Tag Archives: Jules Pemberton

Pilgangoora-PilbaraMinerals

Primero to work on next phase of Pilgangoora P680 lithium expansion project

NRW Holdings Limited’s wholly owned subsidiary, Primero Group Limited, has been awarded a contract for Structural, Mechanical, Piping, Electrical and Instrumentation Construction by Pilgangoora Operations Pty Ltd (POPL), a wholly owned subsidiary of Pilbara Minerals Limited, for the next phase of the Pilgangoora P680 Expansion project, 120km south of Port Hedland, Western Australia.

The award follows a formal Early Contractor Involvement (ECI) phase to determine construction methodology, cost and schedule.

Under the contract, Primero is responsible for the construction of the crushing and ore sorting facilities. Primero will also assist with providing commissioning, integration and shutdown support. The contract at award has an approximate value of A$64 million ($40.7 million), with the contract scheduled for completion in the September quarter of 2024 with the works commencing immediately.

Primero’s Managing Director, Michael Gollschewski, said: “It is pleasing for Primero to be awarded this contract following the combined efforts of Primero and POPL teams in the successful delivery of the first stage of the P680 Expansion. We look forward to building on what is already a strong partnership with the POPL team.”

NRW’s Managing Director, Jules Pemberton, added: “This award continues to build on the long association between Pilbara Minerals and Primero that began with the design and construction of the original Pilgan Plant and continues with the delivery of the P680 Expansion Project. We look forward to the successful completion of these works.”

The P680 Expansion project could see Pilbara Minerals step-up its production run-rate at the operation to a total of circa-680,000 t/y of spodumene concentrate across the combined Pilgangoora operation.

NRW’s Primero Group awarded major EPC contract for KCGM Growth Project

NRW Holdings says its wholly owned subsidiary Primero Group Limited has entered into an EPC contract with Northern Star Resources Limited for its KCGM Growth Project in Kalgoorlie, Western Australia.

The execution of the engineering, procurement and construction contract follows an extensive program of work to define the scope, cost and schedule, according to NRW. Under the agreement, Primero will be responsible for the design, procurement, construction and commissioning of the process plant facilities, with the commercial model for delivery an “Incentivised Target Cost”.

The EPC contract has an approximate value of A$973 million ($647 million). The contract is scheduled for completion by the September quarter of 2026.

Last month, Northern Star announced the final investment decision on the KCGM Mill Expansion project, agreeing to invest A$1.5 billion to boost the mill’s capacity to 27 Mt/y, from 13 Mt/y. Included within this is 20 MW grinding mills – the highest powered, gear-driven mills in the world – and the first gear-driven 28 ft (8.5 m) diameter ball mill, according to FLSmidth.

Primero participated in a competitive early contractor involvement (ECI) program from January 2022 and has worked with the Northern Star project team to develop a technically-superior design that will bring operating benefits to the Fimiston processing plant, it says. Following the ECI program, Primero was engaged to undertake further value engineering and scope development.

Primero’s Managing Director, Michael Gollschewski, said: “The execution of the KCGM Growth Project is the culmination of an 18-month journey with Northern Star. The work conducted to date to develop the capital cost, design, execution strategy and schedule for the project, has been one of the most comprehensive and rigorous ECI programs we have participated in. The effort of the combined teams to define this key project has provided a solid foundation for a safe, efficient and successful delivery.”

NRW’s Managing Director, Jules Pemberton, said: “This EPC contract reinforces Primero’s reputation as a leading provider of world class engineering and construction services. This
project showcases Primero’s full range of in-house capability. I look forward to developing a long-term relationship with one of the industry’s leading gold producers.”

NRW Holdings wins contract mining gig at Allkem’s Mt Cattlin open-pit lithium mine

NRW Holdings Limited says it has been issued with a Letter of Intent from Allkem Limited in respect to the contract for mining services works at the Mt Cattlin open-pit lithium mine in Western Australia.

Formal award of the contract is subject to finalising outstanding terms, but the anticipated value of the contract is circa-A$332 million ($220 million) over a 36-month duration and the project will be supported by a workforce of approximately 140 people, mostly sourced from the surrounding area.

The works to be performed under the contract include load & haul, drill & blast and material rehandling. NRW will use an existing fleet comprising 200-250-t-class excavators and 150-t-class trucks together with ancillary plant. Mobilisation is currently underway preparing for commencement on site in August.

The Mt Cattlin operation produced circa-194,000 t/y of spodumene concentrate grading up to 6% Li20 in the 2022 financial year to June 30, 2022, according to Allkem.

NRW Chief Executive Officer, Jules Pemberton, said: “I am delighted to announce that NRW has been selected by Allkem as its preferred contractor for the mining services contract. NRW is a world leading provider of services across all aspects of the Lithium sector and we look forward to a long and successful partnership with Allkem.”

Primero to deliver non-process infrastructure for Rio Tinto’s Western Range site

NRW Holdings says its wholly owned subsidiary, Primero Group Limited, has been awarded a contract by Rio Tinto for work at the Western Range mine site, within the Pilbara Region of Western Australia.

Under the contract, Primero will be responsible for the design, supply, construction and commissioning of the non-process infrastructure facilities on site. This includes the refuelling facility, mobile equipment maintenance facility, primary crusher maintenance facility, washdown facilities, wastewater treatment plant and water infrastructure.

The contract is scheduled to run for approximately 12 months commencing in April 2023 and has an approximate value of A$54 million ($35 million).

NRW’s Managing Director, Jules Pemberton, said: “This is an exciting opportunity as we continue to reinforce our long-term relationship with Rio Tinto through the delivery of world-class, non-process infrastructure, design and construction performed in-house by Primero
Group.”

NRW’s Primero to work on Pilgangoora P680 Expansion Project

NRW Holdings subsidiary, Primero Group, has been awarded a contract by Pilgangoora Operations Pty Ltd, a wholly-owned subsidiary of Pilbara Minerals Limited, for work at the lithium processing plant that is part of the wider Pilgangoora operation, in Western Australia.

The works to be performed under the contract include upgrading the existing Pilgan lithium processing plant through the construction of a new primary rejection facility and preliminary work in connection with a new crushing and ore sorting facility.

Under the contract, Primero will be responsible for detailed earth and concrete works associated with both the primary rejection and crushing and sorting facilities, together with structural, mechanical, piping, electrical and instrumentation installation associated with the primary rejection facility. Primero will also assist with shutdown, brownfield’s integration and commissioning support to tie the facility into the existing Pilgan plant.

The contract is scheduled to run for approximately eight months, commencing in January 2023, and has an approximate value of A$62 million ($44 million).

NRW Managing Director, Jules Pemberton, said: “This contract builds on a long-term association between POPL and Primero that began with Primero’s involvement in the design and construction of the original Pilgan plant. We look forward to the successful completion of these works.”

The construction activities due to take place on the plant are part of the wider P680 Expansion Project Pilbara Minerals is working on. This could see the company step-up its production run-rate at the operation to a total of circa-680,000 t/y of spodumene concentrate across the combined Pilgangoora operation.

NRW Holdings’ Primero to operate and maintain Finniss lithium processing plant

NRW Holdings Limited’s wholly-owned subsidiary, Primero Group, has executed a long term contract for the operations and maintenance (O&M) of Core Lithium’s processing plant and related infrastructure at its Finniss lithium project in the Northern Territory of Australia.

Under the terms of the contract, Primero will operate and maintain the processing and infrastructure facilities at Finniss for an initial term of five years, with option to extend.

The estimated value of the contract is A$60 million ($38 million), and follows on from the current contract in execution for the engineering, procurement and construction (EPC) of Finniss, awarded to Primero in September 2021.

The O&M contract signed between Core Lithium and Primero highlights the unparalleled industry expertise and proven track record in lithium processing and operational excellence outcomes, NRW said.

“Primero continues to grow its portfolio of contract operation and maintenance services across the base and battery metals sectors with a strong track record of delivery and giving customers assurance of safe outcomes, accelerated plant ramp-up, ongoing operational excellence practices, and continuous improvement to achieve cost effective and optimised production outcomes,” it added.

Primero says it has the majority of key personnel on hand for deployment into the contract commencing from October 2022 and expects to complete all remaining recruitment and operational readiness activities by December 2022, ready for first production.

NRW CEO, Jules Pemberton, said: “The diversification of the Primero business into longer term operational contracts is continuing to grow with this award showcasing the depth and operational knowledge of the group, especially within the battery minerals sector. The capability to develop and operate assets of this nature is well aligned with the group’s strategy over the coming years and will continue to evolve with build own operate and equity style investments in projects. We look forward to a long-term relationship with Core Lithium.”

In mid-2021, Core released a definitive feasibility study for the Finniss project, marking a major milestone in its goal to become Australia’s next major lithium producer by the end of 2022.

The study highlighted an average production of 173,000 t/y of high-quality lithium concentrate at a C1 operating cost of $364/t and a start-up capital cost of A$89 million ($56 million) thanks to the incorporation of a 1 Mt/y DMS processing plant in the project’s design.

Golding wins four-year extension at Kogan Creek coal mine

Golding Contractors Pty Ltd has signed a contract with Aberdare Collieries Pty Ltd, a subsidiary of CS Energy Pty Ltd (CS Energy), to extend the current Contract Mining Agreement (CMA) at the Kogan Creek Mine in Queensland, Australia, to beyond June 30, 2022.

Under the terms of the CMA, the term is extended four years until 30 June 2026, with an option for CS Energy to extend the contract for up to another four years, the NRW Holdings subsidiary said. The contract value for the initial four-year extension is around A$150 million ($110 million).

The contract extension represents the third mining contract term and life-of-mine to date for Golding and CS Energy at Kogan Creek, with Golding performing the civil works in 2006 before mining commenced in 2007.

Kogan Creek is an open-cut mine located in the Surat Basin of southern Queensland. The mine supplies the adjacent Kogan Creek Power Station with approximately 2.5 Mt/y of coal. Golding undertook civil works for the initial construction of the mine before becoming the mine operator in 2006.

Under this new arrangement all major plant and equipment will be supplied by Golding requiring a total new capital spend of circa-A$11 million in the first year. All the remaining fleet required is currently operating on site and is Golding owned.

Golding will continue to employ some 70 people at the mine, most of which live in the local Chinchilla or broader southeast Queensland regions. The scope of work includes: mine design and planning, drilling and blasting, overburden and parting removal as well as selective coal mining from over 30 different plies to ensure coal meets strict specifications.

NRW CEO & Managing Director, Jules Pemberton, said: “This extended agreement is the longest continuous contract in Golding’s proud history. Golding has now successfully negotiated four contract extensions with four different clients in the last six months demonstrating the business’ goal to work with our clients to deliver sustained value.”

Primero bags Finniss lithium process plant EPC contract

Core Lithium has awarded Primero Group with the engineering, procurement and construction (EPC) contract for the Finniss lithium process plant in the Northern Territory of Australia.

Primero’s award status has been updated from the initial preferred status awarded in 2019 and continues the long-standing relationship in the development of the project with the Core Lithium team and follows on from the successful delivery of Core’s definitive feasibility study and subsequent study updates, NRW Holdings, the parent company of Primero, says.

The project will commence immediately and is fully funded with site works planned to commence in March 2022 with commissioning of the facility due to commence in October 2022, according to NRW.

Primero’s work on the Finniss dense media separation (DMS) plant will entail project management; engineering and detailed design; equipment and materials procurement; DMS plant construction; quality assurance and construction verification, and ore commissioning on receipt of first ore, according to Core.

Primero Managing Director, Cameron Henry, says: “The Primero brand is synonymous with the processing and operation of battery metals and future energy and the Core Lithium project is another example of the quality of our processing knowledge in these industries. The working relationship with the Core team has been a four-year journey and we look forward to delivering on this contract and continuing the relationship with Core.”

NRW CEO, Jules Pemberton, added: “The NRW Holdings business continues to diversify its business streams into the future metals and energy space with another great award to the Primero Group team in the electric vehicle space with Core Lithium.”

The August definitive feasibility study on Finniss outlined a Stage 1 mine life of eight years with average production of 173,000 t/y at 5.8% Li2O.

Primero rewarded with circa-A$290 million Mt Holland lithium concentrator contract

NRW Holdings’s wholly owned subsidiary Primero Group has been awarded the engineering, procurement and construction (EPC) contract related to the Mt Holland concentrator project in Western Australia for Covalent Lithium, a joint venture between Wesfarmers and SQM.

The Mt Holland project has been worked on in various development phases over the past 18 months between the Covalent and Primero teams, with the planning and works now culminating in the full award of the circa-A$290 million ($214 million) EPC delivery contract, NRW said.

Primero has been awarded the EPC contract that will process ‘run of mine’ ore at a rate of circa 2 Mt/y and produce an output of circa 400,000 t/y of spodumene concentrate to feed the company’s integrated lithium hydroxide conversion refinery situated in Kwinana.

The project scope covers the vertical delivery of engineering design of all disciplines, procurement of all equipment and materials, site construction, commissioning and performance testing of the spodumene concentrator at the Mt Holland site.

The full execution will commence immediately with site works planned to commence in October and an expected peak workforce of 350 personnel, NRW said.

Primero Managing Director, Cameron Henry, said: “The award of the Mt Holland EPC contract is the culmination of an 18-month journey with the Covalent Lithium team and demonstrates the trust and solid working relationship between the groups in the development of the project. This project is not only a flagship project for Primero and our parent company, NRW Holdings, but also a major project for Western Australia and the further development of the state’s battery minerals supply chain.”

NRW CEO, Jules Pemberton, added: “We are pleased to see the continued growth of the Primero business and, in particular, the scale of projects and quality of clients they continue to attract to the group.

“The project has created opportunities for the combined businesses and provides a great platform for other clients to understand the depth, capability and capacity of the group as a whole from early project inception and feasibility through turnkey multi-discipline delivery and further.”

NRW Holdings recently acquired Primero in a cash and shares deal valuing Primero at around A$100 million.

Golding Contractors to keep mining Phosphate Hill operation for another five years

NRW Holdings Ltd’s wholly-owned subsidiary, Golding Contractors, has signed a five-year contract extension with Southern Cross Fertilisers.

The contract with the Incitec Pivot subsidiary means Golding’s mining agreement at Phosphate Hill, in Queensland, Australia, will extend to September 6, 2026.

The expected contract extension value is anticipated to be between A$110-$120 million ($82-89 million) over the term.

Incitec Pivot agreed to purchase Southern Cross Fertilisers, then Australia’s only producer of ammonium phosphate fertilisers, from BHP for A$165 million back in 2006. The operation produced 979,300 t of ammonium phosphates in Incitec Pivot’s 2020 financial year to September 30, 2020.

Golding’s existing mining fleet will continue to operate in the mine and gypsum operations, with new capital spend limited to replacement of select light and medium vehicles, NRW said.

Golding employs around 80 people at the mine that operates on a fly-in fly-out arrangement from Townsville in northern Queensland.

NRW CEO & Managing Director, Jules Pemberton, said: “This contract extension reaffirms the strong relationship Golding has formed with Southern Cross Fertilisers at Phosphate Hill for more than a decade now, under various contract arrangements, and reflects our ability to secure repeat business through the quality and value of our service offering.”