Minerals a step closer to realising its goal of remote operations from home,” it said.

The three companies, in 2020, successfully navigated COVID-19 challenges to implement an automation upgrade for a Sandvik DD422i development drill  at Prominent Hill. This saw Byrnecut Australia become the first underground operator in the world to successfully use a new automation and tele-remote package for Sandvik development drills.

Sandvik delivers 100th automated loader in APAC region

Sandvik Mining and Rock Solutions says it has delivered its 100th loader connected to the AutoMine® platform in the Asia Pacific region.

A Sandvik LH621i loader was delivered to Byrnecut Australia in March, making it Sandvik’s 100th automated load and haul unit to be delivered in APAC.

Sandvik has 30 AutoMine systems installed across Australia, Papua New Guinea and the Philippines, with customers including Barminco, OceanaGold, Redpath, and Byrnecut, who now have 11 sites in Australia connected to AutoMine. The first AutoMine system in the region was delivered and commissioned in 2008 for Mount Isa Copper Operations, now owned by Glencore.

AutoMine is Sandvik’s automation system for autonomous and tele-remote operation for a wide range of Sandvik and non-Sandvik underground and surface equipment. It provides a safe and controlled process to increase mine productivity and profitability, as well as protect operators and other mine personnel in underground and surface operations.

AutoMine can be scaled from tele-remote or autonomous operation of a single machine to multi-machine control and full fleet automation with automatic mission and traffic control capability. Operators can simultaneously control or monitor multiple machines from the comfort and safety of a remote control room, Sandvik says.

Sandvik recently demonstrated this capability with the successful trial remote operation of a LH621i loader at OZ Minerals’ Prominent Hill mine in South Australia. The LH621i was successfully operated from the Remote Operating Centre in OZ Mineral’s Adelaide office, taking OZ Minerals a step closer to realising its goal of remote operations from home.

“The digitalisation field has developed significantly over the years and we have adapted to meet the industry needs along the way,” Sandvik Mining and Rock Solutions Technical Support Manager – Mine Automation, Ty Osborne, said.

“We have seen our customers change their mindset from ‘this technology is nice but won’t work in our mine’, to, ‘what do have to do to make this work in our mine?’. Our customers are now seeing the value of including digitalisation in their mine planning and recognise the tangible benefits an automated fleet can bring to their operation.”

Byrnecut adds Carrapateena to OZ Minerals underground contract mining portfolio

OZ Minerals Ltd has changed underground mining contractor at its Carrapateena copper-gold mine in South Australia following Downer EDI’s move to divest its mining services businesses to MACA.

The company has now signed an agreement with Byrnecut Australia for the delivery of underground mining and associated mining services at Carrapateena. The two companies know each other well, with Byrnecut already carrying out underground mining services at OZ Minerals’ Prominent Hill for the past 10 years.

The five-year alliance-style contract with Byrnecut is valued at circa-A$130 million/y ($101 million/y), OZ Minerals said. Byrnecut has already commenced a seven-week mobilisation to the Carrapateena site and will assume full responsibility for mining services delivery from March 4, 2021.

“OZ Minerals, Byrnecut and Downer will work together during the transition period to ensure continuity of operational performance and development, and employee support and opportunities, with the objective of providing roles for the majority of the incumbent underground workforce,” the company said. “This transition will include the transfer of equipment from Downer to Byrnecut.”

Byrnecut will now provide underground mining services to both the Carrapateena and Prominent Hill mines.

“Byrnecut is a proven top-tier underground mining contractor who has been providing underground mining services to Prominent Hill for the past 10 years, with their Prominent Hill contract having been renewed in 2020,” OZ Minerals said.

The scope of work comprises all underground mining activity for the duration of the contract including production and development mining and associated mining services; and bedding in steady-state operations at nameplate site capacity.

Byrnecut, OZ Minerals and Sandvik achieve teleremote drilling first

Contract miner Byrnecut Australia has become the first underground operator in the world to successfully use a new automation and teleremote package for Sandvik development drills.

Byrnecut introduced a Sandvik DD422i development drill featuring the package to OZ Minerals’ Prominent Hill gold-copper mine, southeast of Coober Pedy, South Australia, in March.

With COVID-19 travel restrictions preventing Sandvik staff from attending site, Byrnecut, OZ Minerals and Sandvik experts collaborated via phone, teleconference and email to complete remote commissioning of the rig.

The two-boom rig, which can be monitored and controlled from the surface and features a sophisticated boom-collision-avoidance system, has now been in operation for three weeks, according to the companies.

Byrnecut Australia Managing Director, Pat Boniwell, says the new automation features allow for enhanced drill operation across shift changes – a period when, historically, development drilling has stopped or been significantly reduced.

“We’re conservatively looking at a 10% increase in productivity with this machine through being able to drill extra holes and the machine being used more consistently,” he said. “It picks up on the deadtime, and if it does stop for any reason we’re able to remotely reset it.”

The new boom collision avoidance system means both of the rig’s drill booms can be left in operation during shift change – something that was previously not possible. In the first few weeks of operation, the drill has been able to drill 60-70 holes while being operated autonomously and remotely from surface, the companies said.

General Manager of OZ Minerals Prominent Hill operations, Gabrielle Iwanow, says when Byrnecut approached her about trialling the upgraded development drill, she was immediately interested.

“OZ Minerals is a modern mining company,” she said. “We’re interested in innovation and looking for safer, faster, and more efficient ways of doing our work.”

Iwanow said the commissioning of the drill in such trying times is a true credit to all those involved and the positive working relationship between OZ Minerals, Byrnecut and Sandvik.

Byrnecut Drill Master, Noah Wilkinson, says a solid working relationship with Sandvik and good communication contributed to the success of the commissioning.

“People from the Sandvik factory in Finland were able to remote into the machine over the internet and adjust settings that were stopping some of the functions from working,” he explained.

Sandvik’s Global Account Manager for Byrnecut, Andrew Atkinson, paid credit to Byrnecut’s openness to adopting autonomous technologies in areas including development drilling, loader operation, production drilling and ore trucks, which are all engineered for compatibility with Sandvik’s AutoMine® and OptiMine® products.

In addition to the collision avoidance and teleremote capabilities of the DD422i, the new automation package allows for semi-autonomous bit changing.

Another handy feature of the setup during the current period of social distancing has been the virtual network computing capability that allows the control panel of the drill to be viewed remotely on a tablet. This means that during operator training, the instructor need not be in the cabin with the operator.

Outotec to deliver ‘unique’ paste backfill plant to OZ Minerals’ Prominent Hill mine

Outotec says it has been awarded a contract to design and deliver a mine paste backfill system to OZ Minerals’ Prominent Hill copper-gold mine, in South Australia.

The contract price is €15 million ($16.5 million) and it has been booked into Outotec’s 2019 June quarter order intake, the mineral processing company said.

Outotec’s supply includes the design and delivery of a complete paste backfill system, as well as detailed design of the underground distribution network and fill management systems, it said.

The new paste backfill plant will be based on a unique process design, which allows flexibility to use continuously produced fresh tailings or store filter cake to meet the future backfill needs of the underground mining operation, Outotec said. The new facility is expected to have a capacity of 215 m³/h.

“A reliable paste backfill system is critical to the whole mine and its operations. We are pleased to support our customer to improve their tailings management in a sustainable way,” Kimmo Kontola, Head of Outotec Minerals Processing Business, said.

Prominent Hill is a copper-gold mining operation made up of the Malu open-pit mine – which concluded operations last year – the Ankata and Malu underground deposits and a conventional crushing, grinding and flotation processing plant.

Outotec has previously delivered an EPC backfill system, plus build own operate backfill plant for ongoing operation at Prominent Hill.

 

Adelaide Brighton cements contract extension with OZ Minerals at Prominent Hill

ASX-listed Adelaide Brighton has announced the signing of a contract with OZ Minerals for the continuation of cement supply to the Prominent Hill copper-gold operation in South Australia.

The contract period is for a five-year term with options to extend, Adelaide Brighton said.

In addition to the supply of cement, Adelaide Brighton will also supply aggregate and sand from the company’s Sellicks Hill Quarry and Price sand operation as well as auxiliary logistics services, it said.

Adelaide Brighton CEO, Nick Miller, said: “The contract, which now also includes aggregate and sand supply for the Prominent Hill operation, reflects the company’s competitive offering of a broad range of products in the South Australian market.”

Prominent Hill is a copper-gold mining operation in northern South Australia, which is made up of the Malu open-pit mine – which concluded operations last year – the Ankata and Malu underground deposits and a conventional crushing, grinding and flotation processing plant.