Tag Archives: Marathon Gold

Marathon Gold taps Metso Outotec for Valentine processing plant equipment

Marathon Gold has awarded Metso Outotec with orders for key processing equipment for the Valentine gold project in Newfoundland, Canada.

The combined order value of approximately €15 million ($14.9 million) has been booked in Minerals’ Sepetmber-quarter orders received.

“We chose Metso Outotec equipment because of their brand reputation, technology-oriented equipment, commitment to safety and environment, and their service footprint in Atlantic Canada,” Paolo Toscano, Vice President, Projects, Marathon Gold Corporation, said.

Metso Outotec’s scope of delivery consists of a VF Series™ grizzly feeder, a Nordberg® jaw crusher, Planet Positive Premier® SAG and ball mills, a Mill Reline Machine (MRM), vibrating screens and a high-rate tailings thickener with Reactorwell™ feed system.

Andy Lingenfelter, Vice President, Minerals Sales in North and Central America, added: “We are excited to work on the Valentine gold project with Marathon. We were able to align with the project’s key value drivers at an early stage and provide to-the-point technical support.

“Marathon has selected leading-class equipment for their gold production process, and they will also be able to benefit from our broad-based service organisation.”

An April 2021 feasibility study outlined an open-pit mining and conventional milling operation at Valentine with a 2.5 Mt/y processing rate over a 13-year mine life with a 31.5% after-tax internal rate of return and initial capital costs of C$305 million ($228 million). The project has estimated proven reserves of 1.4 Moz (29.68 Mt at 1.46 g/t) and probable reserves of 650,000 oz (17.38 Mt at 1.17 g/t).

Marathon Gold sets sights on first production finish line at Valentine

Marathon Gold has laid out plans for a new open-pit mine in Newfoundland that, it says, could become Atlantic Canada’s largest gold producer.

The prefeasibility study on the Valentine gold project in central Newfoundland outlined a plan for a 12-year operation producing circa-145,000 oz/y of gold at life of mine all-in sustaining costs of $739/oz. This is based on a proven and probable reserves base of 1.87 Moz (41.05 Mt at 1.41 g/t Au).

The initial capital cost to build a 2.5 Mt/y gravity-leaching operation was pegged at $205 million, with Marathon Gold saying it planned on funding an expansion – based on gravity-flotation-leaching – to 4 Mt/y (from year four onwards) from internal cash flow. The post-tax net present value (5% discount) was estimated at $354 million based on a $1,350/oz gold price.

The PFS, completed by Ausenco Engineering Canada as Lead Consultant, contemplates open-pit mining from the Marathon and Leprechaun deposits only.

Each deposit will be developed in three phases, with the Marathon pit achieving a maximum dimension of 1,250 m x 700 m by 294 m deep, and the Leprechaun pit achieving 1,050 m x 650 m by 306 m deep, Marathon said. Life of mine strip ratios will be 6.7 at Marathon, 9.1 at Leprechaun, and 7.6 overall, according to the company.

Benches will be mined by conventional drill & blast/load & haul methods on 6 m bench heights with 8 m wide berms every third bench. Dual-lane haul road allowances will support a diesel-powered mining fleet that will include 32 90 t payload trucks operating between the two open pits, Marathon said.

The study contemplates an initial milling strategy based on grinding to 75 µm followed by gravity concentration and cyanidation of gravity concentrates and tails. Grinding will be by way of a SAG and a ball mill.

The mill will be expanded in year four by coarsening the initial grind to 150 µm and adding flotation and regrinding of the flotation concentrates, followed by cyanidation. No additional grinding equipment will be required for this expansion phase, the company said. Overall gold recovery is estimated at 93% at an average grade of 1.41 g/t Au (85% at cutoff grade and capped at 97%).

The tailings management facility (TMF) will receive thickened tailings from the mill between years one and nine, with the mined-out Leprechaun open pit scheduled to receive tailings starting in year 10, the company said. Effluent and contact water from the TMF, waste rock piles and open pits will be collected and, if necessary, treated prior to release, Marathon explained.

Matt Manson, President & CEO of Marathon, said: “We have taken the approach of identifying the optimum starting point for mining at Valentine, emphasising highest rate of return and lowest risk, while recognising that the large resource inventory and extensive exploration potential along strike and at depth offers plenty of opportunity for mine life extension.

“The Valentine project is expected to be Atlantic Canada’s largest gold producer. Notwithstanding the current COVID-19 challenges, it represents the future of responsible resource development in central Newfoundland.

“With a strong treasury in hand, our attention now turns to the submission of our Environmental Impact Statement, expected later this year, and the commencement of feasibility-level studies.”

The PFS contemplated completion of a feasibility study in the first half of 2021, completion of the environmental assessment and Ministerial Approval by mid-2021, and the commencement of site-specific permitting thereafter. Ground-breaking for site construction is scheduled for January 1, 2022, with a total 18-month construction period and first gold production by mid-2023.

These timeframes have been estimated without consideration of potential impacts from the ongoing COVID-19 challenges, such as disruption to supply chains, labour markets, work practices and permitting, among other factors, the company cautioned.

Ausenco to run with Marathon at Valentine gold project

Marathon Gold has appointed Ausenco Engineering Canada as the lead consultant for the prefeasibility study (PFS) on the Valentine gold project in Newfoundland and Labrador, Canada.

As lead consultant in the PFS, Ausenco will undertake a tradeoff study designed to assess the optimum scope, value, and execution strategy for the project, and will incorporate an updated production schedule, facilities design, operating and capital cost estimates, and process design based on ongoing metallurgical studies.

Ausenco will be assisted by Moose Mountain Technical Services in the areas of mineral reserve estimation and mine design. The PFS will also incorporate the results of work currently being conducted at the Valentine project by Terrane Geoscience Inc in the area of geotechnical drilling and pit slope design, by Gemtec for hydrogeology, by Stantec for environmental assessment, and John T Boyd Company for an updated mineral resource estimate.

An October 2018 preliminary economic assessment on Marathon showed the project to be amenable to open pit mining and conventional milling over a 12-year mine life. Average annual production was pegged at 225,100 oz at an all-in sustaining cost of $666/oz. Total mineral resources currently comprise 16.6 Mt of material at a grade of 2.18 g/t containing 1.17 Moz gold in the measured category, 28.5 Mt at 1.66 g/t containing 1.52 Moz of gold in the indicated category, and 26.9 Mt at 1.77 g/t containing 1.53 Moz of gold in the inferred category.

Matt Manson, Marathon President and CEO, said of the news: “Ausenco’s Canadian based engineering team has a broad range of mine development expertise well suited to the Valentine gold project. In particular, they bring the most recent direct experience in the development of a large open-pit gold project in the Maritimes as the engineering, procurement and construction contractor at the successful Moose River gold mine (pictured) developed by Atlantic Gold Corp (now St Barbara Ltd).

“They will join an existing team of specialised sub-contractors already working with Marathon’s owner’s team to develop the best overall project configuration for subsequent feasibility study, permitting and financing.”

The PFS is expected to take around six months to complete, with results expected early in the June quarter of 2020.