Capstone prepares Cozamin for introduction of paste backfill, dry-stack tailings

An updated Technical Report on Capstone Mining’s Cozamin copper-silver mine in Zacatecas, Mexico, has shown the potential for a mine life extension to 2031, and a plan for dry-stack tailings and underground paste backfill. At the same time, the company says it is studying the use of “innovative mining techniques and enhanced pillar recovery” to make the most of existing reserves and resources.

The updated life of mine plan released outlined average annual copper production of 51.2 MIb (23,224 t) of copper and 1.6 Moz of silver production over 10 years at average C1 costs, including the 50% silver stream, of $1.02/Ib of payable copper. From 2021 to 2027, average annual production is slated to be 58.8 MIb of copper and 1.7 Moz of silver.

The company said a planned ramp-up to 3,780 t/d, or 1.38 Mt/y, by the end of March quarter is on track, with a new section of ramp to open the one-way traffic circuit to debottleneck the mine (pictured) completed in early December 2020, ahead of schedule.

Reserves increased by 39% and now stand at 14.1 Mt, relative to April 30, 2020. Contained copper and silver increased by 37% and 49%, respectively, with around half of this increase due to recovery of high-grade pillars using paste backfill, Capstone said.

The miner said “tailings management transformation” activities were progressing on schedule at site, including feasibility-level design and studies in support of permitting a filtered (dry stack) tailings storage facility.

“This conversion from a slurry tailings impoundment aligns with industry leading socio-environmental best practice for tailings management,” the company said.

Meanwhile, a prefeasibility study (PFS) for an underground paste backfill system was completed in December.

The study indicates a paste backfill system will allow ore extraction containing over 100 MIb of copper and 3.1 Moz of silver between 2023 and 2031, which would have otherwise been left as unmined pillars. The PFS design has a capital cost estimate ranging from $41-$45 million and an increase in operating costs of around $7.50/t of ore mined. Capstone says its management has approved the paste backfill project and work has commenced on procurement of long lead items.

The proposed paste backfill system includes a tailings filter plant, a paste mixing plant, twin boreholes to deliver paste underground and an underground distribution system. The system is expected to be commissioned starting in the December quarter of 2022, with ramp-up completed in the March quarter of 2023.

PFS design of these facilities was completed by Paterson & Cooke in December 2020 and a feasibility study is underway with completion expected in April 2021. Mine planning was completed by Cozamin, with design support provided by a geotechnical consultant, and paste backfill operational guidance provided by AMC Consultants.

Within the latest release, Capstone also flagged the initiation of its “Impact23 Growth” project, which has identified areas of exploration excellence, innovative mining techniques and enhanced pillar recovery at Cozamin.

“By 2023, the goal is to further extend mine life, increase environmental and safety standards, and improve operational efficiencies at Cozamin, utilising mineral resources already discovered in addition to testing new targets,” the company explained.

Included among the options are the innovative mining techniques for resource to reserve conversion flagged at the start of this story.

Capstone says a study will be initiated this year to assess alternative mining techniques with the objective of lowering costs and dilution to convert resources to reserves from the indicated resource base. The current mining methods are longitudinal longhole open stoping and AVOCA, with possible alternatives to be studied including cut-and-fill, drift-and-fill and longhole open stoping with ore sorting technology.

Brad Mercer, Capstone’s SVP and Chief Operating Officer, said: “The life of mine plan announced today maximises extraction of the orebody’s high-grade core by deferring stoping in this area until the paste backfill plant is in operation in 2023. Projected production averages nearly 60 MIb of copper per year for seven years at first quartile costs.

“The Impact23 Growth project that we are kickstarting today is aiming to demonstrate in a 2023 technical report how Cozamin can sustain these levels of performance well into the 2030s.”

Darren Pylot, Capstone’s President and CEO, added: “After 14 years in operation, the best years of Cozamin are ahead. The mine is world class with sustainable low costs and leading safety and environmental performance entrenched throughout the organisation. The growth initiatives are supported by an entrepreneurial fabric at Capstone, as we embrace innovation and technology to create high impact value for our shareholders.”

Orla Mining on course for first gold in 2021 at Camino Rojo Oxide project

The publication of the updated feasibility study on Orla Mining’s Camino Rojo Oxide Gold asset in Zacatecas, Mexico, has come with a 54% increase in contained gold reserves and a 3.5-year extension to the mine life of the in-construction project.

The new reserve estimate at Camino Rojo includes a proven and probable total of 67.4 Mt at 0.73 g/t Au and 14.5 g/t Ag, for total mineral reserves of 1.59 Moz of gold and 31.5 Moz of silver.

The updated study outlined open-pit mining of 67.4 Mt of oxide and transitional ore at a rate of 18,000 t/d. Ore from the pit will be crushed to 80% passing 28 mm, conveyor stacked onto a heap leach pad and leached using a low concentration sodium cyanide solution. Pregnant solution from the heap leach will be processed in a Merrill-Crowe recovery plant where gold and silver will be precipitated and doré will be produced. The site’s proximity to infrastructure, low stripping ratio, compact footprint and flat pad location all contribute to the project’s simplicity and low estimated all-in-sustaining costs of $543/oz of gold, the company said.

An after-tax net present value (5% discount) of $452 million was calculated by the study team led by Kappes Cassiday and Associates and supported by Independent Mining Consultants, Resource Geosciences Inc, John Ward Groundwater Consultant, Barranca Group, Piteau Associates Engineering and HydroGeoLogica Inc.

The main notable physical changes from the 2019 feasibility study are an increase in the size of the open pit, heap leach pad, and mine waste dump because of a layback agreement with the adjacent Fresnillo mine, all of which were anticipated in the initial design. While all material to be mined on the Fresnillo concession has been classified as waste in the latest study, Orla sees opportunities to further expand the reserve and resource base following further work on material in this area.

Jason Simpson, President and Chief Executive Officer of Orla, said: “The updated feasibility study for the Camino Rojo Oxide project demonstrates an increase in recovered gold, mine life, and cash flows.

“An already excellent project has been improved due to the hard work of the entire Orla team and I thank them for their efforts. We are pleased to announce this important enhancement and we will continue to optimise this asset as we move through construction and into production.”

Detailed engineering of the project described in the 2019 feasibility study is over 90% complete and procurement is 85% complete, with the start of earthworks announced on November 26, 2020. Since that time, 230 ha have been cleared for construction activities with over 20,000 cu.m of topsoil being removed and stockpiled. Equipment deliveries to site commenced in December, with a total of $78 million of the total project capital committed through purchase orders and contracts.

Orla says the mining contract is being finalised and expected to be in place early in the March quarter, with first gold production planned for late 2021.