Tag Archives: Koodaideri

SCEE to electrify Rio Tinto’s Gudai-Darri iron ore mine

Southern Cross Electrical Engineering is to perform plant electrical and instrumentation works at the Rio Tinto-owned Gudai-Darri (formerly known as Koodaideri) iron ore mine site in Western Australia as part of a contract valued at over A$65 million ($48 million).

The agreement will see SCEE mobilise to the Pilbara site in late 2020, with completion of work planned for December 2021.

SCEE Managing Director, Graeme Dunn, said: “We are pleased to secure this significant award with such a longstanding and valued client as Rio Tinto for whom we have undertaken many successful projects in the Pilbara. This further boosts our already strong order book and will provide a solid base of construction work in the resources sector into the 2022 financial year.”

Earlier this month, Rio opened Western Australia’s newest airport at the $2.6 billion Gudai-Darri Stage 1 iron ore project (see photo, credit: Rio Tinto). The greenfield mine development, around 35 km northwest of the Yandicoogina mine in the East Pilbara mining region, will initially be developed as a nominal 43 Mt/y high-grade, dry processing operation, with start-up expected in early 2022.

Rio flying high at technologically advanced Gudai-Darri iron ore project

Western Australia’s newest airport has opened at Rio Tinto’s $2.6 billion Gudai-Darri (formerly known as Koodaideri) iron ore project in the Pilbara where construction is progressing ahead of expected production ramp-up in early 2022.

The facility can accept a range of different aircraft including Boeing 737s, A320s, F100s and King Airs. The current flight schedule includes four flights a week with additional flights expected to be added to the schedule next year. The airport is expected to handle more than 600 workers in a day at peak operating times, according to Rio.

The airport will deliver significant benefits in terms of minimising employee interaction with vehicles and driving, as well as helping to manage employee fatigue thanks to a significant reduction in travel time from an alternate regional airport, Rio says. The airport will also provide a safer landing option for Rio Tinto’s long-standing partner, the Royal Flying Doctor Service.

Rio Tinto Projects General Manager, Gudai-Darri, Anthony Radici, said: “You get a real sense of the immense size and scale of our Gudai-Darri operation once you fly into this new airport.

“The construction phase of the project is progressing well with a significant amount of infrastructure at the mine now built, millions of cubic metres of material moved, a new access road, a significant amount of the rail formation installed, two new bridges constructed and now a brand new airport.”

Rio Tinto Iron Ore Acting Chief Executive, Ivan Vella, said: “The construction phase of Gudai-Darri, our most technologically advanced mine, has a strong focus on supporting local businesses with contracts valued at more than $2.3 billion awarded to date.

“These contracts have supported approximately 2,000 jobs in the construction phase and the mining operation is expected to support about 600 jobs on an ongoing basis. We are proud to support West Australian businesses as we progress a pipeline of investment opportunities in the Pilbara valued at more than A$10 billion ($7.3 billion) over the three years to 2022.”

Contracts at Gudai-Darri valued at more than $2.3 billion have been awarded to local Pilbara, Pilbara Aboriginal and West Australian Businesses including Primero Group, NRW, DTMT, Pindan, White Springs, Hicks Civil & Mining and Karratha Earthmoving & Sand Supplies.

The full construction and design of the airport will be completed by local partners Primero Group, NRW, Worley and GHD, together with NRW subcontractors Colas, Fulton Hogan, TEC services, Brookdale Contractors, Bennco and Karlka Fencewright.

Gudai-Darri is a greenfield mine development, around 35 km northwest of the Yandicoogina mine in the East Pilbara mining region. The mine will initially be developed as a nominal 43 Mt/y high-grade, dry processing operation.

Alltype Engineering goes modular for Rio Koodaideri iron ore plant deliveries

WestStar Industrial Ltd’s engineering contractor business, Alltype Engineering, is to help build an iron ore mine plant at the Rio Tinto-owned Koodaideri project in the Pilbara of Western Australia, thanks to a contract award from Laing O’Rourke.

The Phase 1 Structural, Mechanical, and Piping package for the mine plant comes with a value of around A$6 million ($4.4 million) for fabrication works plus associated modularisation scopes, WestStar says.

The execution plan developed by Laing O’Rourke, the managing contractor, is based upon substantial preassembly and modularisation of the structural steel elements at Alltype’s Naval Base facility, in Western Australia (pictured). The contract win takes immediate effect with delivery and install dates up to January 2021, it said.

“The works to be performed leverage off the core competencies of the company with similar delivery strategies utilised for oil and gas, petrochemical and infrastructure projects in the past,” WestStar said.

Koodaideri is a greenfield mine development, around 35 km northwest of the Yandicoogina mine in the East Pilbara mining region. The mine will initially be developed as a nominal 43 Mt/y high-grade, dry processing operation. First production is expected in late 2021.

WestStar acquired Alltype Engineering last year in a deal that involved an upfront payment of around A$5.9 million, along with a deferred consideration subject to Alltype achieving its 2020 financial year targets.

Alltype Engineering Managing Director, Kelvin Andrijich, said: “Alltype Engineering undertook a significant strategic shift in direction in 2017, focusing on multi-discipline construction solutions, technology partnerships with OEMs and leveraging off the well-established industry exposure developed over 35 years of operation. This strategy continues to unfold with our established local fabrication capability and by building upon successive projects delivered of increasing scale and complexity with existing and new clients.

“The support of our new owner, WestStar Industrial, allows the group to execute larger contracts previously constrained by working capital, as well as start to expand the operational footprint to the east coast of Australia where there is further market opportunity for this offering.”

Scott Technology wins sample prep and analysis lab contract from Rio at Robe Valley

Scott Technology has been awarded a further multi-million dollar contract by Rio Tinto to provide and commission the equipment for a new sample preparation and analysis laboratory at the Robe Valley iron ore mine site in Western Australia.

This is the second significant iron ore sample laboratory project awarded to Scott Technology by Rio Tinto in 2020, building on the inaugural order for an automated lab at the Koodaideri project.

The automation and robotics solutions provider said this latest contract builds on the decades-long relationship between the two businesses and Scott’s expertise and experience in this area.

The Robe Valley project scope comprises equipment from Scott Technology’s Rocklabs business as well as third-party supply. Work has begun on the development and planning for the new laboratory, which is expected to commence operation in June 2021.

Rio’s majority-owned Robe Valley operation produces ore from mines at the Mesa A hub and Mesa J hub, with coarse ore from both processed to lump and fines in the process plant at Cape Lambert.

John Kippenberger, CEO of Scott Technology (pictured), said: “Scott has demonstrated success at many iron ore mine site laboratories in recent years, with our Rocklabs crushers and mills providing safe, reliable, productive operation for our clients. We are excited to be working with the Rio Tinto team on another important mining laboratory project.

“This comes on the back of the positive Rio Tinto Koodaideri project work, which is currently underway and also in Western Australia. As recently announced, building work and site mobilisation has commenced at Koodaideri, in line with the original timetable.

“This latest contract award further cements Scott’s evolution in the mining sector from a world leading supplier of sample preparation equipment, to a complete end-to-end automation and analysis solution provider.”

Kippenberger said the iron ore sector was continuing to experience positive interest and investment in automation given the underlying strength in demand for the steel raw material, which boded well for the company picking up more contracts.

“We see an increasing opportunity for our business, for more projects of the same scale with both existing and new customers as they seek increased safety and greater productivity,” he added.

The Robe Valley is around 140 km southwest of Karratha in the Pilbara region, with the Robe Valley deposits owned by the Robe JV, which is 53% owned by Rio Tinto, 33% by Mitsui Iron Ore Development and 14% by Nippon Steel Sumitomo Metals Corp.

The primary requirement of the Robe Valley Sustaining Project is to sustain production from the Robe Valley from the year 2020.

Scott Automation kicks off Koodaideri automated lab construction

Building work on the Koodaideri automated mine site laboratory in the Pilbara of Western Australia has commenced with site mobilisation now underway, according to Scott Automation.

The company, which was awarded a contract by Rio Tinto to design and build the laboratory back in February, said this important milestone was reached on time, despite COVID-19 restrictions.

“A number of Scott’s design and build activities for the Rio project have been moved to the company’s Australian operations to be closer to the customer,” it added.

The automation and robotics solutions provider’s contract involves the building construction and equipment supply for the robotic sample preparation and analysis laboratory, it said.

The project will be undertaken across multiple Scott manufacturing sites and is scheduled to be installed by mid-2021.

In April, Scott contracted Kerman Contracting for the civil and concrete works, as well as the structural, hydraulic, electrical/communication works and fire protection at the site. The supply, installation and commissioning of robotics equipment are all being undertaken by Scott.

Koodaideri, billed by Rio as an “intelligent mine”, will deliver a new production hub for Rio’s iron ore business in the Pilbara, incorporating a processing plant and infrastructure including a 166 km rail line connecting the mine to the existing network.

Construction on Koodaideri Phase 1 started in 2019 with first production expected in late 2021. Once complete, the mine will have an annual capacity of 43 Mt, underpinning production of the company’s flagship iron ore product, Pilbara Blend.

Primero Group lands contract addition at Rio Tinto’s Koodaideri project

Multi-disciplinary engineering and contracting firm, Primero Group, says it has been awarded a material contract extension to the existing Koodaideri Non-Process Infrastructure (NPI) contract awarded in late 2019 by Rio Tinto.

Under the extension, the company will construct the Koodaideri Airport Terminal and Infrastructure, with the contract valued at around A$20 million ($14 million). This will involve the construction delivery of the works to be completed in parallel with the existing contract programmed for completion in 2021.

The contract value of the entire NPI contract now stands at circa-A$150 million, compared with the A$115 million under the original award. The difference represents additional “options selections” that Rio confirmed and included for implementation at the project earlier this year.

Primero’s workforce on the project will peak at approximately 180 personnel and site construction work is well underway, the company noted.

Construction on Koodaideri Phase 1 started in 2019 with first production expected in late 2021. Once complete, the $2.6 billion mine will have an annual capacity of 43 Mt, underpinning production of the company’s flagship iron ore product, Pilbara Blend, Rio says.

With this recent NPI contract addition, Primero’s financial year 2021 contracted order book now stands at approximately A$220 million, the company said.

Primero Managing Director and CEO, Cameron Henry, said: “It is pleasing to be awarded further core NPI work from such a great project partner and Tier 1 client as Rio Tinto. We continue to deliver to plan across all major project works and are increasingly optimistic about the operating and growth outlook for the next year and beyond.”

Scott Technology signs up Kerman for Koodaideri automated lab build

Kerman Contracting is to build an automated iron ore sampling processing laboratory at Rio Tinto’s Koodaideri mine site, in the Pilbara of Western Australia.

The contract award from Scott Technology Ltd will see the company start construction on the lab in the June quarter of this year with estimated completion in February 2021.

The scope includes the civil and concrete works, as well as the structural, hydraulic, electrical/communication works and fire protection, Kerman said. The supply, installation and commissioning of robotics equipment will be undertaken by Scott.

Kerman is also working on Rio Tinto’s other major iron ore expansion project in the Pilbara, the Western Turner Syncline 2 (WTS2) iron ore project.

Kerman’s Managing Director, Chris Kerman, said: “We are very pleased to be awarded the design and construction of the Koodaideri laboratory building. Over the last nine months, Kerman and Scott have been working collaboratively on refining the scope and price. We are now looking forward to getting the project underway and establishing a long lasting business relationship with Scott.”

In February, Scott Technology said it had been awarded a significant contract by Rio Tinto to design and build the automated mine site laboratory, adding that the agreement involved the building construction and equipment supply for the robotic sample preparation and analysis laboratory (graphic above).

Koodaideri, billed by Rio as an “intelligent mine”, will deliver a new production hub for Rio’s iron ore business in the Pilbara, incorporating a processing plant and infrastructure including a 166 km rail line connecting the mine to the existing network.

Construction on Koodaideri Phase 1 started in 2019 with first production expected in late 2021. Once complete, the mine will have an annual capacity of 43 Mt, underpinning production of the company’s flagship iron ore product, Pilbara Blend.

Rio increases scope of Primero work at Koodaideri, Robe Valley

Primero says it has been awarded variation extensions to contracts it already has in place with Rio Tinto at the in-development Koodaideri iron ore project and the Robe Valley iron ore operations, both in the Pilbara of Western Australia.

The multi-disciplinary engineering and contracting firm said the extensions have a combined value of around A$20 million ($12.3 million).

The variations awarded under the Mesa K (Robe Valley) contract reflect additional civil works at the Mesa J PP2 (process plant 2) wet processing facility, currently being developed as part of Rio Tinto’s Robe Valley sustaining projects, Primero said.

Back in October 2018, Rio, together with joint venture partners Mitsui and Nippon Steel & Sumitomo Metal, approved an investment of $1.55 billion to sustain production capacity at two projects forming part of the Robe River joint venture, which also includes Robe Valley.

The additions to the Koodaideri contract, meanwhile, reflect additional “options selections” that have now been confirmed and included for implementation, according to Primero.

Construction on Koodaideri Phase 1 started in 2019 with first production expected in late 2021. Once complete, the $2.6 billion mine will have an annual capacity of 43 Mt, underpinning production of the company’s flagship iron ore product, Pilbara Blend.

Primero Group secured a A$115 million contract with Rio Tinto’s iron ore division to design, fabricate, supply, deliver, construct, install, test and commission the Mine Infrastructure Area and associated facilities at Koodaideri back in late 2019.

The Mesa J works (under the Mesa K contract) are expected to be completed in 2020, Primero said. The additional Koodaideri works are planned to be completed in-line with the original contracted time frame of mid 2021.

Scott Technology to automate Koodaideri sampling and analysis process

Scott Technology says it has been awarded a significant contract by Rio Tinto to design and build the automated mine site laboratory for the Koodaideri iron ore project, in the Pilbara region of Western Australia.

The automation and robotics solutions provider’s contract involves the building construction and equipment supply for the robotic sample preparation and analysis laboratory (graphic above), it said.

The project will be undertaken across multiple Scott manufacturing sites and is scheduled to be installed by mid-2021.

Scott Technology said: “The project leverages recent advancements in automation and digitisation, helping to deliver a safer and more productive mining operation. Once completed and in production in 2021, the Koodaideri laboratory will be the safest, most productive, highest quality iron ore facility in the world.”

Koodaideri, billed by Rio as an “intelligent mine”, will deliver a new production hub for Rio’s iron ore business in the Pilbara, incorporating a processing plant and infrastructure including a 166 km rail line connecting the mine to the existing network.

Construction on Koodaideri Phase 1 started in 2019 with first production expected in late 2021. Once complete, the mine will have an annual capacity of 43 Mt, underpinning production of the company’s flagship iron ore product, Pilbara Blend.

The contract award highlights Scott’s evolution in the mining sector from a leading supplier of sample preparation equipment, to a complete end-to-end automation and analysis solution provider, it said.

“The company’s commitment to R&D is helping to drive efficiency and output of some of the world’s largest mines, and Scott is currently working with multiple global mining companies and commercial laboratories on large scale automation projects, particularly in the Asia Pacific region,” it said. “In recent years, the company has implemented solutions in the mining sector such as robotic refuel, robotic idler change, sampling systems, and automated sample preparation facilities.”

Scott CEO, John Kippenberger, said: “Demand for industrial automation continues to intensify, driven by a continuing focus on health and safety, and to improve productivity, quality and profitability.

“As a global leader in automation and robotic solutions, Scott is well positioned to take advantage of this growing demand and we are progressing a number of opportunities across a range of sectors. With these latest developments in our technology platform, we see the mining sector continuing to play an increasingly important role as a contributor to Scott’s future growth.

“We are looking forward to partnering with Rio Tinto on this innovative project that once complete will set the new benchmark for safety and operational excellence in Iron Ore sample preparation and analysis.”

Primero Group to take on EPC contract at Rio’s Koodaideri iron ore mine

Primero Group has secured a A$115 million ($79 million) contract with Rio Tinto’s iron ore division that will see it design, fabricate, supply, deliver, construct, install, test and commission the Mine Infrastructure Area and associated facilities at the Koodaideri iron ore project in the Pilbara of Western Australia.

The scope includes the complete engineering, procurement and construction (EPC) contract of the facilities for this project, which will commence immediately and is scheduled to be completed in mid-2021.

Primero says it expects to employ a workforce of over 150 personnel at its peak.

Koodaideri, billed by Rio as an “intelligent mine”, will deliver a new production hub for Rio’s iron ore business in the Pilbara, incorporating a processing plant and infrastructure including a 166 km rail line connecting the mine to the existing network.

Construction on Koodaideri Phase 1 started this year with first production expected in late 2021. Once complete, the mine will have an annual capacity of 43 Mt, underpinning production of the company’s flagship iron ore product, Pilbara Blend.

In addition to mine infrastructure and the accommodation camp, an airport and mine support facilities will be built. Throughout the construction period, Rio expects to employ over 2,000 people with 600 permanent roles created once the mine is operational.

In addition to the Koodaideri work, Primero said it had been awarded Phase 2 of the proposed processing upgrade, on an engineering, procurement and construction management (EPCM) basis, for Northern Star Resources’ Pogo gold mine, in Alaska, USA.

The works will be conducted predominantly from Primero’s Americas Montreal (Canada) office with works progressively executed this winter to ensure construction windows are met in the summer period, it said.

The upgrade works will increase throughput of the current processing facility from 1 Mt/y to 1.3 Mt/y by January 2021, with the potential to move to a Phase 3 (1.5 Mt/y) over the coming years.

Primero said: “Works are set to progress over the next 12 months including detailed design and equipment procurement with the planning for on-site works commencing over the winter period to be executed in the warmer months, post winter.”

The award of the project is the first major contract with Northern Star Resources, Primero added.

Northern Star acquired Pogo, the company’s first mine outside of Australia, from Sumitomo Metal Mining late last year for $260 million.