Tag Archives: Copiapó

Pucobre takes the rapid mine development route with Epiroc

Faced with the challenge of boosting productivity and lowering costs, Chile-based copper miner Pucobre has teamed up with Epiroc to implement the first Rapid Mine Development (RMD) project in the country.

Combining technology and changes in mindset to build high-quality mine infrastructure, the company is now on a path to become a 4.0 mine, Epiroc says.

In 2016, Pucobre, a selective underground copper mining company, was faced with a conundrum: grades at its deposits were falling, and global red metal prices were unstable.

The company knew it needed to change to remain competitive and began looking for ways of working that were more productive, efficient and cost effective. That is when the idea of Rapid Mine Development (RMD) appeared on the horizon, Epiroc said.

“RMD is a method for making higher-quality tunnels, faster in the underground mine development cycle,” it said. “What previously depended largely on the skill and experience of the drill operator and explosives technician are now computer-supported tools for standardisation and optimisation.

“For Pucobre, RMD has meant not only a change in technology but also a cultural change oriented toward quality and discipline.”

The project started as part of a strategic partnership with Epiroc, unique in Chile, which commenced with a contract in 2017 to replace Pucobre’s truck and loader fleet with Minetruck MT65 trucks and Scooptram ST18 loaders, vehicles with higher capacity.

The partnership was unique because it guaranteed the mechanical operability of the equipment over its working lifetime, Epiroc said. This is nine years in the case of the trucks, and 5-6 years for the loaders. The previous vehicles used by Pucobre had to be changed every 2-3 years, which led to the first in many steps of change management for Pucobre, with more focus on complete maintenance of the vehicles to ensure their longevity.

On its premises in Atacama desert, Pucobre set up a training centre with simulators to instruct drivers how to handle these new vehicles, installed a maintenance workshop, and had Epiroc staff permanently on site to jointly solve problems that might arise. Encouraged by this experience, Pucobre and Epiroc began to explore new ways to streamline the operation.

Sebastián Ríos (pictured below), CEO of Pucobre, said: “Epiroc has always shown a great disposition for solving problems and working to ensure that the trucks and loaders are successful.”

According to Marco Troncoso, Pucobre’s Mining Operations Head, before embarking on RMD, the company’s way of working was “very dependent on specific skills of its people”, with Pucobre keen to leverage technology and improve the efficiency of its workers.

Troncoso said: “Epiroc said to us: ’let us help you build the new house in which you will live for the next 30 years.’ Once you get used to doing things in a quality way, the results improve.”

Epiroc visited Pucobre’s three site operations near the northern city of Copiapó, and Pucobre came up with a three-year development plan (2019-2021) to boost productivity by 40% and reduce costs by 25%.

Pucobre and Epiroc went on site visits to Australia, Nevada (USA), Sweden and Canada where the company could see leading mining companies using Boomer face drilling rigs in action, as well as the new concepts of mine management, which would also be adopted.

Two alternatives were proposed to help Pucobre meet its goals. One was to use multi-role face drills, like in Australia, which combine blasthole drilling and rock reinforcement such as scaling, bolting and meshing in a single rig. The other alternative was RMD, a method which promises longer rounds, higher accuracy, reduced overbreak and better quality tunnels, Epiroc said.

“Most importantly, with the latest Boomer S2 rigs – equipped with ABC Total, a smart function that allows for complete automation of the drilling process – RMD offered a path that would enable the machinery to operate autonomously during lunch breaks and shift changes, thereby resulting in more productivity gains,” the company said.

Once Pucobre had opted for RMD, the company invested in four of the latest Boomer face drilling rigs and three Simba production drill rigs. To monitor development and meet key performance indicators, Pucobre went digital, building a new Mining Operations Centre on site. In the future, the company is expected to deploy Epiroc’s 6th Sense Mine Management Solution, which combines the Mobilaris scheduler and other task management and reporting features, as well as the Certiq telematics solution, which gathers, compares and communicates vital equipment information to the surface.

Investing in and betting on RMD has meant a major leap of faith on the part of Pucobre. The total investment over the nine-year contract period is likely to reach $60-70 million, factoring in machinery, spare parts and technology. There have also been major time investments in training and change management.

Ríos said: “This is the biggest change in Pucobre in the last 30 years.”

A big challenge for Pucobre was the increased development rates over the coming years, which came with a significant cost increase. Cost estimations prior to project start showed significant cost savings by using RMD to prevent this.

So, the alternative – to keep doing things the way they had before – was not compelling. According to Epiroc’s calculations, without RMD, Pucobre’s annual development costs would have increased 3%/y from $25.5 million in 2019 to $27 million in 2022. With RMD, development costs are projected to fall to $21.3 million in 2022.

Change management has been the other major challenge on this journey, adapting attitudes and skill sets to the new ways of working. Pucobre introduced Short Interval Control (SIC), which is a structured process that measures short intervals of production to identify opportunities for improvement.

To manage the operation, it is necessary to have as much information online as possible, such as the location of vehicles and work plans for the day, so that personnel in the Mining Operations Centre can make decisions and improve productivity.

Ríos said: “The engineering department had to modify how it plans, now with shorter intervals. What was previously done in the field now has to be carefully planned and coordinated before it is executed.”

Cultural differences between the Swedish and Chilean way of doing things have required compromises on both sides and commitment and team work to make this unique joint venture successful.

The RMD project at Pucobre is being implemented in four stages. After getting used to using standardised, computerised drill plans using navigation methods, the project has now moved to a second stage – to optimise the machinery to extend explosive rounds to 4.4 m, from 3.8 m. The goal is to reach 95% of the blasting target with less than 5% underbreak or overbreak and to increase development rates from 1,100 m/mth to 1,400 m/mth.

Stage 3 is continuous improvement, leveraging reported data from the rigs to correct divergence using Rig Remote Access (RRA), which enables two-way communication between the drill and the RRA server using the site W-LAN wireless network.

But the principal objective is to reach stage 4, where drills can operate autonomously during lunch and shift breaks using the ABC Total smart function.

Progress has been fast, according to Hilario Arce, Head of Pucobre’s mining operations. With the Minetruck MT65 trucks and Scooptram ST18 loaders, Pucobre has already increased its monthly mineral extraction to 460,000 t, from 333,000 t previously. Two of the three mining sites are now operating 100% RMD, the third one is coming soon. Operators are getting close to the 95% blasting target, and Arce is confident 60-70% of drilling will be automated come March 2021.

The Epiroc Simba 7 long-hole rigs are the most advanced to date in Punta del Cobre in terms of the use of ABC Total, but the system will start implementation in Boomer rigs in December.

Working closely together has been key for Epiroc to build trust, says Charlie Ekberg, General Manager of Epiroc Chile, who underscores that demonstrating success with Pucobre will be key for winning similar projects elsewhere in Chile. Epiroc is also betting on introducing teleremote technology for mine loaders and battery-powered trucks in Chile next year.

“That’s why we put so much effort into training,” Ekberg said. “It’s not just about selling the machine. We want the equipment to work and, if a machine is standing idle, we want to know why. We’ve had to learn how the customer thinks and always be one step ahead.”

In terms of results and costs of the overall project, Pucobre is still only halfway to where it wants to be, according to Ríos. But he knows Pucobre is on the right path.

He said: “There are still gaps. Sometimes the trucks aren’t loading to their full capacity, or the loading cycle and return to the surface is taking longer than planned. That equation still has room for improvement.”

It has been a learning experience for both Epiroc and Pucobre. Overly ambitious KPIs and targets set at the beginning have had to be modified to suit the pace of progress and time needed to train with this new way of doing things. That is where change management has been one of the biggest challenges.

“There are many things that change in the day-to-day operation,” Ríos said. “You contract new people, new technology, there is a change in planning. You have to look at the way that people adapt to this new way of working.

“You have to support people in this process so that it flows with the help of the human resources department. Change is difficult. It’s like working from home, which many people have done this year. You have to manage it well, for it to be successful. We trust our people will do it.”

This first appeared as an Epiroc customer story here.

Rio2 and STRACON establish mining and construction alliance for Fenix gold project

Rio2 Ltd says it has taken another key step towards the development of its Fenix gold project, in Chile, by selecting STRACON SA as the lead mining services contractor for the project.

Both companies have executed an early contractor involvement (ECI) agreement for early works associated with contract mining services. Under the ECI agreement, the parties will work exclusively over the coming months to further optimise the mining and civil construction aspects of the project and conclude contract documentation.

The scope of the mining services contract will include mining of ore at the rate of 7.3 Mt/y (20,000 t/d), waste mining, drilling, blasting, hauling, supply of operating personnel and mining equipment, supervision and management, dust suppression and road maintenance. The scope also includes water transportation from Copiapó to the mine site and maintenance of the entire mobile fleet of equipment plus all pre-mining and civil construction activities including the construction of platforms, leach pad, ponds, access roads and waste material deposits.

The financial terms of the mining contract will use an alliancing-style commercial framework based on the mine plan, methodologies and productivity estimate assumptions contained in the prefeasibility study, which outlined a heap leach gold mine producing an average of 93,000 oz/y during the first 13 years and 50,000 oz/y during the final three years of production as stockpiled ore is being crushed and leached.

The environmental baseline study for the Environmental Impact Assessment (EIA) of the Fenix gold project has been progressing since November 2018. During 2019, engineering works and studies were completed for inclusion in the EIA. In January 2020, the information gathering stage for the baseline study was finalised, with the EIA completed and filed with the Environmental Impact Assessment System in the March quarter. Environmental approval is expected in the June quarter of 2021.

The preparation of sectorial permit applications is currently in process and will be submitted in conjunction with the filing of the EIA. The approval of sectorial permits is expected in the September quarter of 2021 and the start of earthworks for construction of the project is targeted for the December quarter of 2021.

The basis for Rio2 establishing a mining and construction alliance with STRACON at the Fenix gold project is a best for project business strategy, the company said. Together with STRACON, the Rio2 management team collaborated, implemented and executed with this same approach when they built and operated the La Arena and Shahuindo gold mines in Peru with Rio Alto Mining.

At Fenix, Rio2 and STRACON will work together as an integrated team, dedicated to exceeding goals, controlling budgets and adding value through exceptional performance while working in a safe and environmentally sustainable manner focused on every detail of the mining and construction process, Rio2 said.

“The alliance will implement an inclusive social policy as a priority based on the hiring of local personnel and service companies from Copiapó and the Atacama Region,” it added.

The payment model of an alliance includes reimbursement of 100% of contractor project costs plus a fee (corporate overheads and profit); a key performance indicator-based regime that rewards for outstanding performance and punishes poor performance; and unanimous, best for project, management and decision making and the selection of an integrated owner/contractor team on the basis of best person for each position and avoiding duplication of roles, Rio 2 said.

Alex Black, President and CEO of Rio2, said: “The signing of this ECI agreement with STRACON, a leading mining and civil construction contractor in Latin America, forms a key part of Rio2’s strategy to prepare for next year’s construction phase of our Fenix gold project.

“The Rio2 management team is pleased to work again with STRACON, this time in Chile, and look forward to further optimising the mining and construction solution for the project and finalising contract documentation in readiness for next year’s work program.”

Steve Dixon, Chief Executive Officer of STRACON, said: “The project will be delivered under a collaborative alliance agreement, a framework which has been successfully utilised over the past 10 years at several of STRACON’s projects throughout Latin America.”

FLSmidth responds to north Chile mining demand with opening of new service centre

FLSmidth says it has launched a new service centre for customers in the north of Chile focused on timely delivery of mining equipment to customers and component maintenance.

The opening event, held last week, was attended by a number of key customers and representatives from local authorities, according to FLSmidth.

The 8,000 m² facility, in Copiapó, is geared towards meeting the high demand for mining service and technical support in the region.

FLSmidth said: “The service centre has a primary emphasis on supplying solutions that extend the asset’s life cycle, such as repairs and rebuilds; equipment and components upgrades; parts and consumables strategic stocking programs; tailored training programs; technical assistance; and customised service packages.”

The facility ensures customers receive the required knowhow to optimise their operations, as well as support when it comes to inspections, process audits and technical issues, the company added.

Andrés Costa, President FLSmidth South America, said: “This is a significant milestone for the company, since Copiapó represents an important part of our operations in Chile. The huge mining industry potential in the area and our large installed base requires an infrastructure like this so we can work closer with our customers, get to know their challenges and deliver sustainable productivity solutions to their operations.”

Carlos Sagredo, Plant Manager North Chile, said: “This new service centre will deliver extra availability and reliability to our customers, improving their productivity and uptime, reducing total cost of ownership and extending their equipment lifespan.”

Copiapó Service Center joins other FLSmidth service facilities in South America region, such as São Paulo (Brazil), Arequipa (Peru), Iquique, Antofagasta and Santiago (Chile).