Tag Archives: polyhalite

STRABAG wins MTS contract for Sirius UK polyhalite project

Sirius Minerals has varied its existing mineral transport system (MTS) tunnelling contract with STRABAG AG to include the engineering, procurement and construction of the fit-out of the system at its polyhalite project in Yorkshire, England.

The MTS fit-out scope includes the fit-out of the MTS conveyor, the maintenance railway, electrical and communications infrastructure, and all other services in the tunnel essential to the operation of the MTS.

Sirius said the price of the MTS fit-out was in line with the company’s capital re-estimate announced on September 6.

The MTS will carry the company’s mined polyhalite from 360 m underground at the Woodsmith mine site to the materials handling facility at Wilton, Teesside, on a 37 km underground conveyor system. The tunnel will be constructed by three tunnel boring machines and the conveyor system in the MTS will be designed to handle 20 Mt/y of throughput. It will also contain maintenance rail and services, including a 66 kV power feeder from Wilton International industrial complex.

More than 50% of the MTS fit-out price is on a fixed rate or lump-sum basis, with the remainder based upon estimated prices to be converted into fixed prices prior to completion of stage two financing. The proposed schedule for the MTS fit-out is in line with the company’s overall project schedule, Sirius said.

This is a significant step forward for the project, with Sirius saying it has now completed its procurement for the major construction packages related to the stage two senior debt financing process.

Chris Fraser, Managing Director and CEO of Sirius, said the company’s efforts were now focused on the successful execution of its financing plan to fully finance the construction of its polyhalite project.

As previously announced, the company expects the capital funding requirement of the project to be $3.4-$3.6 billion (previously $3bn), with a $3 billion senior debt financing being the appropriate level of debt.

Given the timing of completion of the final procurement contracts, final lender commitment letters are expected to be received in December and January. The company is targeting financial close of stage two financing in the March quarter.

Sirius awards more contracts for North Yorkshire polyhalite project as capital costs rise

Construction firm STRABAG and engineering group Jacobs have become the latest recipients of contracts for the Sirius Minerals’ owned North Yorkshire polyhalite project in the northeast of England.

STRABAG, which had already been awarded a design and build contract for the first drive of the mineral transport system (MTS) tunnel between Wilton and Lockwood Beck, near Teesside, has been contracted to construct drives two and three. Jacobs, meanwhile, has been given an engineer, procurement and construction contract for the materials handling facility (MHF) at Wilton.

These announcements came as Sirius updated its capital cost estimate for stage two of the project, which is expected to see the mine expand from 10 Mt/y of polyhalite to 20 Mt/y.

This has seen the stage two capital requirement go from $3 billion in November 2016 to $3.6 billion today.

The majority of the cost increase is associated with the MTS (pictured), which Sirius said reflected its own increased understanding of the “geotechnical characteristics of the strata within which the MTS will be excavated”.

This followed further ground investigation and seismic work that led to a refinement of the parameters set out in the geotechnical baseline report upon which the tunnelling contract was determined.

Chris Fraser, Managing Director and CEO of Sirius Minerals, said the cost increase reflected “an optimisation of the MTS tunnel design and a significantly improved risk allocation for Sirius to support the senior debt financing”.

The MTS cost increase is driven by a combination of the following factors:

  • Optimisation of the tunnel design including an increase in the planned internal diameter of the tunnel from 4.3 m to 4.9 m and an increase in lining thickness from 250 mm to 350 mm;
  • A decrease in advance rates as compared from 25 m/d to 17 m/d, and;
  • A commercial risk allocation which transfers construction and delivery risk to STRABAG.

The MTS includes a 37 km tunnel for a conveyor system to transport the polyhalite from the mine near Whitby to Wilton on Teesside for processing. STRABAG will construct the tunnel by using a Tunnel Boring Machine and the company expects to use a high-capacity conveyor belt system capable of transporting 20 Mt/y of polyhalite at 7.5 m/s.

The MHF will be constructed and managed by Jacobs’ UK subsidiary, with the EPC contract agreed on a target price basis, with financial incentives for completing the scope of work under budget, and financial penalties should completion be late or the cost be above the target price.

The plant has been scoped to include 7 Mt/y of granulated and 3 Mt/y of coarse product in its first phase of development but with a footprint for up to 20 Mt/y of granulated product.

Sirius said its procurement process for the project is nearing completion for the major packages and it is in the final stage of negotiations for the outstanding scopes of work.

Included in this is the MTS fit out, which includes the supply and installation of the MTS conveyor and the associated power supply, and the port facilities which includes construction of the outload circuit, wharf and product storage facility.

Sirius has identified STRABAG as its preferred contractor for the MTS fit out and is in advanced negotiations for provision of port facilities.

As the upfront capital for stage two of the project has increased, Sirius has developed a construction programme that defers the initial costs associated with the port facilities and has amended the scope of work to include temporary truck and train transportation of product from the storage facility at Wilton to the port.

“This enables the construction of the overland conveyor to be deferred until such time as it can be funded through operating cash flows, currently assumed to be 2025,” Sirius said.

While capital costs may have increased in this latest update, the company’s operating cost estimates have actually dropped from $32.6/t in stage one (10 Mt/y) to $29.4/t, and $27.6/t in stage two (20 Mt/y) to $27.4/t.

Sirius has already raised $1.2 billion for mine construction at the project, which is expected to produce first polyhalite in 2021, reach 10 Mt/y production in 2024, expand to 13 Mt/y in 2026 and grow further to 20 Mt/y in 2029.