Centinela becomes first Antofagasta mine to gain Copper Mark credentials

Centinela, in Chile, has become the first of the Antofagasta’s mines to obtain the international Copper Mark, an assurance framework that certifies the company operates under strict internationally recognised sustainable production standards, the copper miner says.

Zaldívar (owned 50:50 by Antofagasta and Barrick Gold) expects to obtain the Copper Mark next month and the group’s other two mining operations, Los Pelambres and Antucoya, will shortly begin their own certification processes, Antofagasta said.

Iván Arriagada, Chief Executive Officer of Antofagasta plc, said: “The importance of obtaining this certification lies in Antofagasta’s commitment to modern and sustainable mining, which transparently incorporates the best practices of the global mining industry.”

Inspired by the UN Sustainable Development Goals, the Copper Mark takes a comprehensive approach to sustainability and includes the verification of activities at the sites where copper is produced, the miner said. To this end, it requires compliance with 32 criteria in five categories: business and human rights, community, labour and working conditions, environment and governance.

Copper Mark follows up its original certification with a further review within one year, and then every three years thereafter to certify ongoing compliance with the criteria. In this way, Copper Mark offers workers, investors, copper end-users and communities a simple and credible way to verify sustainable practices, the company said.

Carlos Espinoza, General Manager of Centinela, said: “After a rigorous process, involving self-assessment and an independent audit, we are very proud to be the first mining operation in the company to obtain the Copper Mark, which certifies that our operating and other processes are carried out in accordance with the best sustainability practices in the industry.”

SENET wins EPCM gig at AMAK’s Moyeath copper-zinc project in Saudi Arabia

Al Masane Al Kobra Mining Co (AMAK) has awarded SENET, a wholly owned subsidiary of DRA Global, the engineering, procurement and construction management (EPCM) contract for the design and execution of the Moyeath copper-zinc project in the Kingdom of Saudi Arabia, SENET says.

AMAK has been producing copper, zinc in concentrate and gold and silver in doré from its operations in the country since 2012.

Moyeath is a third major orebody (together with Saadah and Al Houra) discovered in the immediate vicinity to the AMAK underground mines. The Moyeath orebody is a high-grade copper-zinc volcanogenic massive sulphide deposit, SENET says.

The planned 400,000 t/y run of mine flotation process plant will produce copper and zinc concentrates, while filtered tailings will be trucked to an existing dry stacking area operated by AMAK, which handles tailings from its Al Masane (pictured) and Guyan process plants.

Preliminary test works shows it is possible to produce saleable copper and zinc concentrates, with most of the gold and silver reporting to flotation concentrates, SENET noted. The mineralogy of the Moyeath orebody is complex and requires a similarly complex approach to produce copper and zinc concentrates at favourable recoveries and saleable concentrate grades.

Trevali to test out FLSmidth’s Rapid Oxidative Leach tech on Caribou material

Trevali Mining has announced the commencement of a pilot plant testing program using Caribou run-of-mine and milled material at FLSmidth’s Rapid Oxidative Leach (ROL) process testing facility in Salt Lake City, Utah.

The program expands on previous laboratory test work and is aimed at demonstrating the potential to recover zinc, lead, copper, gold and silver as a precipitate or metal and additional zinc and lead from Caribou ore and mill tailings.

The leach test program is targeting an improvement to zinc, lead, copper, gold and silver metal recoveries, the potential to produce a precipitate or metal on site replacing the current ore concentrate that is produced at Caribou – which, if implemented, would lead to savings on transport costs and offsite treatment costs – and the opportunity to process historic mill tailings, which include gold and copper metals, in addition to run of mine ore. The latter would increase revenues and reduce closure liabilities, Trevali said.

Trevali says the use of FLSmidth’s ROL technology also provides the potential to reduce Trevali’s carbon footprint at Caribou and extend Caribou’s mine life and treat lower-grade deposits in the Bathurst camp of Canada.

FLSmidth says ROL leaches 97-99% of copper directly on-site in six to eight hours, from concentrates as low as 5% Cu. In gold, ROL has the potential to unlock the value of undeveloped refractory gold deposits with less than 3 g/t gold head grade, it says.

Unlike other refractory processing techniques, the ROL process uses the application of mechanical energy coupled with oxidation under atmospheric conditions. The process relies on stirred media reactors to accelerate the oxidation of sulphide minerals. This eliminates the need for ultrafine grinding, high temperatures and high pressure which makes it energy saving and very cost-effective, according to the mining OEM.

Trevali said a successful pilot plant test program using ROL may allow Trevali to replace the existing flotation circuit at Caribou with atmospheric leach vessels and potentially an SX/EW train, introducing the possibility of producing base and precious metals on-site and thereby save transport costs and offsite treatment costs.

Conceptual objectives of the program include:

  • Recovery of metals/minerals that are not recoverable using the current technology at Caribou (precious metals and magnetite); and
  • Improved payables/selectivity of the traditional flotation process using new and emerging technologies.

Ricus Grimbeek, President and Chief Executive Officer of Trevali, said: “FLSmidth’s ROL metallurgical technology has the potential to transform the Caribou mine and the wider Bathurst Mining Camp.

“This next phase of the testing program is an essential step in evaluating the suitability and economic viability of a processing solution with the potential to enhance the value of the in-situ material and tailings at Caribou as well as the surrounding deposits in the Bathurst region. The positive results to date support further study and analysis given the potential implications for the Bathurst Mining Camp in general and Trevali in particular.”

Beyond quantifying the ability to recover additional metal values, the objective for the pilot plant test program is to determine the various kinetic factors, mass and energy balance and engineering data to support future engineering on a preliminary economic assessment for potential processing of the Trevali mill feed and mill tailings and produce metal on site.

Continuous pilot plant trials commenced in June 2021 (Phase 1) to tune the pilot plant and provide material for precious metal leach tests in late July, followed by a test program at the Caribou Mine site that is planned for September 2021 (Phase 2). Leach data and results are expected to verify that batch testing results can be achieved in a continuous operation.

New Gold to collaborate with MineSense in underground ore sorting move

MineSense is gearing up for a move underground with the help of New Gold and its New Afton gold-copper mine in British Columbia, Canada.

The Vancouver-based technology company has already established and proven its ShovelSense technology for the open-pit mining sector, with its X-ray Fluorescence (XRF) sensor-based system now operating on shovels, wheel loaders and excavators on a commercial basis across six operating mines. This includes large installations at Teck’s Highland Valley and Copper Mountain’s copper operations in BC, as well as one ShovelSense unit at the Antamina copper operation in Peru.

Designed for operation in extreme environments and retrofits on any existing mobile equipment, ShovelSense units come equipped with a human machine interface and proprietary algorithms that measure and report ore grade/characteristics. They can also connect directly to fleet management or other existing control software systems, enabling mine operators to reconcile geological block models with actual ore grade data.

Having finetuned the system for above-ground operations, the company is now embarking on its underground move, according to MineSense President and CEO, Jeff More.

A trial of the underground ShovelSense system at New Gold’s New Afton mine is first up to complete product development. The company will be installing a unit on a Cat R1600G LHD for this step. This will be followed closely by installation at a “large entity” in Chile – with More anticipating start up in the September or December quarter.

The development agreement with New Gold at the BC-based mine is looking to trial and finetune the system for underground operations, with More confident the ShovelSense system will stand up to the test.

“The core technology – all of the algorithms, software, hardware – is the same as ShovelSense for open-pit mining,” More said. “It is the ‘application package’ – looking at how we can attach the unit to the machine and protect it in an underground environment – that is what we have to test out. The design for this is already complete; it’s just a matter of trialling it.”

New Afton represents a good test for the system.

New Afton is Canada’s only operating block cave mine, with the New Afton deposit part of a larger copper-gold porphyry district in the region. The operation regularly mines 15,000-16,000 t/d of ore and waste, with the majority of this currently going to the mill.

The company has already pursued “ore segregation” projects to boost the grade of material being fed through to the processing side, but the move into the higher-grade C-Zone in 2023-2029 will place an even greater emphasis on ore/waste boundaries and milled tonnes at the operation.

At the same time, the ShovelSense deployment at New Afton will represent the first time MineSense has sent a unit into a mine that has so much payable gold, with most operations the company has worked on being primarily base metal-oriented.

In 2020, New Afton produced 64,000 oz of the yellow metal, along with 32,659 t of the red metal.

“This will be the first time we’re touching gold at this level; we have other mines that have payable gold but not at that level,” More explained.

In New Afton’s case, sampling and historical data has proven that the orebody’s copper and gold ratios tend to be consistent and unchanging over the long term. With this knowledge, New Afton has used technology in the past to determine the copper value and make ore/waste production decisions. ShovelSense allows New Afton to move the ore/waste production decision to the drawpoint, according to MineSense. This reduces mixing and blending during the crushing and conveying circuit which can homogenise the material to the point where it is not worth segregating.

Trialling new technology such as this is nothing new for New Afton.

The operation already uses automated loading through Sandvik’s AutoMine solution, is employing electrification with the use of Sandvik and MacLean Engineering battery-powered mobile equipment, and, in the process plant, has Gekko Systems’ highest volume InLine Pressure Jig IPJ3500 to improve gravity concentration.

More says the ShovelSense unit could be in the Cat LHD bucket at New Afton in August, with the machine then going through an above-ground trial ahead of the underground transition at the end of September.

“By early Q4, we should have completed the pilot,” he said.

Sandvik’s i-series truck set to start work at OZ Minerals’ Pedra Branca

Sandvik has recently delivered its first i-series truck to Brazil, with the 45-t payload TH545i heading to OZ Minerals Brazil’s Pedra Branca copper mine in Pará in the northern part of the country.

The model has automation features that bring more productivity and safety to the operation, according to Sandvik. Compared to its predecessor, the Sandvik TH540, the truck offers a significant capacity increase by carrying 5 t more. The truck’s standard engine power, meanwhile, increased to 450 kW, from 405 kW, to maintain the same speed with the increased payload.

Other equipment will be delivered to the Pedra Branca mine over the next few months, with, in all, five different models of drilling, loading and transport equipment making up the “modern and complete fleet”, Sandvik said.

The new fleet additions are all part of OZ Minerals’ ramp-up efforts at the underground mine, which is targeting increased mining from ore stopes from the June quarter onwards.

Ivanplats to trial Epiroc battery-electric drills and LHDs at Platreef mine

Epiroc says it has won a significant order for battery-electric mining equipment from Ivanplats that will be used to develop its greenfield Platreef mine in South Africa in the “most sustainable and productive manner possible”.

Ivanplats, a subsidiary of Canada-based Ivanhoe Mines, has ordered several Boomer M2 Battery face drill rigs and Scooptram ST14 Battery LHDs (pictured).

These machines will be trialled during the Platreef underground mine’s initial development phase, Epiroc said, adding that Ivanplats has the ambition to use all battery-electric vehicles in its mining fleet at Platreef.

The order exceeds ZAR150 million ($10.2 million) in value and was booked in the June quarter of 2021.

Ivanhoe indirectly owns 64% of the Platreef project through its subsidiary, Ivanplats. The South Africa beneficiaries of the approved broad-based, black economic empowerment structure have a 26% stake in the project, with the remaining 10% owned by a Japanese consortium of ITOCHU Corporation, Japan Oil, Gas and Metals National Corporation, and Japan Gas Corporation.

The Platreef 2020 feasibility study builds on the results of the 2017 feasibility study and is based on an unchanged mineral reserve of 125 Mt at 4.4 g/t 3PGE+Au, project designs for mining, and plant and infrastructure as in the 2017 study; except with an increased production rate from 4 Mt/y to 4.4 Mt/y, in two modules of 2.2 Mt/y, for annual production of more than 500,000 oz of palladium, platinum, rhodium and gold; plus more than 35 MIb of nickel and copper.

The initial plan is to start at a mining rate of 700,000 t/y before scaling up. An updated feasibility study on the plan is expected to be published before the end of the year.

Helena Hedblom, Epiroc’s President and CEO, said it was “encouraging” that Ivanplats is considering going all battery-electric at Platreef.

“Battery-electric equipment is increasingly embraced by mining companies as it provides a healthier work environment, lower total operating costs and higher productivity,” she said. “The technology is now well established, and Epiroc is driving this change toward emissions-free mining.”

Marna Cloete, Ivanhoe Mines’ President and CFO, said: “We want to be at the forefront of utilising battery electric, zero-emission equipment at all of our mining operations. This partnership with Epiroc for emissions-free mining equipment at the Platreef Mine is an important first step towards achieving our net-zero carbon emissions goals while mining metals required for a cleaner environment.”

Boomer M2 Battery face drill rigs and Scooptram ST14 Battery loaders are built in Sweden, and are automation-ready and equipped with Epiroc’s telematics solution Certiq.

The equipment will be delivered early to Platreef in 2022. Epiroc will also provide on-site operator and maintenance training to Ivanplats, it said.

Epiroc intends to offer its complete fleet of underground mining equipment as battery-electric versions by 2025, and its full fleet for surface operations as battery-powered versions by 2030.

Perenti’s Barminco seals Savannah nickel project contract

Perenti Global’s hard-rock underground mining subsidiary, Barminco, has finalised a contract with Panoramic Resources for development and production works at the Savannah nickel project in the Kimberley region of Western Australia.

The finalised contract represents a value of around A$280 million ($208 million) over a four-year contract term, Perenti said.

Under the terms of the initial letter of intent, announced on the April 6, 2021, Barminco commenced mobilisation and early mining works ahead of the schedule. With finalisation of the contract, Barminco expects development and production works will ramp-up over the coming six months to achieve full run rate of revenue early in the March quarter of 2022.

The contract will be serviced by new underground mining equipment including the use of tele-remote mining equipment, expected to deliver both safety and productivity benefits, Panoramic said.

Ore processing at Savannah is scheduled to begin in November with first concentrate shipment from Savannah targeted for the following month, Panoramic said. The building of an ore stockpile on the surface has already commenced and the company plans for this to reach 100,000 t prior to turning on the processing plant.

Perenti’s Managing Director and CEO, Mark Norwell, said: “We look forward to working together with the team at Panoramic to develop what we all expect will be Australia’s next long-life nickel producing mine. Despite the challenging labour market conditions in Western Australia, we have been successful in mobilising a labour force of approximately 110 highly skilled underground employees. We expect this to increase to 170 as the project ramps up. Securing this labour force has enabled us to commence early works ahead of schedule.”

Savannah has outlined a 12-year mine life with an average annual production target of 9,072 t of nickel, 4,683 t of copper and 676 t cobalt in concentrate. The mine is set to operate at average site all-in costs of A$6.36/lb of payable nickel, net of copper and cobalt by-product credits and royalty payments. This equates to roughly $4.86/Ib or $10,714/t.

The operation, with more than A$100 million already invested, has been maintained since the suspension of operations in April 2020 with a view towards operational readiness and project optimisation. This includes the recent completion of the FAR#3 ventilation raise, underground capital development on four mining levels at Savannah North and ancillary capital works on surface and underground infrastructure, which are currently being completed, Panoramic says.

ANDRITZ ups the filtration ante with new ME2500 filter press

ANDRITZ has introduced a new filter press, the ME2500, to complete its range of “proven” A4F and the SE series filter presses for the mining and minerals industry.

The ME2500 is the best-fit for fast processing of tailings (also with high clay content) or mining concentrates like iron, copper, lead or zinc, the company says. The new model has an hourly processing capacity of up to 450 kg/sq.m, a filtration area of up to 840 sq.m, and features chained plates for faster filter cake discharge. These attributes enable the highest throughputs without compromising on safety, while reflecting a customer focus on saving water, ANDRITZ says.

The innovative closure system on the ME2500 largely replaces hydraulic components with electrical ones and further reduces cycle times, thus increasing capacity and operating availability.

“The increased use of electrical components enables highly sustainable operation of the filter press by reducing the amount of hydraulic oil needed, as well as improving safety thanks to more precise control and less reliance on high-pressure lines that are susceptible to leaks,” the company said.

In addition, and to further optimise the productivity of single machines or plants with multiple filter presses, all modules of the ANDRITZ intelligent filter press – controlled by the Metris addIQ control system – are also available for the ME2500 filter press and can be provided with the full range of options. This draws on smart sensors, data analytics and augmented reality, including multiple sensors to allow for online safety monitoring of the plate package and moveable parts.

The company concluded: “The safe disposal of tailings generated by the mining and minerals sector is a significant cost factor for the industry. ANDRITZ is known for its innovative range of overhead and sidebar filter presses that meet the industry’s most stringent requirements with regard to fast cake discharge and saving water and costs. The maintenance-friendly equipment from ANDRITZ is easily upgradeable, with a modular design for customised process solutions.”

Rio Tinto and Schneider Electric partner on decarbonisation initiatives

Rio Tinto and Schneider Electric have signed a memorandum of understanding (MoU) for a “first-of-its-kind” collaboration to develop a circular and sustainable market ecosystem for both companies and their customers.

This multi-product partnership will see Schneider Electric use responsibly-sourced materials produced by Rio Tinto. These include low-carbon aluminium and copper produced with renewable power, iron ore and borates. Rio Tinto will, in turn, use energy and industrial services from Schneider Electric, as the companies work together to develop digital platforms, technologies and solutions to be deployed across the metals and mining supply chain to drive further decarbonisation, they said.

Rio Tinto Chief Commercial Officer, Alf Barrios, said: “This unique partnership will help accelerate decarbonisation and renewable energy solutions by combining low-carbon materials with cutting-edge digital technology. Working together will allow Rio Tinto and Schneider Electric to pursue opportunities beyond what is possible for either company on its own.

“This collaboration also opens doors to consider strategic initiatives such as expanding the use of artificial intelligence and predictive analytics to reduce downtime in our plants, digitisation of our supply chains, and a host of other transformative technologies.”

Schneider Electric Executive Vice-President Industrial Automation, Barbara Frei, said: “We are excited to work with Rio Tinto to develop clean and pioneering solutions to meet industrial decarbonisation challenges. As the world’s most sustainable corporation and a manufacturer with a global network of smart factories and smart distribution centres, Schneider Electric is on a mission to make industries of the future eco-efficient, agile, and resilient through open, software-centric industrial automation and sustainable energy solutions. This new partnership demonstrates that Rio Tinto is as passionate as we are about bridging progress and sustainability for all.”

The partnership will draw on Schneider Electric’s Energy as a Service expertise to evaluate the use of innovative solutions, including microgrids, to supply energy from low-carbon sources, and artificial intelligence and advanced analytics to help meet sustainability goals at Rio Tinto sites and throughout its supply chain.

Rio Tinto’s START traceability and transparency initiative, the first sustainability label for aluminium using blockchain technology, will be deployed with Schneider Electric to unlock value for customers, suppliers and partners, it said. The companies will work to expand this transparency, offering START in combination with Schneider Electric’s EcoStruxure™ platform, an IoT system architecture that connects everything in an enterprise to deliver enhanced safety, reliability, efficiency and sustainability.

The companies will also partner to evaluate emerging innovation opportunities, such as the efficient production of critical materials for renewable technologies and advances in low-carbon, green steel manufacturing, both of which will play a significant long-term role in industrial decarbonisation.

Monadelphous Group banks engineering work with BHP, Rio and Codelco

Monadelphous Group Ltd has secured several new construction and maintenance contracts in the resources sector totalling around A$215 million ($163 million).

Included within this slate of new work is a contract for smelter campaign maintenance works at the BHP owned Olympic Dam copper mine in South Australia. Monadelphous said work will commence immediately and is expected to be completed in December 2021.

Monadelphous has also been awarded a two-year extension to its existing maintenance services contract at Olympic Dam. The contract scope includes civil, structural, mechanical, building maintenance and electrical services, as well as the addition of underground rail maintenance services.

In the iron ore sector in the Pilbara region of Western Australia, Monadelphous has been awarded several contracts, including several sustaining capital contracts under its panel agreements with BHP and Rio Tinto; and a contract with Rio for the provision of construction and support services associated with the Gudai-Darri iron ore project, with work expected to be completed by the end of 2021.

In Chile, the company’s maintenance and construction services business, Buildtek, has secured a number of new contracts, including a three-year contract with Codelco for the operations and maintenance of water infrastructure at the Chuquicamata underground mine in Calama. Buildtek has been providing these services on this site since 2018.

In addition, the engineering company has secured two new contracts with Codelco for maintenance activities associated with the concentrator plant at El Teniente mine in Rancagua; and a contract with BHP Minera Escondida for the construction of modularised pump stations and associated infrastructure of the Escondida copper mine in Coloso.

Finally, Monadelphous, in collaboration with global heavy lifting services company Fagioli, has secured a contract with NMT International (Australia) to deliver specialist heavy lifting and haulage services at the Iron Bridge magnetite project, a joint venture between Fortescue Metals Group subsidiary FMG Magnetite Pty Ltd and Formosa Steel IB. The strategic collaboration with Fagioli enables Monadelphous’ specialist Heavy Lift business to increase capacity and broaden capability for the Australian resources and energy markets, it said.