Tag Archives: articulated dump trucks

U.S. Gypsum and Altorfer Cat overcome logistical hurdles in AD30 delivery to Sperry

U.S. Gypsum’s (USG) Sperry mine in Iowa, USA, has added another large piece of Cat equipment to its underground loading and hauling fleet – this time a 30-t payload Cat AD30 underground truck.

Located 192 m below the surface and accessible only by a shaft measuring 1.5 m x 1.8 m, the only way to get the new equipment into the mine was to disassemble, lower and reassemble it underground.

USG has successfully commissioned three Cat® R1600 underground loaders over the last decade, relying on Altorfer Cat, the Cat dealer serving a three-state region that includes the Sperry location near Mediapolis, Iowa.

Several of the Altorfer team members responsible for the first mine transfer of the R1600s were also on hand for the AD30 transfer, including Sales Representative, Jeff Krug, and Field Technician, Chris Wolf.

“Altorfer and United States Gypsum have had a relationship for many years, starting with surface equipment,” Krug says. “When the opportunity to offer Cat mining solutions for their underground equipment materialised, the mine quickly realised there were many of the same components in the underground machines as on the surface. Parts availability and a strong service partnership made it much easier for them to switch to Cat machines.”

Since 1959, the underground Sperry operation has produced gypsum and now produces over 590,000 t/y of raw gypsum. Most of the mine’s gypsum is used in the on-site manufacturing plant, where USG makes Sheetrock® brand wallboard. Gypsum also has medicinal and agricultural uses.

The room and pillar mine has an average ceiling height of about 3 m. Gypsum is mined using the drill and blast method, then the rock is hauled to the mine’s crusher.

“The physical size of the mine has always been a limiting factor for selection of mobile equipment,” Dennis Hollingsworth, former Mine General Foreman, says. “When Cat started producing more underground equipment, it created a new choice for us – first with the R1600s, and now the AD30.”

After the successful implementation of Sperry’s R1600 fleet, Altorfer developed best practices for the mine transfer process that were shared with other dealers around the world. Taking advantage of those lessons learned, the Altorfer team spent several weeks planning and collaborating with the Sperry team before beginning the AD30 transfer.

First, the AD30 arrived at Altorfer’s Cedar Rapids, Iowa, facility, where it was adapted to the specific requirements of the mine. The bed was removed and modified so it could meet the 1.8-m height requirement for loading. In addition, tyres were replaced with a lower profile tyre to meet the maximum height requirement of the mine.

Finally, the machine arrived on the surface of the Sperry mine. Joining Wolf were two Sperry employees who also worked on the R1600 mine transfers: Mine Maintenance Supervisor, Doug Edle, and Technician, A.J. Kuisle.

“Taking the machine apart is the most important part of the process,” Wolf says. “You need to remove things in a precise order, be two to three steps ahead and have a plan for keeping track of everything.”

The team removed the rear axle and all the cooling lines and wiring harnesses from the rear frame, then separated the rear frame from the front frame. Then they tackled the front frame, removing the cab, engine transmission and front axle and lowering them into the mine. Next was the removal of the fire suppression system and wiring harnesses, as well as hoses and valves.

Once everything was removed from the front frame, the team welded on fixtures they would use to line up the frame pieces for reassembly. Then the cutting began, with oxyacetylene torches and an air arc being used to cut the frame into smaller pieces that would fit down the shaft.

Once all the pieces and parts were down the shaft, the AD30 was cleaned and the welding team put the frame back together. Then Wolf and Kuisle got busy reassembling the rest of the machine.

“It took about three weeks to get it back together and running,” Wolf said. “We were very particular to make sure that everything was assembled correctly, that there were no hoses or wires rubbing. Then we started it up and installed the bed and made sure everything was working correctly.”

Hollingsworth is proud of the teamwork involved in the machine transfer. “Getting new equipment underground has always been a challenge,” he says “Bringing a new piece of equipment underground and re-assembling it has always been a process that our mechanics take pride in being able to accomplish. Chris Wolf has a been a part of that process four times now, and I think, feels the same way. He has done a great job helping with the teardown and reassembly of all four Cat machines.”

Altorfer’s role in the life of the new AD30 didn’t stop once the machine was assembled underground. Before handing off the keys, the team took it for a test drive. When the testing was complete, Wolf provided training to the employees who would be operating the new truck.

“The training process went well,” Hollingsworth says. “Chris came in on both shifts and trained all of the operators. It’s something we’ve come to expect from Altorfer that we don’t typically get from other manufacturers.”

And finally, about four-and-a-half weeks after the mine transfer process began, the AD30 went to work.

Hollingsworth said the mine’s satisfaction with its Cat R1600s, the long life and rebuildability of Cat machines, and the quality of Altorfer’s service all contributed to the decision to purchase the AD30. “The AD30 has been a great addition to the mine fleet,” he says. “The truck is running great. The operators took to it quickly. They like the way it drives and performs.”

Just like Sperry mine’s other Cat equipment, the new machine will be supported throughout its life by Altorfer, with more new Cat machines continuing to join the mine’s fleet in the years to come.

Hyundai Construction Equipment to enter the ADT market with 30- and 45-t models

Hyundai Construction Equipment (HCE) is set to display 23 machines at bauma 2022 in Munich, in October, with some of the key highlights being a new ADT and a concept hydrogen vehicle.

The company’s stand is 30% larger than in previous years, representing the ongoing growth journey it is on.

HCE’s stand will reveal Hyundai’s position as a technology leader, with a clear roadmap to a cleaner, safer and more productive construction site, whatever the industry sector, it said.

The entry of the company into the articulated dump truck (ADT) market involves the launch of two models, using proven, innovative design and technology to deliver high productivity and superior mobility on site, the company says.

Aimed at the 30-t and 45-t sectors, the HA30A and HA45A are built around a full-time six-wheel drive concept, with front and rear limited slip differentials and a longitudinal differential than can be manually locked, for maximum drive and traction on difficult terrain.

The two ADTs are the first visible sign of the new cooperation between Hyundai Construction Equipment Europe (HCEE) and Hyundai Doosan Infracore (HDI), since the purchase of the Doosan business last year by Hyundai Heavy Industries Group.

The HW155H concept wheeled excavator, powered by a hydrogen fuel cell, meanwhile, features a 14-t payload that can offer eight hours of operation with a 20-minute refuelling time, according to the company. It is based on proven hydrogen commercial vehicle technology, according to the company, with the only emission from the machine being water.

The trucks have a compact chassis design to aid manoeuvrability, with a sloping rear frame and a front-mounted differential integrated into the ZF transmission, allowing for a shorter front frame section.

This, the company says, results in the smallest turning radius in the sector and outstanding stability.

Self-levelling hydro-gas suspension on the front axle further supports a comfortable ride, delivering maximum tractability in tough ground conditions, it said. The turning ring is mounted in front of the chassis articulation point, resulting in an equal weight distribution to the front wheels in all driving situations for increased stability and traction.

Having equal weight distribution allows the operator to use the limited slip differentials with just a 45° locking value, maintaining drive to both front wheels even when steering. The two rear axles employ a tandem bogie drive design, with a single central differential and twin internal gear drives on each side of the truck. These tandem reduction gearboxes rotate in total by almost 40°, allowing maximum oscillation of the rear axles to maintain ground contact on rough terrain, the company said. The single central differential increases ground clearance beneath the truck.

The HA30A and HA45A are equipped with a full hydraulic retarder, combined with an electronic engine brake as standard. This supports the oil-cooled wet disc brakes to achieve an extended service lifetime of up to 15,000 hours. A hydraulically-activated mechanical parking brake, meanwhile, holds the machine when stationary.

The trucks are supplied with a gradient meter, with flip-over protection and a Body Over Centre of Gravity function, to assist drivers when tipping and operating on rough terrain. The sloping rear chassis section evenly spreads the load between the front and rear axles.

The HA30A has a 16.8 cu.m heaped body capacity that rises to 17.8 cu.m with a tailgate fitted. The larger HA45A offers a 24.4 cu.m heaped capacity, rising to 26 cu.m with a tailgate.

Both dump bodies can be optionally heated by the engine exhaust gases to prevent freezing and sticking of materials when operating in colder temperatures. Internal wear plates are available as an option for hard rock use.

Hyundai has employed powerful EU Stage V-compliant Scania diesel engines to power both trucks. The HA30A uses a five-cylinder, 9.3-litre, DC9 turbocharged diesel, developing 276 kW and 1,876 Nm of torque. The larger HA45A employs a six-cylinder, 12.7-litre DC13 diesel engine, producing a maximum 368 kW and 2,476 Nm of torque. Both engines drive through eight-speed ZF automatic transmissions, with integrated retarders.

The torque converter has lock-up in all gears, reducing fuel consumption and increasing efficiency. Fuel, AdBlue diesel engine exhaust fluid and a standard auto-lube greasing system can all be easily accessed from ground level, for improved site safety. The engine canopy tilts forward for access to filters and fill points, while the complete cab structure can also be tilted towards the rear of the truck to provide access for repair and maintenance.

Hyundai’s Himate telematic monitoring system is standard, with satellite and GSM connectivity, to reach the most inaccessible construction and mining sites across the world. This allows customers to remotely monitor productivity, fuel consumption, system warning and maintenance status, reducing unplanned downtime and improving fleet utilisation.

With the most spacious ROPS/FOPS cab on the market, the Hyundai ADT features an ergonomic layout to the controls, which are easily reached from the high-quality air-suspended operator’s seat.

There is plenty of storage around the cab interior, with room for an optional cool/hot box and 12 V power sockets for operator phones and other accessories. Full cab climate control is standard on both models and the cab boasts an internal sound level of just 72 dB(A) for maximum comfort throughout the working day, the company says.

The sloping bonnet provides an excellent view to the front of the truck and there are sliding side windows with hand rails to the side of the seat. A comprehensive monitor panel provides an integrated payload meter, to prevent overloading and to record productivity. Diagnostic functions are included within the monitoring system and the operator can remotely check hydraulic and transmission oil levels from the cab.

A gradient metre ensures that the truck is driven safely within its limits, while an integrated rear-view camera and large mirrors provide excellent all-round visibility, when reversing under an excavator or into the tipping area, the company claims.

The Hyundai HA30A and HA45A articulated dump trucks provide an ideal excavating partner for a wide range of crawler excavators and wheeled loading shovels, according to the company. Designed primarily for major earthmoving and muck shifting projects, highways construction and mine and quarry operations, Hyundai’s articulated haulers provide maximum drive and traction in the worst site conditions, maintaining all-year round productivity for the customer, it says.

Terex Trucks to launch EU Stage V TA300, TA400 ADTs at Hillhead Digital

Terex Trucks is readying the launch of new EU Stage V versions of its TA300 and TA400 articulated haulers for the fast-approaching Hillhead Digital event.

The machines have been updated with an EU Stage V emission-compliant engine – and now deliver an improvement in fuel efficiency, an even stronger performance, as well as low total cost of ownership, the company says.

Both haulers come with a reduction of up to 7% in fuel consumption when compared with the Stage IV engine, according to Terex Trucks. Customers in Europe will also benefit from the haulers’ strong engine performance and excellent responsive power in all conditions.

Equipped with a Variable Geometry Turbo, the new Stage V engine allows for faster response at all engine speeds and an efficient combustion performance, according to the company. This helps improve operators’ efficiency while keeping the total cost of ownership low.

The TA300 and TA400 Stage V engine’s effective aftertreatment system uses selective catalytic reduction technology, removing the need for exhaust gas recirculation. This way, no exhaust gas is returned to the combustion chamber of the engine, helping to improve efficiency and durability of the machine. The diesel oxidation catalyst and a large-capacity diesel particulate filer ensure the engine meets the latest EU emission standards.

Kenny Price, Regional Sales Manager for EMEA at Terex Trucks, said: “Introducing the Stage V compliant engine for the TA300 and TA400 is part of our focus on delivering efficient, productive, high-quality and durable articulated haulers, while keeping the total cost of ownership down.

“We’re excited about presenting the new Stage V haulers to customers at Hillhead Digital.”

Just like the Terex Trucks Stage IV haulers, the new Stage V TA300 and TA400 are equipped with Scania DC9 and DC13 engines. Thanks to a drivetrain that is matched with the engine, the trucks deliver a powerful performance and excel in demanding work environments. For heightened levels of operational safety and control, an engine exhaust brake is installed as standard, which also reduces brake component wear.

The haulers also come with three-stage aspirated air filtration, which provides increased engine protection to lengthen maintenance intervals. All of this helps deliver strong, durable engine performance and keeps the total cost of ownership low.

The new Stage V TA300 and TA400 engines are also linked to Terex Trucks’ Haul Track telematics system, which allows customers to have visibility and control of the haulers, according to the company. They can access machine GPS location and tracking together with a range of downloadable daily performance reports such as machine hours worked, engine speed, idle time and system fault code alerts. This helps customers to plan maintenance more efficiently, maximises uptime and prolongs component lifecycles.

The first Stage V 28-t-payload TA300 and 38-t-payload TA400 are already rolling off the production line and will be delivered to the first customers in Europe from March, according to Terex Trucks.

Terex Trucks will present its new EU Stage V emission-compliant TA300 and TA400 dump trucks at the Hillhead Digital 2021 exhibition from March 30-31.