Tag Archives: TNG Ltd

TNG brings Clough into Mount Peake Peake vanadium-titanium-iron project fold

TNG Ltd has appointed a subsidiary of engineering and construction company, Clough, to work with TNG’s project development team and the SMS Group on its flagship Mount Peake vanadium-titanium-iron project in the Northern Territory of Australia.

TNG announced in September that it had decided to progress development of the project with a fully-integrated mining and processing operation within its existing mining leases. As part of this strategy, it was considered by the TNG team important to have a suitable Australian-based engineering group on board.

Following a tender process, Clough Projects Australia Pty Ltd was selected to work with TNG’s team to initially develop an optimised plant layout for the integration of the TIVAN® processing facility (TPF) and beneficiation plant at the mine site, on the basis of the deliverables prepared under the front-end engineering and design (FEED) study completed by SMS group.

Clough, TNG says, will work with SMS and TNG’s team given the severe restrictions on travel between Europe and Australia due to the COVID-19 pandemic that have impacted SMS’ ability to deliver a team in Australia.

TNG previously engaged Clough to assess the definitive feasibility study for the project and this new contract expands on this early work to progress the overall mine development, it says.

The optimised layout will be unconstrained compared with the size and shape requirements at the former Darwin site. This offers the potential to capitalise on improving constructability, operability and maintenance for the project, as well as further cost optimisations from integrated infrastructure, the company says.

The integrated plants will be positioned within the company’s existing Mining Lease 29855, which has a size of 1,460 ha. This area is capable of hosting a fully-integrated operation encompassing mining activities and waste storage, the beneficiation plant, the TPF and non-process infrastructure, according to TNG.

TNG’s Managing Director & CEO, Paul Burton, said: “From a strategic and logistical perspective given the continued global COVID-19-related travel restrictions, it is an advantage to have a locally-based engineering group working on this phase of the Mount Peake project with TNG and SMS.

“We expect the integrated plant layout will pave the way for further optimisation work that will tie back into the recently completed FEED study. These work programs are already underway. We look forward to working closely with Clough and our other engineering partners to rapidly advance the Mount Peake project.”

Located 235 km north of Alice Springs, Mount Peake is expected to be a long-life project producing a suite of high-quality, high-purity strategic products for global markets including vanadium pentoxide, titanium dioxide pigment and iron ore fines. The project, which is expected to be a top-10 global producer, has received Major Project Status from the Northern Territory and Federal Governments.

TNG “de-risks” Mount Peake vanadium-titanium-iron project with SMS contract

TNG has signed up SMS Group to carry out the front-end engineering and design (FEED) phase of its Mount Peake vanadium-titanium-iron project in the Northern Territory of Australia.

The mandate for the contract encompasses the Mount Peake concentrator, the TIVAN® processing plant and all associated plant and equipment.

The two companies have been working together on the TIVAN process for some time. The process, developed by the two companies and Perth, Australia-based metallurgical consultants METS and the CSIRO, has been primarily designed for hydro-metallurgical extraction of vanadium, preferably as vanadium pentoxide, from a titano-magnetite orebody and also for separating the titanium and iron, preferably as ferric oxide and titanium dioxide.

The process has undergone more than six years of development including several successful pilot plant test stages, and is designed to use conventional and existing equipment currently used in extractive resources, TNG says.

In addition to the FEED contract for the process, plant and equipment, SMS’ scope will include providing a proposal for full procurement and construction, including the balance of plant and equipment to be provided on a turnkey, single-source, fixed price EPC basis.

Under the contract, SMS will now design and engineer the entire processing flowsheet for Mount Peake, which includes the concentrator, where magnetite concentrate is to be produced, and the downstream processing plant, where three high-purity products – vanadium pentoxide, titanium dioxide and iron oxide – will be produced.

Interestingly, SMS has agreed to provide to TNG production quantity, production rate and production quality guarantees, elements TNG Managing Director Paul Burton (pictured, left) said would significantly “de-risk” the project.

SMS’s responsible Managing Director Herbert Weissenbaeck (pictured, right) said the agreement was the logical next step in the development of TIVAN and Mount Peake – “which together have the potential to essentially disrupt the TiO2 pigment and vanadium space”.

The downstream processing plant will use TNG’s 100%-owned TIVAN process. The scope of work for the plant will include a titanium pigment plant – to be developed in collaboration with its nominated sub-contractor Ti-Cons.

An updated definitive feasibility study on Mount Peake from 2017 envisaged pre-production capex of A$853 million ($617 million) for a 3 Mt/y project ramping up to 6 Mt/y in year five. This would see 24.3 Mt of magnetic concentrate turned into 10.6 Mt iron oxide and 243,000 t of vanadium oxide.