Tag Archives: construction

GR Engineering cements Yangibana rare earth project EPC contract

GR Engineering Services has been awarded an engineering, procurement and construction (EPC) contract with Yangibana Pty Ltd, a wholly owned subsidiary of Hastings Technology Metals Limited, for a beneficiation plant and associated infrastructure for the Yangibana rare earths project in Western Australia.

As previously announced on May 3, 2023, GR Engineering had entered into a binding term sheet with Yangibana Pty Ltd for these works.

The contract sum, including the provisional sum, is A$210 million ($138 million) as previously disclosed. This is made up of a fixed price component of A$180 million for the beneficiation plant and a provisional component of A$30 million mainly for the plant and tailings storage facility earthwork.

GR Engineering has commenced early works up to an agreed capped amount. The EPC contract is conditional on GR Engineering being issued with a commencement notice, which is dependent on Hastings finalising funding for the project as well as a number of other pre-conditions standard for an EPC contract.

Construction is planned to be complete in the March quarter of 2025 with first concentrate on truck in the June quarter of 2025

Under the A$210 million contract, GRES will design and construct the Yangibana beneficiation plant and all associated infrastructure, including engineering, manufacture, supply, installation, dry and wet commissioning, and testing of the facility over a period of less than 18 months. When completed, the plant will have a feed capacity of 1. 1 Mt/y and a rare earth concentrate output capacity of 37,000 t/y, Hastings says.

NRW’s Primero Group awarded major EPC contract for KCGM Growth Project

NRW Holdings says its wholly owned subsidiary Primero Group Limited has entered into an EPC contract with Northern Star Resources Limited for its KCGM Growth Project in Kalgoorlie, Western Australia.

The execution of the engineering, procurement and construction contract follows an extensive program of work to define the scope, cost and schedule, according to NRW. Under the agreement, Primero will be responsible for the design, procurement, construction and commissioning of the process plant facilities, with the commercial model for delivery an “Incentivised Target Cost”.

The EPC contract has an approximate value of A$973 million ($647 million). The contract is scheduled for completion by the September quarter of 2026.

Last month, Northern Star announced the final investment decision on the KCGM Mill Expansion project, agreeing to invest A$1.5 billion to boost the mill’s capacity to 27 Mt/y, from 13 Mt/y. Included within this is 20 MW grinding mills – the highest powered, gear-driven mills in the world – and the first gear-driven 28 ft (8.5 m) diameter ball mill, according to FLSmidth.

Primero participated in a competitive early contractor involvement (ECI) program from January 2022 and has worked with the Northern Star project team to develop a technically-superior design that will bring operating benefits to the Fimiston processing plant, it says. Following the ECI program, Primero was engaged to undertake further value engineering and scope development.

Primero’s Managing Director, Michael Gollschewski, said: “The execution of the KCGM Growth Project is the culmination of an 18-month journey with Northern Star. The work conducted to date to develop the capital cost, design, execution strategy and schedule for the project, has been one of the most comprehensive and rigorous ECI programs we have participated in. The effort of the combined teams to define this key project has provided a solid foundation for a safe, efficient and successful delivery.”

NRW’s Managing Director, Jules Pemberton, said: “This EPC contract reinforces Primero’s reputation as a leading provider of world class engineering and construction services. This
project showcases Primero’s full range of in-house capability. I look forward to developing a long-term relationship with one of the industry’s leading gold producers.”

Orefields Raise Boring, Cementation Canada to collaborate on mining project delivery in Scandinavia

Sweden-based Orefields Raise Boring AB has established a Memorandum of Understanding (MoU) with Cementation Canada Inc that could see the two companies collaborate on projects in Scandinavia going forward.

Cementation, a global mine development contractor, complements Orefield’s’ mining services, which include pilot drilling, raiseboring, down-reaming, horizontal raiseboring and casting/grouting, it says, offering capability and experience to engineer and sink shafts, drive decline ramps, lateral development, production mining and mine construction to access and mine orebodies.

Additionally, the team’s offerings include full in-house engineering and design-supply services for crushing/screening and conveying systems that condition and deliver run-of-mine ore to the processing facility.

In addition to introducing expanded capabilities beneficial to the broader Scandinavian Region, the Orefields + Cementation Tier 1 Team bring innovative delivery model alternatives that reduce risk for the mine owner when compared with the conventional engineering procuement and construction (EPC) or design-bid-build approaches, they say.

For example, creative risk-reducing alternatives include:

  • Design-build-operate/maintain (DBOM)
    • DBOM + system ownership
    • Following an agreed period of operation, option to transfer ownership
    • Owner’s mine build & mining partner

Cementation explained: “Over the life of the facility, operations and maintenance expenses often far exceed the initial cost to design and build systems. Consequently, the design and construction of the system significantly impacts operational reliability and the resultant costs that accumulate over the years. Our DBOM approach, being performed by a single accountable venture, reduces risk inherent in spreading work packages between different organisations (as with EPC or design-bid-build approaches, for example). Simply put, the principle behind the DBOM delivery model is that we ‘pack our own parachute’, so we make sure it is done right from the beginning through to deployment.”

With this partnership specifically being established in Sweden for the benefit and added value to the Scandinavian Region, technical and professional labour resources, as well as the supply of materials, equipment and fabrication/construction, will be procured in the local regions where possible. Depending on the availability of qualified Scandinavian-based resources, secondary preference will be given to other European Region countries.

GR Engineering wins Mt Ida EPC contract from Aurenne Alt Resources

GR Engineering Services says it has executed an engineering, procurement and construction (EPC) contract with Aurenne Alt Resources Pty Ltd in relation to the Mt Ida gold project in Western Australia.

Mt Ida, which Aurenne inherited with the acquisition of Alt Resources last year, is in the eastern goldfields of the state.

GR Engineering said the contract sum is approximately A$73 million ($54 million) and work is expected to start immediately.

Geoff Jones, Managing Director of GR Engineering, said: “GR Engineering is pleased to have been awarded the EPC contract by Aurenne and we look forward to working collaboratively with the Aurenne team. This project further reinforces GR Engineering’s reputation as the leading gold EPC contractor in Australia.”

Alt Resources previously outlined the need for a 750,000 t/y processing facility at Mt Ida in a 2020 feasibility study prior to being acquired by Aurenne.

GR Engineering awarded with Abra EPC contract

GR Engineering Services has been awarded a conditional engineering, procurement and construction (EPC) contract to deliver a 1.2 Mt/y lead sulphide flotation process plant and ancillary infrastructure for Galena Mining’s Abra Base Metals project in Western Australia.

The award, worth some A$74 million ($50 million), follows work carried out by the ASX-listed engineering company on the feasibility study and at the preliminary design stage of Abra.

The work will be undertaken on a guaranteed maximum price basis, according to GR Engineering, which confirmed that the contract remained subject to GR Engineering being issued with a full notice to proceed. This is dependent on Abra Mining Pty, Galena’s operating subsidiary, achieving financial close on its proposed project financing facilities. Galena, which owns 86.16% of the project through Abra, has said it will require A$170 million of pre-development capex to get the mine up and running.

GR Engineering has already commenced early engineering works up to an agreed capped amount, it said.

Geoff Jones, Managing Director of GR Engineering, said: “We are pleased to have been awarded the contract for the delivery of the Abra Base Metals project, which has followed GR Engineering’s involvement to date in the project’s feasibility study and preliminary design work.”

Galena completed a definitive feasibility study on Abra last year for development of a mine and processing facility with a 16-year life producing a high-value, high-grade lead-silver concentrate containing around 95,000 t/y of lead and 805,000 oz/y of silver after ramp-up.

Earlier this month, the construction of the Abra box cut commenced (pictured).